644 E 76TH ST 90001

Certificate Information: 644 E 76TH ST 90001

Application / Permit
23014-10000-02199
Plan Check / Job No.
B23LA10227
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
22'-4"x26'-4" ADDITION AT REAR OF (E) 1 STORY SINGLE FAMILY DWELLING PER WFPP. "COMPLY WITH DEPARTMENT ORDER effective date 02/13/2015. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 1/19/2024
Issuing Office
Metro
Current Status
CofO Issued on 4/1/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/2/2023 APPLICANT
Assigned to Plan Check Engineer 6/8/2023 SAMUEL GONZALEZ
Corrections Issued 6/10/2023 SAMUEL GONZALEZ
Building Plans Picked Up 6/16/2023 APPLICANT
Applicant returned to address corrections 7/5/2023 JOSEPH RAFOLS
Plan Check Approved 7/27/2023 AUNG SOE
Issued 1/19/2024 APPLICANT
CofO in Progress 8/14/2025 DANIEL GUEVARA
Permit Finaled 4/1/2026 CLAUDIO MORENO
CofO Issued 4/1/2026 CLAUDIO MORENO
Permit Finaled 4/1/2026 CLAUDIO MORENO

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 7/5/2023 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 7/6/2023 TREVOR QUAN
Community Plan Implem. Overlay Cleared 7/26/2023 HELEN JADALI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEREMY TODD, (213) 978-4495 Office Hours: 7:00-8:00 AM MON-FRI
MARVIN FONSECA, (213) 978-4495 Office Hours: 7:00-8:00 AM MON-FRI
DANIEL GUEVARA, (213) 978-4495 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 5/1/2024 Not Ready for Inspection DANIEL GUEVARA
Green Building Rough 5/1/2024 Not Ready for Inspection DANIEL GUEVARA
Excavation/Setback/Form/Re-Bar 5/21/2024 Approved DANIEL GUEVARA
BUILDING-Rough-Frame 9/11/2024 Not Ready for Inspection DANIEL GUEVARA
Drywall Nailing 9/11/2024 Not Ready for Inspection DANIEL GUEVARA
ELECTRICAL-Rough 9/11/2024 Corrections Issued DANIEL GUEVARA
Final 9/11/2024 Not Ready for Inspection DANIEL GUEVARA
Footing/Foundation/Slab 9/11/2024 Not Ready for Inspection DANIEL GUEVARA
Green Building Final 9/11/2024 Not Ready for Inspection DANIEL GUEVARA
HVAC-Rough 9/11/2024 Approved DANIEL GUEVARA
Pre-Inspection 9/11/2024 Approved DANIEL GUEVARA
SGSOV-Seismic Gas S/O Valve 9/11/2024 SGSOV Not Ready DANIEL GUEVARA
ELECTRICAL-Rough 9/24/2024 Approved DANIEL GUEVARA
PLUMBING-Rough 9/24/2024 Approved DANIEL GUEVARA
BUILDING-Rough-Frame 10/30/2024 Approved DANIEL GUEVARA
Floor/Roof Diaphrgm/Shear Wall 10/30/2024 Approved DANIEL GUEVARA
Green Building Rough 10/30/2024 Approved DANIEL GUEVARA
Insulation 10/30/2024 Approved DANIEL GUEVARA
Footing/Foundation/Slab 12/13/2024 Approved DANIEL GUEVARA
SGSOV-Seismic Gas S/O Valve 12/13/2024 SGSOV Approved DANIEL GUEVARA
Drywall Nailing 12/20/2024 Approved DANIEL GONZALEZ
Interior/Exterior Lathing 12/20/2024 Approved DANIEL GONZALEZ
ELECTRICAL-Final 2/7/2025 Approved DANIEL GUEVARA
Final 2/7/2025 Partial Approval DANIEL GUEVARA
Green Building Final 2/7/2025 Approved DANIEL GUEVARA
HVAC-Final 2/7/2025 Approved DANIEL GUEVARA
PLUMBING-Final 2/7/2025 Approved DANIEL GUEVARA
Smoke Detectors 2/7/2025 Approved DANIEL GUEVARA
Final 8/14/2025 OK to Issue CofO DANIEL GUEVARA