2010 E 112TH ST 90059

Certificate Information: 2010 E 112TH ST 90059

Application / Permit
23014-10000-02206
Plan Check / Job No.
B23LA10277
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
21'-8" X 17'-0" ADDITION AND CONVERT EXISTING GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d)- PER ENGINEER
Permit Issued
Issued on 8/11/2023
Issuing Office
Current Status
CofO Issued on 5/7/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/3/2023 APPLICANT
Assigned to Plan Check Engineer 6/8/2023 DANIEL ABRAMYAN
Corrections Issued 6/8/2023 DANIEL ABRAMYAN
Plan Check Approved 8/9/2023 DANIEL ABRAMYAN
Issued 8/11/2023 APPLICANT
CofO in Progress 3/23/2026 ARTHUR NEGRETE
Permit Finaled 5/7/2026 ANSON MAGLASANG
CofO Issued 5/7/2026 ANSON MAGLASANG
Permit Finaled 5/7/2026 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 7/14/2023 NEIL TUANO
Eng Process Fee Ord 176,300 Cleared 7/14/2023 NEIL TUANO
Roof/Waste drainage to street Cleared 7/14/2023 NEIL TUANO
Sewer availability Cleared 7/14/2023 NEIL TUANO

Contact Information

Contractor Owner-Builder       ,
Engineer Gao,, Jianfeng; Lic. No.: C88478 18825 ELMHURST ST      ROWLAND HEIGHTS, CA 91748

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/11/2024 Corrections Issued BEN MOLSTAD
PLUMBING-Rough 4/16/2024 Partial Approval BEN MOLSTAD
Deputy Drilled-In Anchors 4/18/2024 Conditional Approval BEN MOLSTAD
Excavation/Setback/Form/Re-Bar 4/22/2024 Corrections Issued BEN MOLSTAD
Footing/Foundation/Slab 4/22/2024 Corrections Issued BEN MOLSTAD
Deputy Drilled-In Anchors 5/6/2024 Partial Approval EUGENE CASSIDY
Footing/Foundation/Slab 5/6/2024 Corrections Issued BEN MOLSTAD
Footing/Foundation/Slab 5/13/2024 Partial Approval BEN MOLSTAD
Deputy Drilled-In Anchors 5/20/2024 Conditional Approval BEN MOLSTAD
Underground Mechanical 5/22/2024 Partial Approval BEN MOLSTAD
Footing/Foundation/Slab 5/23/2024 Approved BEN MOLSTAD
Floor/Roof Diaphrgm/Shear Wall 10/29/2024 Corrections Issued ANTHONY EGSON
BUILDING-Rough-Frame 6/18/2025 Approved JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 6/18/2025 Approved JOHN KLARIN
Rough-Elec/Plmb/HVAC 6/18/2025 Approved JOHN KLARIN
Insulation 6/23/2025 Corrections Issued EUGENE CASSIDY
Interior/Exterior Lathing 6/23/2025 Partial Approval EUGENE CASSIDY
Drywall Nailing 6/27/2025 Corrections Issued JOHN KLARIN
Drywall Nailing 7/1/2025 Approved JOHN KLARIN
Final 2/26/2026 Corrections Issued ARTHUR NEGRETE
SGSOV-Seismic Gas S/O Valve 2/26/2026 SGSOV Not Required ARTHUR NEGRETE
Smoke Detectors 2/26/2026 Approved ARTHUR NEGRETE
ELECTRICAL-Final 3/20/2026 Approved ARTHUR NEGRETE
Final 3/20/2026 OK to Issue CofO ARTHUR NEGRETE
HVAC-Final 3/20/2026 Approved ARTHUR NEGRETE
PLUMBING-Final 3/20/2026 Approved ARTHUR NEGRETE
Service/Power Release 3/20/2026 Approved ARTHUR NEGRETE