4037 W BRUNSWICK AVE 90039

Certificate Information: 4037 W BRUNSWICK AVE 90039

Application / Permit
23014-10000-01981
Plan Check / Job No.
B23LA09341
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED, IRREGULARLY SHAPED 28' X 20'6" ACCESSORY DWELLING UNIT (549 SF) WITH NEW 2' X 6'3" COVERED PORCH PER LAMC 12.22.A.33(c) AND (d). WORK TO BE DONE PER ENGINEER.
Permit Issued
Issued on 8/28/2023
Issuing Office
Current Status
CofO Issued on 6/17/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/18/2023 APPLICANT
Assigned to Plan Check Engineer 5/24/2023 MADISON ODELL
Corrections Issued 5/24/2023 MADISON ODELL
Applicant returned to address corrections 8/23/2023 MADISON ODELL
Plan Check Approved 8/27/2023 MADISON ODELL
Issued 8/28/2023 APPLICANT
CofO in Progress 6/14/2024 THOMAS LOGRASSO
Permit Finaled 6/17/2024 DEROLD HAUFF
CofO Issued 6/17/2024 DEROLD HAUFF

Permit Application Clearance Information

ZI Cleared 6/5/2023 LOUIS ORTEGA
Address approval Cleared 6/6/2023 JESSICA OPINION
Eng Process Fee Ord 176,300 Cleared 6/13/2023 JESSICA OPINION
Sewer availability Cleared 6/13/2023 JESSICA OPINION
Low Impact Development (LID) Cleared 7/3/2023 ERNEST TSE
Roof/Waste drainage to street Cleared 7/6/2023 NEIL TUANO
Construction near power lines Cleared 8/21/2023 RIDWAN HARDY
Construction within easement Cleared 8/21/2023 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Standley,, Craig Erick; Lic. No.: NA87675       ,

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/16/2023 Not Ready for Inspection HAMIK HARTOUNIAN
Footing/Foundation/Slab 11/16/2023 Not Ready for Inspection HAMIK HARTOUNIAN
Underground Mechanical 11/16/2023 Not Ready for Inspection HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 11/21/2023 Approved ROY SPAULDING
Piling/Pier/Caisson 11/21/2023 Approved ROY SPAULDING
Pre-Inspection 11/21/2023 Approved ROY SPAULDING
Floor/Roof Diaphrgm/Shear Wall 12/20/2023 Corrections Issued HAMIK HARTOUNIAN
ELECTRICAL-Rough 1/18/2024 Approved HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 1/18/2024 Partial Approval HAMIK HARTOUNIAN
PLUMBING-Rough 1/18/2024 Approved HAMIK HARTOUNIAN
Sewer 1/18/2024 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 1/22/2024 Conditional Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 1/25/2024 Not Ready for Inspection HAMIK HARTOUNIAN
Green Building Rough 1/25/2024 Not Ready for Inspection HAMIK HARTOUNIAN
Interior/Exterior Lathing 1/25/2024 Conditional Approval HAMIK HARTOUNIAN
Verify Sprinkler Sign Off 1/25/2024 Not Ready for Inspection HAMIK HARTOUNIAN
BUILDING-Rough-Frame 1/31/2024 Corrections Issued HAMIK HARTOUNIAN
Green Building Rough 1/31/2024 Not Ready for Inspection HAMIK HARTOUNIAN
Interior/Exterior Lathing 1/31/2024 Not Ready for Inspection HAMIK HARTOUNIAN
BUILDING-Rough-Frame 2/27/2024 Approved HAMIK HARTOUNIAN
Green Building Rough 2/27/2024 Approved HAMIK HARTOUNIAN
HVAC-Rough 2/27/2024 Conditional Approval HAMIK HARTOUNIAN
Verify Sprinkler Sign Off 2/27/2024 Approved HAMIK HARTOUNIAN
Insulation 3/4/2024 Approved JOSEPH MCGARRY
Drywall Nailing 3/11/2024 Approved CHARLES BOGHOSKHAN
Interior/Exterior Lathing 3/19/2024 Approved CHARLES BOGHOSKHAN
Shower Pan 3/19/2024 Approved CHARLES BOGHOSKHAN
Shower Pan 3/20/2024 Approved HAMIK HARTOUNIAN
Final 5/8/2024 Not Ready for Inspection THOMAS LOGRASSO
Final 6/5/2024 Corrections Issued THOMAS LOGRASSO
Footing/Foundation/Slab 6/5/2024 Approved THOMAS LOGRASSO
Green Building Final 6/5/2024 Not Ready for Inspection THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 6/5/2024 SGSOV Approved THOMAS LOGRASSO
Smoke Detectors 6/5/2024 Approved THOMAS LOGRASSO
Final 6/13/2024 OK to Issue CofO THOMAS LOGRASSO
Green Building Final 6/13/2024 Approved THOMAS LOGRASSO
Service/Power Release 6/13/2024 Not Required THOMAS LOGRASSO