2641 S KELTON AVE 90064

Certificate Information: 2641 S KELTON AVE 90064

Application / Permit
23014-10000-01987
Plan Check / Job No.
B23LA09353
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) Addition of existing SFD
Permit Issued
Issued on 3/12/2024
Issuing Office
Current Status
CofO Issued on 11/8/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/26/2023 APPLICANT
Assigned to Plan Check Engineer 6/15/2023 CARLOS MONTES
Corrections Issued 6/21/2023 CARLOS MONTES
Quality Review Completed 6/22/2023 GARO TELMI
Applicant returned to address corrections 10/27/2023 CARLOS MONTES
Applicant returned to address corrections 1/26/2024 CARLOS MONTES
Applicant returned to address corrections 2/20/2024 CARLOS MONTES
Applicant returned to address corrections 3/7/2024 CARLOS MONTES
Plan Check Approved 3/12/2024 CARLOS MONTES
Issued 3/12/2024 APPLICANT
CofO in Progress 10/24/2025 KIRK SANDERS
Permit Finaled 11/8/2025 RICHARD STEINBACH
CofO Issued 11/8/2025 RICHARD STEINBACH
Permit Finaled 11/8/2025 RICHARD STEINBACH

Permit Application Clearance Information

Sewer availability Cleared 6/29/2023 DARIN LAM
Grading Pre-Inspection Cleared 7/5/2023 ROBERT HUGHES
Eng Process Fee Ord 176,300 Cleared 10/16/2023 DARIN LAM
Roof/Waste drainage to street Cleared 1/18/2024 VLADIMIR ARUTYUNYAN
GPI Written Notices Cleared 3/12/2024 CARLOS MONTES

Contact Information

Architect Asamoah,, B Kwesi; Lic. No.: C36558 850 ROSE AVENUE      VENICE, CA 90291
Contractor Ochoa Victor Manuel; Lic. No.: 908306-B       ,
Contractor Victor Manuel Ochoa; Lic. No.: 908306-B       ,

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/28/2024 Conditional Approval JESUS PINEDA
Footing/Foundation/Slab 5/28/2024 Corrections Issued JESUS PINEDA
Special/Order Compliance 5/28/2024 Corrections Issued JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 6/17/2024 Partial Approval JESUS PINEDA
Footing/Foundation/Slab 6/17/2024 Approved JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 7/11/2024 Partial Approval JESUS PINEDA
Deputy Steel/Welding 7/17/2024 Conditional Approval JESUS PINEDA
BUILDING-Rough-Frame 10/4/2024 Not Ready for Inspection KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 10/4/2024 Corrections Issued KIRK SANDERS
Green Building Rough 10/4/2024 Not Ready for Inspection KIRK SANDERS
Wood Frame 10/4/2024 Not Ready for Inspection KIRK SANDERS
BUILDING-Rough-Frame 11/13/2024 Not Ready for Inspection DANIEL VERA
Floor/Roof Diaphrgm/Shear Wall 11/13/2024 Approved DANIEL VERA
Green Building Rough 11/13/2024 Not Ready for Inspection DANIEL VERA
HVAC-Rough 12/19/2024 Corrections Issued STEPHANIE SWANSON
ELECTRICAL-Rough 1/6/2025 Corrections Issued CARLOS MATAMOROS
HVAC-Rough 1/6/2025 Partial Approval CARLOS MATAMOROS
ELECTRICAL-Rough 1/16/2025 Partial Approval CARLOS MATAMOROS
HVAC-Rough 1/16/2025 Partial Approval CARLOS MATAMOROS
PLUMBING-Rough 1/16/2025 Approved CARLOS MATAMOROS
ELECTRICAL-Rough 1/24/2025 Not Ready for Inspection KIRK SANDERS
HVAC-Rough 1/24/2025 Approved KIRK SANDERS
Shower Pan 1/29/2025 Approved ARAM AVEDISIAN
Underground Mechanical 1/29/2025 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Rough 1/30/2025 Approved CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 2/13/2025 Not Ready for Inspection DANIEL VERA
Floor/Roof Diaphrgm/Shear Wall 2/18/2025 Approved DANIEL VERA
BUILDING-Rough-Frame 3/11/2025 Corrections Issued WILBER ROSALES
Final 3/11/2025 Corrections Issued WILBER ROSALES
Green Building Rough 3/11/2025 Approved WILBER ROSALES
Interior/Exterior Lathing 3/11/2025 Partial Approval WILBER ROSALES
Special/Order Compliance 3/11/2025 Partial Inspection BOBBY KEY
Verify Sprinkler Sign Off 3/11/2025 Approved WILBER ROSALES
Insulation 3/25/2025 Approved KIRK SANDERS
BUILDING-Rough-Frame 4/4/2025 Approved BOBBY KEY
Interior/Exterior Lathing 4/4/2025 Partial Approval BOBBY KEY
Drywall Nailing 4/9/2025 Corrections Issued STEPHANIE SWANSON
Drywall Nailing 4/17/2025 Approved KIRK SANDERS
Final 4/17/2025 Corrections Issued KIRK SANDERS
Interior/Exterior Lathing 5/7/2025 Approved STEPHANIE SWANSON
PLUMBING-Final 9/30/2025 Conditional Approval MEL KHACHATOURIAN
Gas Test 10/2/2025 Approved JAYLIN GRAVITTE
ELECTRICAL-Final 10/8/2025 Corrections Issued MICHAEL ALLEN
PLUMBING-Final 10/8/2025 Conditional Approval MICHAEL ALLEN
HVAC-Final 10/9/2025 Corrections Issued ANDREW NAVE
PLUMBING-Final 10/9/2025 Approved ANDREW NAVE
ELECTRICAL-Final 10/20/2025 Approved KIRK SANDERS
Final 10/20/2025 Corrections Issued KIRK SANDERS
Green Building Final 10/20/2025 Approved KIRK SANDERS
HVAC-Final 10/20/2025 Approved KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 10/20/2025 SGSOV Approved KIRK SANDERS
Smoke Detectors 10/20/2025 Approved KIRK SANDERS
Special/Order Compliance 10/22/2025 Conditional Approval KIRK SANDERS
Final 10/23/2025 OK to Issue CofO KIRK SANDERS