2210-2212 S BEVERWIL DR 90034
Certificate Information: 2210-2212 S BEVERWIL DR 90034
- Application / Permit
- 23014-10000-02153
- Plan Check / Job No.
- B23LA10074
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION ADN REMODEL TO THE EXISTING SFD. REPLACEMENT ROOF. IMPROVEMENT BACKAYRD LANDSCAPE INMPROVEMENT CONVERTING (E) ATTACHED 2 CAR GARAGE INTO JADU BUILDING TO BE FULLY SPRINKLERED NFPA- 13D
- Permit Issued
- Issued on 12/27/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/3/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/31/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/1/2023 | RACHEL BEYENE |
| Corrections Issued | 6/6/2023 | RACHEL BEYENE |
| Quality Review Completed | 6/9/2023 | KEN GILL |
| Applicant returned to address corrections | 7/13/2023 | RACHEL BEYENE |
| Applicant returned to address corrections | 7/24/2023 | RACHEL BEYENE |
| Applicant returned to address corrections | 7/27/2023 | RACHEL BEYENE |
| Applicant returned to address corrections | 9/6/2023 | RACHEL BEYENE |
| Building Plans Picked Up | 9/12/2023 | APPLICANT |
| Applicant returned to address corrections | 10/16/2023 | RACHEL BEYENE |
| Applicant returned to address corrections | 10/16/2023 | GARO TELMI |
| Applicant returned to address corrections | 11/16/2023 | RACHEL BEYENE |
| Plan Check Approved | 12/27/2023 | MARCELA FRANQUEZ |
| Issued | 12/27/2023 | APPLICANT |
| CofO in Progress | 11/26/2024 | ASHLEY THOMPSON |
| Permit Finaled | 12/3/2024 | RICHARD STEINBACH |
| CofO Issued | 12/3/2024 | RICHARD STEINBACH |
| Permit Finaled | 12/3/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/14/2023 | JASON NG |
| Sewer availability | Cleared | 7/14/2023 | JASON NG |
| Address approval | Cleared | 9/15/2023 | DARIN LAM |
| Low Impact Development (LID) | Cleared | 9/15/2023 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 9/15/2023 | DARIN LAM |
| Construction near power lines | Cleared | 9/28/2023 | WALTER RAMIREZ |
| Specific Plan | Cleared | 10/5/2023 | PEDRO AYALA |
| Grading Pre-Inspection | Cleared | 10/16/2023 | RAHEL BEYENE |
| Miscellaneous | Cleared | 12/27/2023 | MARCELA FRANQUEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Jalalpour,, Mohammad; Lic. No.: S6696 | 152 DEERFIELD AVE IRVINE, CA 92606 |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/27/2024 | Conditional Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 2/28/2024 | Approved | MEL KHACHATOURIAN |
| METHANE-Barrier | 2/28/2024 | Approved | MEL KHACHATOURIAN |
| METHANE-Subgrade | 2/28/2024 | Approved | MEL KHACHATOURIAN |
| Underground Mechanical | 3/13/2024 | Partial Approval | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 3/14/2024 | Partial Approval | OGANES TARAKHCHYAN |
| Insulation | 3/18/2024 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/19/2024 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/20/2024 | Partial Inspection | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/17/2024 | Approved | OGANES TARAKHCHYAN |
| Gas Test | 5/7/2024 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 5/7/2024 | Approved | JESUS RODRIGUEZ |
| Special/Order Compliance | 5/7/2024 | Corrections Issued | JESUS RODRIGUEZ |
| HVAC-Rough | 5/8/2024 | Partial Approval | OGANES TARAKHCHYAN |
| Shower Pan | 5/9/2024 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 5/10/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 5/13/2024 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 5/13/2024 | Partial Approval | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 5/16/2024 | Corrections Issued | ASHLEY THOMPSON |
| Green Building Rough | 5/20/2024 | Approved | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 5/20/2024 | Partial Approval | MEL KHACHATOURIAN |
| Insulation | 5/24/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Verify Sprinkler Sign Off | 5/24/2024 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 5/29/2024 | Corrections Issued | ASHLEY THOMPSON |
| Insulation | 5/29/2024 | Corrections Issued | ASHLEY THOMPSON |
| METHANE-Rough | 5/29/2024 | Not Ready for Inspection | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 6/4/2024 | Approved | MICHAEL PELHAM |
| Insulation | 6/4/2024 | Approved | MICHAEL PELHAM |
| Interior/Exterior Lathing | 6/4/2024 | Approved | MICHAEL PELHAM |
| METHANE-Rough | 6/4/2024 | Approved | MICHAEL PELHAM |
| Drywall Nailing | 6/10/2024 | Approved | ASHLEY THOMPSON |
| Gas Test | 7/29/2024 | No Access for Inspection | ASHLEY THOMPSON |
| Special/Order Compliance | 7/29/2024 | Partial Approval | REGINA MENDEZ |
| Gas Test | 9/11/2024 | Corrections Issued | ASHLEY THOMPSON |
| HVAC-Final | 9/11/2024 | Corrections Issued | ASHLEY THOMPSON |
| PLUMBING-Final | 9/11/2024 | Corrections Issued | ASHLEY THOMPSON |
| Gas Test | 9/13/2024 | Approved | ASHLEY THOMPSON |
| PLUMBING-Final | 9/13/2024 | Approved | ASHLEY THOMPSON |
| ELECTRICAL-Final | 9/16/2024 | Corrections Issued | STEPHANIE SWANSON |
| Service/Power Release | 9/16/2024 | Approved | STEPHANIE SWANSON |
| Smoke Detectors | 9/16/2024 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Final | 9/18/2024 | Approved | STEPHANIE SWANSON |
| HVAC-Final | 9/18/2024 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Final | 9/19/2024 | Approved | ARAM AVEDISIAN |
| Final | 10/29/2024 | Corrections Issued | ASHLEY THOMPSON |
| Green Building Final | 10/29/2024 | Approved | ASHLEY THOMPSON |
| SGSOV-Seismic Gas S/O Valve | 10/29/2024 | SGSOV Approved | ASHLEY THOMPSON |
| Final | 11/26/2024 | OK to Issue CofO | ASHLEY THOMPSON |