159 W 93RD ST 90003
Certificate Information: 159 W 93RD ST 90003
- Application / Permit
- 23014-10000-01973
- Plan Check / Job No.
- B23LA09316
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition to (E) SFD with interior remodel and structural revision. All work per engineered plans.
- Permit Issued
- Issued on 10/10/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/18/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/23/2023 | MICHAEL LANZONE |
| Corrections Issued | 5/23/2023 | MICHAEL LANZONE |
| Building Plans Picked Up | 5/26/2023 | APPLICANT |
| Plan Check Approved | 10/6/2023 | DANIEL SMILEY |
| Issued | 10/10/2023 | APPLICANT |
| CofO in Progress | 8/16/2024 | MICHAEL LEWIS |
| CofO Issued | 9/12/2024 | RUBEN SALAS |
| Permit Finaled | 9/12/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 6/12/2023 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 6/12/2023 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 6/22/2023 | CELINA MORENO |
| Sewer availability | Cleared | 9/27/2023 | CHRISTINA BRACO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/1/2023 | Approved | MICHAEL LEWIS |
| Footing/Foundation/Slab | 11/1/2023 | Corrections Issued | MICHAEL LEWIS |
| Deputy Drilled-In Anchors | 11/3/2023 | Approved | MICHAEL LEWIS |
| Footing/Foundation/Slab | 11/28/2023 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 2/21/2024 | Partial Approval | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 2/26/2024 | Partial Approval | MICHAEL LEWIS |
| Insulation | 2/26/2024 | Partial Approval | MICHAEL LEWIS |
| ELECTRICAL-Rough | 3/13/2024 | Corrections Issued | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 3/13/2024 | Not Ready for Inspection | JOSEPH MCGARRY |
| PLUMBING-Rough | 3/13/2024 | Corrections Issued | JOSEPH MCGARRY |
| Wood Frame | 3/13/2024 | Corrections Issued | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 3/27/2024 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 3/27/2024 | Approved | MICHAEL LEWIS |
| HVAC-Rough | 3/27/2024 | Approved | MICHAEL LEWIS |
| PLUMBING-Rough | 3/27/2024 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 4/2/2024 | Approved | MICHAEL LEWIS |
| Green Building Rough | 4/2/2024 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 4/2/2024 | Approved | MICHAEL LEWIS |
| Insulation | 4/4/2024 | Approved | MICHAEL LEWIS |
| Drywall Nailing | 4/16/2024 | Approved | JOSH MEISTER |
| Final | 5/13/2024 | Corrections Issued | JOSE MACIAS |
| Green Building Final | 5/13/2024 | Approved | JOSE MACIAS |
| SGSOV-Seismic Gas S/O Valve | 5/13/2024 | SGSOV Not Ready | JOSE MACIAS |
| Smoke Detectors | 5/13/2024 | Approved | JOSE MACIAS |
| Final | 8/15/2024 | OK to Issue CofO | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 8/15/2024 | SGSOV Approved | MICHAEL LEWIS |