6948 N NEWCASTLE AVE 91335
Certificate Information: 6948 N NEWCASTLE AVE 91335
- Application / Permit
- 23014-10000-02015
- Plan Check / Job No.
- B23LA09470
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- **ePlan** Addition to (E) Dettached Accessory Dwelling Unit at rear of the lot per LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 1/18/2024
- Issuing Office
- Current Status
- CofO Issued on 9/2/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/22/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/26/2023 | JOHNPAUL ISIP |
| Corrections Issued | 5/30/2023 | JOHNPAUL ISIP |
| Applicant returned to address corrections | 10/10/2023 | EDWIN ESPIN |
| Applicant returned to address corrections | 12/19/2023 | AMY GUEVARRA |
| Plan Check Approved | 1/3/2024 | EDWIN ESPIN |
| Issued | 1/18/2024 | APPLICANT |
| CofO in Progress | 8/20/2025 | ARUTYUN MADATYAN |
| Permit Finaled | 9/2/2025 | JOHN JANSON |
| CofO Issued | 9/2/2025 | JOHN JANSON |
| Permit Finaled | 9/2/2025 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/12/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 7/12/2023 | CARLOS AGUILERA |
| Low Impact Development (LID) | Cleared | 8/28/2023 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 8/28/2023 | DAGOVERTO GUERRERO |
| Construction near power lines | Cleared | 10/5/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Keshishian,, Anthony; Lic. No.: C89551 | 2654 RISA D GLENDALE, CA 91208 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/18/2024 | Not Ready for Inspection | JEFFREY BULL |
| Underground Mechanical | 7/11/2024 | Approved | JEFFREY BULL |
| Deputy Drilled-In Anchors | 7/16/2024 | Conditional Approval | JEFFREY BULL |
| Footing/Foundation/Slab | 8/9/2024 | Approved | JEFFREY BULL |
| Floor/Roof Diaphrgm/Shear Wall | 9/25/2024 | Approved | JEFFREY BULL |
| ELECTRICAL-Rough | 10/18/2024 | Approved | KRISTEN CAUSEY |
| HVAC-Rough | 10/18/2024 | Approved | KRISTEN CAUSEY |
| PLUMBING-Rough | 10/18/2024 | Not Ready for Inspection | KRISTEN CAUSEY |
| Interior/Exterior Lathing | 10/29/2024 | Partial Approval | JEFFREY BULL |
| PLUMBING-Rough | 10/29/2024 | Approved | JEFFREY BULL |
| BUILDING-Rough-Frame | 11/5/2024 | Approved | ARUTYUN MADATYAN |
| Green Building Rough | 11/5/2024 | Approved | ARUTYUN MADATYAN |
| Insulation | 11/5/2024 | Approved | ARUTYUN MADATYAN |
| Drywall Nailing | 11/15/2024 | Approved | KRISTEN CAUSEY |
| Final | 1/14/2025 | Corrections Issued | ARUTYUN MADATYAN |
| Green Building Final | 1/14/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 1/14/2025 | SGSOV Approved | ARUTYUN MADATYAN |
| Smoke Detectors | 1/14/2025 | Approved | ARUTYUN MADATYAN |
| Final | 3/28/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Green Building Final | 3/28/2025 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 8/19/2025 | Approved | ARUTYUN MADATYAN |
| Final | 8/19/2025 | OK to Issue CofO | ARUTYUN MADATYAN |
| HVAC-Final | 8/19/2025 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Final | 8/19/2025 | Approved | ARUTYUN MADATYAN |