2641 S KELTON AVE 90064
Certificate Information: 2641 S KELTON AVE 90064
- Application / Permit
- 23014-10000-01987
- Plan Check / Job No.
- B23LA09353
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) Addition of existing SFD
- Permit Issued
- Issued on 3/12/2024
- Issuing Office
- Current Status
- CofO Issued on 11/8/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/26/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/15/2023 | CARLOS MONTES |
| Corrections Issued | 6/21/2023 | CARLOS MONTES |
| Quality Review Completed | 6/22/2023 | GARO TELMI |
| Applicant returned to address corrections | 10/27/2023 | CARLOS MONTES |
| Applicant returned to address corrections | 1/26/2024 | CARLOS MONTES |
| Applicant returned to address corrections | 2/20/2024 | CARLOS MONTES |
| Applicant returned to address corrections | 3/7/2024 | CARLOS MONTES |
| Plan Check Approved | 3/12/2024 | CARLOS MONTES |
| Issued | 3/12/2024 | APPLICANT |
| CofO in Progress | 10/24/2025 | KIRK SANDERS |
| Permit Finaled | 11/8/2025 | RICHARD STEINBACH |
| CofO Issued | 11/8/2025 | RICHARD STEINBACH |
| Permit Finaled | 11/8/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Sewer availability | Cleared | 6/29/2023 | DARIN LAM |
| Grading Pre-Inspection | Cleared | 7/5/2023 | ROBERT HUGHES |
| Eng Process Fee Ord 176,300 | Cleared | 10/16/2023 | DARIN LAM |
| Roof/Waste drainage to street | Cleared | 1/18/2024 | VLADIMIR ARUTYUNYAN |
| GPI Written Notices | Cleared | 3/12/2024 | CARLOS MONTES |
Contact Information
| Architect | Asamoah,, B Kwesi; Lic. No.: C36558 | 850 ROSE AVENUE VENICE, CA 90291 |
| Contractor | Ochoa Victor Manuel; Lic. No.: 908306-B | , |
| Contractor | Victor Manuel Ochoa; Lic. No.: 908306-B | , |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/28/2024 | Conditional Approval | JESUS PINEDA |
| Footing/Foundation/Slab | 5/28/2024 | Corrections Issued | JESUS PINEDA |
| Special/Order Compliance | 5/28/2024 | Corrections Issued | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 6/17/2024 | Partial Approval | JESUS PINEDA |
| Footing/Foundation/Slab | 6/17/2024 | Approved | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 7/11/2024 | Partial Approval | JESUS PINEDA |
| Deputy Steel/Welding | 7/17/2024 | Conditional Approval | JESUS PINEDA |
| BUILDING-Rough-Frame | 10/4/2024 | Not Ready for Inspection | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 10/4/2024 | Corrections Issued | KIRK SANDERS |
| Green Building Rough | 10/4/2024 | Not Ready for Inspection | KIRK SANDERS |
| Wood Frame | 10/4/2024 | Not Ready for Inspection | KIRK SANDERS |
| BUILDING-Rough-Frame | 11/13/2024 | Not Ready for Inspection | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 11/13/2024 | Approved | DANIEL VERA |
| Green Building Rough | 11/13/2024 | Not Ready for Inspection | DANIEL VERA |
| HVAC-Rough | 12/19/2024 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 1/6/2025 | Corrections Issued | CARLOS MATAMOROS |
| HVAC-Rough | 1/6/2025 | Partial Approval | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 1/16/2025 | Partial Approval | CARLOS MATAMOROS |
| HVAC-Rough | 1/16/2025 | Partial Approval | CARLOS MATAMOROS |
| PLUMBING-Rough | 1/16/2025 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 1/24/2025 | Not Ready for Inspection | KIRK SANDERS |
| HVAC-Rough | 1/24/2025 | Approved | KIRK SANDERS |
| Shower Pan | 1/29/2025 | Approved | ARAM AVEDISIAN |
| Underground Mechanical | 1/29/2025 | Partial Approval | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 1/30/2025 | Approved | CHRISTOPHER WILSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/13/2025 | Not Ready for Inspection | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 2/18/2025 | Approved | DANIEL VERA |
| BUILDING-Rough-Frame | 3/11/2025 | Corrections Issued | WILBER ROSALES |
| Final | 3/11/2025 | Corrections Issued | WILBER ROSALES |
| Green Building Rough | 3/11/2025 | Approved | WILBER ROSALES |
| Interior/Exterior Lathing | 3/11/2025 | Partial Approval | WILBER ROSALES |
| Special/Order Compliance | 3/11/2025 | Partial Inspection | BOBBY KEY |
| Verify Sprinkler Sign Off | 3/11/2025 | Approved | WILBER ROSALES |
| Insulation | 3/25/2025 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 4/4/2025 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 4/4/2025 | Partial Approval | BOBBY KEY |
| Drywall Nailing | 4/9/2025 | Corrections Issued | STEPHANIE SWANSON |
| Drywall Nailing | 4/17/2025 | Approved | KIRK SANDERS |
| Final | 4/17/2025 | Corrections Issued | KIRK SANDERS |
| Interior/Exterior Lathing | 5/7/2025 | Approved | STEPHANIE SWANSON |
| PLUMBING-Final | 9/30/2025 | Conditional Approval | MEL KHACHATOURIAN |
| Gas Test | 10/2/2025 | Approved | JAYLIN GRAVITTE |
| ELECTRICAL-Final | 10/8/2025 | Corrections Issued | MICHAEL ALLEN |
| PLUMBING-Final | 10/8/2025 | Conditional Approval | MICHAEL ALLEN |
| HVAC-Final | 10/9/2025 | Corrections Issued | ANDREW NAVE |
| PLUMBING-Final | 10/9/2025 | Approved | ANDREW NAVE |
| ELECTRICAL-Final | 10/20/2025 | Approved | KIRK SANDERS |
| Final | 10/20/2025 | Corrections Issued | KIRK SANDERS |
| Green Building Final | 10/20/2025 | Approved | KIRK SANDERS |
| HVAC-Final | 10/20/2025 | Approved | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 10/20/2025 | SGSOV Approved | KIRK SANDERS |
| Smoke Detectors | 10/20/2025 | Approved | KIRK SANDERS |
| Special/Order Compliance | 10/22/2025 | Conditional Approval | KIRK SANDERS |
| Final | 10/23/2025 | OK to Issue CofO | KIRK SANDERS |