8445 S CROYDON AVE 90045
Certificate Information: 8445 S CROYDON AVE 90045
- Application / Permit
- 23014-10000-01991
- Plan Check / Job No.
- B23LA09378
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT GARAGE AND PORTION OF STORAGE TO ADU PER LAMC 12.22 A.33 (c) & (d) & TWO STORY GROUND FLOOR ADDITION
- Permit Issued
- Issued on 3/28/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/30/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/19/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/8/2023 | SERGIO GUTIERREZ |
| Corrections Issued | 7/5/2023 | SERGIO GUTIERREZ |
| Quality Review Completed | 7/14/2023 | KEN GILL |
| Building Plans Picked Up | 8/4/2023 | APPLICANT |
| Applicant returned to address corrections | 10/11/2023 | SERGIO GUTIERREZ |
| Plan Check Approved | 1/10/2024 | SERGIO GUTIERREZ |
| Issued | 3/28/2024 | APPLICANT |
| CofO in Progress | 9/30/2024 | BOBBY KEY |
| Permit Finaled | 9/30/2024 | RICHARD STEINBACH |
| CofO Issued | 9/30/2024 | RICHARD STEINBACH |
| Permit Finaled | 9/30/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 8/14/2023 | JASON NG |
| Sewer availability | Cleared | 8/14/2023 | JASON NG |
| Eng Process Fee Ord 176,300 | Cleared | 8/15/2023 | JASON NG |
| Construction near power lines | Cleared | 9/1/2023 | RIDWAN HARDY |
| Construction within easement | Cleared | 9/1/2023 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 9/1/2023 | JOHN CONNEALLY |
| Low Impact Development (LID) | Cleared | 9/8/2023 | TOMMY YIN |
| Roof/Waste drainage to street | Cleared | 9/18/2023 | DARIN LAM |
| Specific Plan | Cleared | 9/20/2023 | WESTON PRINGLE |
Contact Information
| Architect | , ; Lic. No.: C35683 | , |
| Contractor | R S R Construction; Lic. No.: 853717-B | 10242 PARKINSON AVENUE WHITTIER, CA 90605 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/15/2024 | Partial Approval | BOBBY KEY |
| Sewer | 4/15/2024 | Not Ready for Inspection | BOBBY KEY |
| Excavation/Setback/Form/Re-Bar | 4/17/2024 | Approved | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 4/17/2024 | Approved | TEMISTOCLES CAAL |
| Special/Order Compliance | 4/17/2024 | Corrections Issued | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 5/1/2024 | Corrections Issued | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 5/1/2024 | Partial Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 5/9/2024 | Partial Approval | BOBBY KEY |
| ELECTRICAL-Rough | 6/3/2024 | Corrections Issued | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 6/3/2024 | Corrections Issued | BOBBY KEY |
| HVAC-Rough | 6/3/2024 | Corrections Issued | BOBBY KEY |
| PLUMBING-Rough | 6/3/2024 | Corrections Issued | BOBBY KEY |
| Special/Order Compliance | 6/3/2024 | Corrections Issued | BOBBY KEY |
| ELECTRICAL-Rough | 6/5/2024 | Corrections Issued | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 6/5/2024 | Approved | BOBBY KEY |
| HVAC-Rough | 6/5/2024 | Approved | BOBBY KEY |
| PLUMBING-Rough | 6/5/2024 | Not Ready for Inspection | BOBBY KEY |
| BUILDING-Rough-Frame | 6/17/2024 | Not Ready for Inspection | BOBBY KEY |
| Green Building Rough | 6/17/2024 | Not Ready for Inspection | BOBBY KEY |
| Interior/Exterior Lathing | 6/17/2024 | Not Ready for Inspection | BOBBY KEY |
| Rough-Elec/Plmb/HVAC | 6/17/2024 | Not Ready for Inspection | BOBBY KEY |
| BUILDING-Rough-Frame | 6/20/2024 | Partial Approval | BOBBY KEY |
| Green Building Rough | 6/20/2024 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 6/20/2024 | Partial Approval | BOBBY KEY |
| Rough-Elec/Plmb/HVAC | 6/20/2024 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 6/26/2024 | Approved | BOBBY KEY |
| Insulation | 6/26/2024 | Approved | BOBBY KEY |
| Drywall Nailing | 7/2/2024 | Corrections Issued | BOBBY KEY |
| Drywall Nailing | 7/5/2024 | Approved | JESUS PINEDA |
| Sewer | 7/23/2024 | Approved | BOBBY KEY |
| Gas Test | 7/26/2024 | Approved | BOBBY KEY |
| Underground Mechanical | 7/26/2024 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 9/13/2024 | Corrections Issued | BOBBY KEY |
| Final | 9/13/2024 | Corrections Issued | BOBBY KEY |
| Green Building Final | 9/13/2024 | Approved | BOBBY KEY |
| HVAC-Final | 9/13/2024 | Corrections Issued | BOBBY KEY |
| PLUMBING-Final | 9/13/2024 | Corrections Issued | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 9/13/2024 | SGSOV Not Ready | BOBBY KEY |
| Smoke Detectors | 9/13/2024 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 9/24/2024 | Approved | BOBBY KEY |
| Final | 9/24/2024 | Not Ready for Inspection | BOBBY KEY |
| HVAC-Final | 9/24/2024 | Approved | BOBBY KEY |
| PLUMBING-Final | 9/24/2024 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 9/24/2024 | SGSOV Approved | BOBBY KEY |
| Final | 9/30/2024 | OK to Issue CofO | BOBBY KEY |
| Service/Power Release | 9/30/2024 | Approved | BOBBY KEY |