8445 S CROYDON AVE 90045

Certificate Information: 8445 S CROYDON AVE 90045

Application / Permit
23014-10000-01991
Plan Check / Job No.
B23LA09378
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT GARAGE AND PORTION OF STORAGE TO ADU PER LAMC 12.22 A.33 (c) & (d) & TWO STORY GROUND FLOOR ADDITION
Permit Issued
Issued on 3/28/2024
Issuing Office
Metro
Current Status
CofO Issued on 9/30/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/19/2023 APPLICANT
Assigned to Plan Check Engineer 6/8/2023 SERGIO GUTIERREZ
Corrections Issued 7/5/2023 SERGIO GUTIERREZ
Quality Review Completed 7/14/2023 KEN GILL
Building Plans Picked Up 8/4/2023 APPLICANT
Applicant returned to address corrections 10/11/2023 SERGIO GUTIERREZ
Plan Check Approved 1/10/2024 SERGIO GUTIERREZ
Issued 3/28/2024 APPLICANT
CofO in Progress 9/30/2024 BOBBY KEY
Permit Finaled 9/30/2024 RICHARD STEINBACH
CofO Issued 9/30/2024 RICHARD STEINBACH
Permit Finaled 9/30/2024 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 8/14/2023 JASON NG
Sewer availability Cleared 8/14/2023 JASON NG
Eng Process Fee Ord 176,300 Cleared 8/15/2023 JASON NG
Construction near power lines Cleared 9/1/2023 RIDWAN HARDY
Construction within easement Cleared 9/1/2023 RIDWAN HARDY
Hydrant and Access approval Cleared 9/1/2023 JOHN CONNEALLY
Low Impact Development (LID) Cleared 9/8/2023 TOMMY YIN
Roof/Waste drainage to street Cleared 9/18/2023 DARIN LAM
Specific Plan Cleared 9/20/2023 WESTON PRINGLE

Contact Information

Architect , ; Lic. No.: C35683       ,
Contractor R S R Construction; Lic. No.: 853717-B 10242 PARKINSON AVENUE      WHITTIER, CA 90605

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/15/2024 Partial Approval BOBBY KEY
Sewer 4/15/2024 Not Ready for Inspection BOBBY KEY
Excavation/Setback/Form/Re-Bar 4/17/2024 Approved TEMISTOCLES CAAL
Footing/Foundation/Slab 4/17/2024 Approved TEMISTOCLES CAAL
Special/Order Compliance 4/17/2024 Corrections Issued TEMISTOCLES CAAL
BUILDING-Rough-Frame 5/1/2024 Corrections Issued BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 5/1/2024 Partial Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 5/9/2024 Partial Approval BOBBY KEY
ELECTRICAL-Rough 6/3/2024 Corrections Issued BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 6/3/2024 Corrections Issued BOBBY KEY
HVAC-Rough 6/3/2024 Corrections Issued BOBBY KEY
PLUMBING-Rough 6/3/2024 Corrections Issued BOBBY KEY
Special/Order Compliance 6/3/2024 Corrections Issued BOBBY KEY
ELECTRICAL-Rough 6/5/2024 Corrections Issued BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 6/5/2024 Approved BOBBY KEY
HVAC-Rough 6/5/2024 Approved BOBBY KEY
PLUMBING-Rough 6/5/2024 Not Ready for Inspection BOBBY KEY
BUILDING-Rough-Frame 6/17/2024 Not Ready for Inspection BOBBY KEY
Green Building Rough 6/17/2024 Not Ready for Inspection BOBBY KEY
Interior/Exterior Lathing 6/17/2024 Not Ready for Inspection BOBBY KEY
Rough-Elec/Plmb/HVAC 6/17/2024 Not Ready for Inspection BOBBY KEY
BUILDING-Rough-Frame 6/20/2024 Partial Approval BOBBY KEY
Green Building Rough 6/20/2024 Approved BOBBY KEY
Interior/Exterior Lathing 6/20/2024 Partial Approval BOBBY KEY
Rough-Elec/Plmb/HVAC 6/20/2024 Approved BOBBY KEY
BUILDING-Rough-Frame 6/26/2024 Approved BOBBY KEY
Insulation 6/26/2024 Approved BOBBY KEY
Drywall Nailing 7/2/2024 Corrections Issued BOBBY KEY
Drywall Nailing 7/5/2024 Approved JESUS PINEDA
Sewer 7/23/2024 Approved BOBBY KEY
Gas Test 7/26/2024 Approved BOBBY KEY
Underground Mechanical 7/26/2024 Approved BOBBY KEY
ELECTRICAL-Final 9/13/2024 Corrections Issued BOBBY KEY
Final 9/13/2024 Corrections Issued BOBBY KEY
Green Building Final 9/13/2024 Approved BOBBY KEY
HVAC-Final 9/13/2024 Corrections Issued BOBBY KEY
PLUMBING-Final 9/13/2024 Corrections Issued BOBBY KEY
SGSOV-Seismic Gas S/O Valve 9/13/2024 SGSOV Not Ready BOBBY KEY
Smoke Detectors 9/13/2024 Approved BOBBY KEY
ELECTRICAL-Final 9/24/2024 Approved BOBBY KEY
Final 9/24/2024 Not Ready for Inspection BOBBY KEY
HVAC-Final 9/24/2024 Approved BOBBY KEY
PLUMBING-Final 9/24/2024 Approved BOBBY KEY
SGSOV-Seismic Gas S/O Valve 9/24/2024 SGSOV Approved BOBBY KEY
Final 9/30/2024 OK to Issue CofO BOBBY KEY
Service/Power Release 9/30/2024 Approved BOBBY KEY