5113-5113 1/2 E MIRIAM ST 90042

Certificate Information: 5113-5113 1/2 E MIRIAM ST 90042

Application / Permit
23014-10000-02080
Plan Check / Job No.
B23LA09733
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
CONVERT (E) GARAGE AND STORAGE OF (E) DUPLEX TO ATTACHED ADU PER CA Govt. Code 65852.2(e)(1)(C)
Permit Issued
Issued on 10/18/2023
Issuing Office
Current Status
CofO Issued on 9/17/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/26/2023 APPLICANT
Assigned to Plan Check Engineer 5/31/2023 CARLOS MONTES
Corrections Issued 6/1/2023 CARLOS MONTES
Quality Review Completed 6/1/2023 GARO TELMI
Applicant returned to address corrections 9/29/2023 CARLOS MONTES
Plan Check Approved 10/13/2023 CARLOS MONTES
Issued 10/18/2023 APPLICANT
CofO in Progress 8/12/2024 HAMIK HARTOUNIAN
No Progress 8/12/2024 CHARLES BOGHOSKHAN
CofO in Progress 8/12/2024 CHARLES BOGHOSKHAN
CofO in Progress 8/13/2024 SCOTT FINNILA
CofO in Progress 8/30/2024 ALIZAH MAYAGOITIA
CofO Issued 9/17/2024 DEROLD HAUFF
Permit Finaled 9/17/2024 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 8/15/2023 ALEXANDER HELFER
Address approval Cleared 8/21/2023 JESSICA OPINION
BHO/Hillside ordinance Cleared 8/21/2023 AMBER CAMPBELL
BHO/Hillside ordinance Cleared 8/23/2023 JESSICA OPINION
BHO/Hillside ordinance Cleared 8/23/2023 JESSICA OPINION
BHO/Hillside ordinance Cleared 8/23/2023 JESSICA OPINION
BHO/Hillside ordinance Cleared 8/23/2023 JESSICA OPINION
Eng Process Fee Ord 176,300 Cleared 8/24/2023 JESSICA OPINION
Sewer availability Cleared 8/24/2023 JESSICA OPINION

Contact Information

Contractor Lee Richard C C; Lic. No.: 292360-B       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/20/2023 Conditional Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 11/2/2023 Corrections Issued HAMIK HARTOUNIAN
Underground Mechanical 11/2/2023 Corrections Issued HAMIK HARTOUNIAN
Footing/Foundation/Slab 11/8/2023 Conditional Approval HAMIK HARTOUNIAN
Underground Mechanical 11/8/2023 Partial Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 12/18/2023 Corrections Issued AMY COLIN
ELECTRICAL-Rough 12/18/2023 Approved AMY COLIN
PLUMBING-Rough 12/18/2023 Approved AMY COLIN
BUILDING-Rough-Frame 12/27/2023 Approved HAMIK HARTOUNIAN
Deputy Wood Construction 12/27/2023 Conditional Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 12/27/2023 Approved HAMIK HARTOUNIAN
Green Building Rough 12/27/2023 Approved HAMIK HARTOUNIAN
Insulation 12/27/2023 Approved HAMIK HARTOUNIAN
Drywall Nailing 1/5/2024 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 1/5/2024 Conditional Approval HAMIK HARTOUNIAN
Final 7/9/2024 Not Ready for Inspection THOMAS LOGRASSO
BUILDING-Rough-Frame 7/15/2024 Approved HAMIK HARTOUNIAN
Final 7/15/2024 Corrections Issued HAMIK HARTOUNIAN
Footing/Foundation/Slab 7/15/2024 Approved HAMIK HARTOUNIAN
Green Building Final 7/15/2024 Approved HAMIK HARTOUNIAN
HVAC-Rough 7/15/2024 Approved HAMIK HARTOUNIAN
Smoke Detectors 7/15/2024 Approved HAMIK HARTOUNIAN
Special/Order Compliance 7/15/2024 Partial Inspection SCOTT FINNILA
Final 7/18/2024 Partial Inspection OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 7/18/2024 SGSOV Approved OSVALDO PARAMO
Final 8/12/2024 Not Ready for Inspection HAMIK HARTOUNIAN
Final 8/30/2024 OK to Issue CofO ALIZAH MAYAGOITIA
Service/Power Release 8/30/2024 Approved ALIZAH MAYAGOITIA