5244 E BARKER DR 90042

Certificate Information: 5244 E BARKER DR 90042

Application / Permit
23014-10000-02059
Plan Check / Job No.
B23LA09635
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION TO (E) SFD (1-STORY)
Permit Issued
Issued on 1/30/2024
Issuing Office
Current Status
Issued on 1/30/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/24/2023 APPLICANT
Assigned to Plan Check Engineer 5/25/2023 CARLOS MONTES
Corrections Issued 5/30/2023 CARLOS MONTES
Quality Review Completed 5/30/2023 GARO TELMI
Applicant returned to address corrections 10/13/2023 CARLOS MONTES
Plan Check Approved 11/2/2023 CARLOS MONTES
Issued 1/30/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 6/28/2023 ADRIAN SANCHEZ
BHO/Hillside ordinance Cleared 7/13/2023 ADRIAN SANCHEZ
BHO/Hillside ordinance Cleared 7/13/2023 ADRIAN SANCHEZ
BHO/Hillside ordinance Cleared 7/13/2023 ADRIAN SANCHEZ
BHO/Hillside ordinance Cleared 7/13/2023 ADRIAN SANCHEZ
Sewer availability Cleared 7/19/2023 ADRIAN SANCHEZ
Eng Process Fee Ord 176,300 Cleared 7/26/2023 ADRIAN SANCHEZ
BHO/Hillside ordinance Cleared 8/8/2023 STEVE MELGAR
Distance to fire station Cleared 8/11/2023 KURT CORRAL
Hydrant and Access approval Cleared 8/11/2023 KURT CORRAL
Low Impact Development (LID) Cleared 9/27/2023 LUIS LUVANO
Roof/Waste drainage to street Cleared 9/28/2023 ADRIAN SANCHEZ
GPI Written Notices Cleared 11/2/2023 CARLOS MONTES
Grading Pre-Inspection Cleared 11/2/2023 CARLOS MONTES

Contact Information

Architect Blatt,, Michael Rosner; Lic. No.: NA19981       ,
Contractor Pearson Builders; Lic. No.: 885937-B       ,
Contractor Svengrupp Inc; Lic. No.: 885937-B       ,
Engineer Irvine,, Jon Alan; Lic. No.: GE2891 145 N SIERRA MADRE BLVD STE 1      PASADENA, CA 91107

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/4/2024 Partial Approval ROY SPAULDING
Underground Mechanical 12/4/2024 Approved ROY SPAULDING
ELECTRICAL-Rough 12/17/2024 Partial Approval BRENDAN MORELLI
Footing/Foundation/Slab 12/17/2024 Partial Approval BRENDAN MORELLI
PLUMBING-Rough 12/17/2024 Partial Approval BRENDAN MORELLI
Deputy Drilled-In Anchors 1/15/2025 Conditional Approval JOSH MEISTER
Footing/Foundation/Slab 1/17/2025 Partial Approval CRAIG DAVIS
Underground Mechanical 1/17/2025 Partial Approval CRAIG DAVIS
ELECTRICAL-Rough 1/22/2025 Partial Approval LILIANA PORTILLO
Footing/Foundation/Slab 1/22/2025 Approved LILIANA PORTILLO
Deputy Drilled-In Anchors 4/3/2025 Conditional Approval JOSH MEISTER
Floor/Roof Diaphrgm/Shear Wall 4/30/2025 Approved DAVID WILLIAMS
Deputy Wood Construction 5/20/2025 Conditional Approval ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 5/21/2025 Approved DAVID WILLIAMS