- CONVERT (E) 18' X 20' DETACHED GARAGE AND (N) 20'1" X 12' ADDITION TO (N) ACCESSORY DWELLING UNIT (558 SF) PER LAMC 12.22.A.33(c) AND (d). WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 10/31/2023
- Issuing Office
- Current Status
- CofO Issued on 6/3/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/30/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/2/2023 | MADISON ODELL |
| Corrections Issued | 6/2/2023 | MADISON ODELL |
| Applicant returned to address corrections | 10/18/2023 | MADISON ODELL |
| Applicant returned to address corrections | 10/27/2023 | MADISON ODELL |
| Plan Check Approved | 10/30/2023 | MADISON ODELL |
| Issued | 10/31/2023 | APPLICANT |
| CofO in Progress | 5/31/2024 | BOBBY KEY |
| Permit Finaled | 6/3/2024 | DANIEL ORRANTE |
| CofO Issued | 6/3/2024 | DANIEL ORRANTE |
| Permit Finaled | 6/3/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Sewer availability | Cleared | 8/3/2023 | NEIL TUANO |
| Address approval | Cleared | 8/9/2023 | NEIL TUANO |
| Eng Process Fee Ord 176,300 | Cleared | 8/9/2023 | NEIL TUANO |
| Roof/Waste drainage to street | Cleared | 8/9/2023 | NEIL TUANO |
| Specific Plan | Cleared | 9/6/2023 | FREDDY GARCIA |
| Construction near power lines | Cleared | 10/14/2023 | RIDWAN HARDY |
| Construction within easement | Cleared | 10/14/2023 | RIDWAN HARDY |
Contact Information
| Contractor | A P Remodeling Inc; Lic. No.: 1049032-B | , |
| Contractor | Ap Remodeling Inc; Lic. No.: 1049032-B | , |
| Engineer | Hsiao,, Stephanie; Lic. No.: NA75937 | , |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/13/2023 | Partial Approval | BOBBY KEY |
| Sewer | 12/20/2023 | Approved | BOBBY KEY |
| Footing/Foundation/Slab | 12/26/2023 | Corrections Issued | BOBBY KEY |
| Footing/Foundation/Slab | 12/28/2023 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 1/18/2024 | Partial Approval | HERBERT GIRON |
| ELECTRICAL-Rough | 1/25/2024 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 1/25/2024 | Partial Approval | BOBBY KEY |
| HVAC-Rough | 1/25/2024 | Not Ready for Inspection | BOBBY KEY |
| PLUMBING-Rough | 1/25/2024 | Corrections Issued | BOBBY KEY |
| HVAC-Rough | 1/30/2024 | Approved | BOBBY KEY |
| PLUMBING-Rough | 1/30/2024 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 2/2/2024 | Not Ready for Inspection | HERBERT GIRON |
| Shower Pan | 2/2/2024 | Approved | HERBERT GIRON |
| Special/Order Compliance | 2/2/2024 | Partial Inspection | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 2/13/2024 | Not Ready for Inspection | BOBBY KEY |
| Interior/Exterior Lathing | 2/13/2024 | Not Ready for Inspection | BOBBY KEY |
| Interior/Exterior Lathing | 2/26/2024 | Partial Approval | HERBERT GIRON |
| BUILDING-Rough-Frame | 2/29/2024 | Conditional Approval | BOBBY KEY |
| Interior/Exterior Lathing | 2/29/2024 | Partial Approval | BOBBY KEY |
| Special/Order Compliance | 2/29/2024 | Corrections Issued | BOBBY KEY |
| Underground Mechanical | 2/29/2024 | Corrections Issued | BOBBY KEY |
| Insulation | 3/6/2024 | Approved | TEMISTOCLES CAAL |
| Special/Order Compliance | 3/6/2024 | Partial Inspection | HERBERT GIRON |
| BUILDING-Rough-Frame | 3/11/2024 | Approved | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 3/11/2024 | Approved | HERBERT GIRON |
| Green Building Rough | 3/11/2024 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 3/11/2024 | Approved | HERBERT GIRON |
| Drywall Nailing | 3/13/2024 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 5/17/2024 | Corrections Issued | BOBBY KEY |
| Final | 5/17/2024 | Corrections Issued | BOBBY KEY |
| HVAC-Final | 5/17/2024 | Corrections Issued | BOBBY KEY |
| PLUMBING-Final | 5/17/2024 | Corrections Issued | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 5/17/2024 | SGSOV Approved | BOBBY KEY |
| Smoke Detectors | 5/17/2024 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 5/31/2024 | Approved | BOBBY KEY |
| Final | 5/31/2024 | OK to Issue CofO | BOBBY KEY |
| HVAC-Final | 5/31/2024 | Approved | BOBBY KEY |
| PLUMBING-Final | 5/31/2024 | Approved | BOBBY KEY |