17410 W GILMORE ST 91406
Certificate Information: 17410 W GILMORE ST 91406
- Application / Permit
- 23014-10000-02170
- Plan Check / Job No.
- B23LA10133
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- GROUND FLOOR ADDITION TO (E) 1-STORY SFD AND COVERED PATIO ADDITION PER IB 2020-006 ALL CONSTRUCTION PER WFPP.
- Permit Issued
- Issued on 1/23/2024
- Issuing Office
- Metro
- Current Status
- Issued on 1/23/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/1/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/15/2023 | VIVIAN LAO |
| Corrections Issued | 6/21/2023 | VIVIAN LAO |
| Quality Review Completed | 6/26/2023 | KEN GILL |
| Building Plans Picked Up | 7/11/2023 | APPLICANT |
| Plan Check Approved | 1/17/2024 | VIVIAN LAO |
| Issued | 1/23/2024 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 8/24/2023 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 9/1/2023 | CARLOS AGUILERA |
| ZI | Cleared | 9/8/2023 | DANIEL CORONADO |
| Construction near power lines | Cleared | 12/1/2023 | RIDWAN HARDY |
| Construction within easement | Cleared | 12/1/2023 | RIDWAN HARDY |
| Sewer availability | Cleared | 12/5/2023 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| BUILDING-Rough-Frame | 6/11/2026 |
| PLUMBING-Rough | 6/11/2026 |
| ELECTRICAL-Rough | 6/11/2026 |
| Green Building Rough | 6/11/2026 |
Inspection Request History
| Pre-Inspection | 1/28/2025 | Partial Inspection | MORRIS JACKSON |
| Excavation/Setback/Form/Re-Bar | 5/1/2026 | Partial Approval | SEAN WIRCH |
| Footing/Foundation/Slab | 5/1/2026 | Corrections Issued | SEAN WIRCH |
| PLUMBING-Rough | 5/1/2026 | Partial Approval | SEAN WIRCH |
| BUILDING-Rough-Frame | 6/4/2026 | Corrections Issued | JON MCHUGH |
| Footing/Foundation/Slab | 6/4/2026 | Not Ready for Inspection | JON MCHUGH |
| Green Building Rough | 6/4/2026 | Not Ready for Inspection | JON MCHUGH |