Permit Issued
Issued on 10/30/2023
Issuing Office
Current Status
CofO Issued on 1/27/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/22/2023 APPLICANT
Assigned to Plan Check Engineer 6/8/2023 ARSALAN SHABESTARI
Corrections Issued 6/10/2023 ARSALAN SHABESTARI
Quality Review Completed 6/16/2023 GARO TELMI
Plan Check Approved 10/27/2023 ARSALAN SHABESTARI
Issued 10/30/2023 APPLICANT
CofO in Progress 1/17/2025 EVAN COOPER
Permit Finaled 1/27/2025 RICHARD STEINBACH
CofO Issued 1/27/2025 RICHARD STEINBACH
Permit Finaled 1/27/2025 RICHARD STEINBACH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/23/2023 DARIN LAM
Sewer availability Cleared 6/23/2023 DARIN LAM
Grading Pre-Inspection Cleared 6/26/2023 SERGIO VALENZUELA
Hydrant and Access approval Cleared 7/25/2023 JOHN CONNEALLY
Low Impact Development (LID) Cleared 8/28/2023 ROGELIO CORTES
Roof/Waste drainage to street Cleared 8/29/2023 DARIN LAM
Coastal Zone Cleared 9/6/2023 RUBEN VASQUEZ
ZA Case Cleared 9/6/2023 RUBEN VASQUEZ
GPI Written Notices Cleared 10/4/2023 ARSALAN SHABESTARI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

STEPHANIE SWANSON, (213) 469-1255 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/27/2023 Approved EVAN COOPER
Deputy Drilled-In Anchors 1/19/2024 No Access for Inspection KENNETH NAGLE
Footing/Foundation/Slab 1/19/2024 Conditional Approval HERBERT GIRON
BUILDING-Rough-Frame 2/7/2024 Corrections Issued EVAN COOPER
Deputy Drilled-In Anchors 2/7/2024 Approved EVAN COOPER
Green Building Rough 2/7/2024 Not Ready for Inspection EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 4/1/2024 Partial Approval ARAM AVEDISIAN
BUILDING-Rough-Frame 5/10/2024 Not Ready for Inspection STEPHANIE SWANSON
ELECTRICAL-Rough 5/10/2024 Corrections Issued STEPHANIE SWANSON
Green Building Rough 5/10/2024 Not Ready for Inspection STEPHANIE SWANSON
HVAC-Rough 5/10/2024 Corrections Issued STEPHANIE SWANSON
PLUMBING-Rough 5/10/2024 Approved STEPHANIE SWANSON
ELECTRICAL-Rough 5/23/2024 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 5/23/2024 Partial Approval EVAN COOPER
Green Building Rough 5/23/2024 Not Ready for Inspection EVAN COOPER
BUILDING-Rough-Frame 6/12/2024 Approved EVAN COOPER
Green Building Rough 6/12/2024 Approved EVAN COOPER
Interior/Exterior Lathing 6/12/2024 Partial Approval EVAN COOPER
Insulation 6/18/2024 Approved KENNETH NAGLE
Drywall Nailing 6/27/2024 Approved EVAN COOPER
Interior/Exterior Lathing 6/27/2024 Partial Approval EVAN COOPER
Interior/Exterior Lathing 7/10/2024 Approved EVAN COOPER
Footing/Foundation/Slab 9/20/2024 Approved EVAN COOPER
Green Building Final 9/20/2024 Not Ready for Inspection EVAN COOPER
SGSOV-Seismic Gas S/O Valve 9/20/2024 No Access for Inspection EVAN COOPER
Service/Power Release 9/20/2024 Approved EVAN COOPER
Smoke Detectors 9/20/2024 Not Ready for Inspection EVAN COOPER
Final 11/25/2024 Corrections Issued EVAN COOPER
Green Building Final 11/25/2024 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 11/25/2024 SGSOV Approved EVAN COOPER
Smoke Detectors 11/25/2024 Approved EVAN COOPER
Final 12/10/2024 OK to Issue CofO EVAN COOPER