644 E 76TH ST 90001
Certificate Information: 644 E 76TH ST 90001
- Application / Permit
- 23014-10000-02199
- Plan Check / Job No.
- B23LA10227
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 22'-4"x26'-4" ADDITION AT REAR OF (E) 1 STORY SINGLE FAMILY DWELLING PER WFPP. "COMPLY WITH DEPARTMENT ORDER effective date 02/13/2015. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 1/19/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/1/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/2/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/8/2023 | SAMUEL GONZALEZ |
| Corrections Issued | 6/10/2023 | SAMUEL GONZALEZ |
| Building Plans Picked Up | 6/16/2023 | APPLICANT |
| Applicant returned to address corrections | 7/5/2023 | JOSEPH RAFOLS |
| Plan Check Approved | 7/27/2023 | AUNG SOE |
| Issued | 1/19/2024 | APPLICANT |
| CofO in Progress | 8/14/2025 | DANIEL GUEVARA |
| Permit Finaled | 4/1/2026 | CLAUDIO MORENO |
| CofO Issued | 4/1/2026 | CLAUDIO MORENO |
| Permit Finaled | 4/1/2026 | CLAUDIO MORENO |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 7/5/2023 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 7/6/2023 | TREVOR QUAN |
| Community Plan Implem. Overlay | Cleared | 7/26/2023 | HELEN JADALI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEREMY TODD, (213) 978-4495 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARVIN FONSECA, (213) 978-4495 | Office Hours: 7:00-8:00 AM MON-FRI |
| DANIEL GUEVARA, (213) 978-4495 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 5/1/2024 | Not Ready for Inspection | DANIEL GUEVARA |
| Green Building Rough | 5/1/2024 | Not Ready for Inspection | DANIEL GUEVARA |
| Excavation/Setback/Form/Re-Bar | 5/21/2024 | Approved | DANIEL GUEVARA |
| BUILDING-Rough-Frame | 9/11/2024 | Not Ready for Inspection | DANIEL GUEVARA |
| Drywall Nailing | 9/11/2024 | Not Ready for Inspection | DANIEL GUEVARA |
| ELECTRICAL-Rough | 9/11/2024 | Corrections Issued | DANIEL GUEVARA |
| Final | 9/11/2024 | Not Ready for Inspection | DANIEL GUEVARA |
| Footing/Foundation/Slab | 9/11/2024 | Not Ready for Inspection | DANIEL GUEVARA |
| Green Building Final | 9/11/2024 | Not Ready for Inspection | DANIEL GUEVARA |
| HVAC-Rough | 9/11/2024 | Approved | DANIEL GUEVARA |
| Pre-Inspection | 9/11/2024 | Approved | DANIEL GUEVARA |
| SGSOV-Seismic Gas S/O Valve | 9/11/2024 | SGSOV Not Ready | DANIEL GUEVARA |
| ELECTRICAL-Rough | 9/24/2024 | Approved | DANIEL GUEVARA |
| PLUMBING-Rough | 9/24/2024 | Approved | DANIEL GUEVARA |
| BUILDING-Rough-Frame | 10/30/2024 | Approved | DANIEL GUEVARA |
| Floor/Roof Diaphrgm/Shear Wall | 10/30/2024 | Approved | DANIEL GUEVARA |
| Green Building Rough | 10/30/2024 | Approved | DANIEL GUEVARA |
| Insulation | 10/30/2024 | Approved | DANIEL GUEVARA |
| Footing/Foundation/Slab | 12/13/2024 | Approved | DANIEL GUEVARA |
| SGSOV-Seismic Gas S/O Valve | 12/13/2024 | SGSOV Approved | DANIEL GUEVARA |
| Drywall Nailing | 12/20/2024 | Approved | DANIEL GONZALEZ |
| Interior/Exterior Lathing | 12/20/2024 | Approved | DANIEL GONZALEZ |
| ELECTRICAL-Final | 2/7/2025 | Approved | DANIEL GUEVARA |
| Final | 2/7/2025 | Partial Approval | DANIEL GUEVARA |
| Green Building Final | 2/7/2025 | Approved | DANIEL GUEVARA |
| HVAC-Final | 2/7/2025 | Approved | DANIEL GUEVARA |
| PLUMBING-Final | 2/7/2025 | Approved | DANIEL GUEVARA |
| Smoke Detectors | 2/7/2025 | Approved | DANIEL GUEVARA |
| Final | 8/14/2025 | OK to Issue CofO | DANIEL GUEVARA |