2214 S HIGHLAND AVE 90016
Certificate Information: 2214 S HIGHLAND AVE 90016
- Application / Permit
- 23014-10000-01957
- Plan Check / Job No.
- B23LA09244
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION IRREGULAR SHAPED ( 31'-6" X 18'-2") TO (E) SINGLE-FAMILY DWELLING TO CREATE MASTER BEDROOM, BATHROOM, WALKIN CLOSET AND INTERIOR REMODEL. WORK PER ENGINEER.
- Permit Issued
- Issued on 9/19/2023
- Issuing Office
- Current Status
- CofO Issued on 6/11/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/17/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/18/2023 | ALEC MOUSAKHANIAN |
| Corrections Issued | 5/19/2023 | ALEC MOUSAKHANIAN |
| Applicant returned to address corrections | 9/6/2023 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 9/12/2023 | ROSENDO MEDINA |
| Issued | 9/19/2023 | APPLICANT |
| CofO in Progress | 6/10/2024 | JUSTIN HAWLEY |
| CofO Issued | 6/11/2024 | DEROLD HAUFF |
| Permit Finaled | 6/11/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Low Impact Development (LID) | Cleared | 8/21/2023 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 8/23/2023 | JEANIE LAM |
| Sewer availability | Cleared | 8/25/2023 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 9/6/2023 | JEANIE LAM |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Zelada,, Mynor Anibal; Lic. No.: C48666 | 22634 SYLVAN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/6/2023 | Approved | CALEB MEISTER |
| Deputy Drilled-In Anchors | 10/18/2023 | Conditional Approval | CALEB MEISTER |
| BUILDING-Rough-Frame | 10/19/2023 | Partial Approval | CALEB MEISTER |
| PLUMBING-Rough | 10/19/2023 | Partial Approval | CALEB MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 10/23/2023 | Partial Approval | CALEB MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 11/14/2023 | Partial Approval | STUART CHAPMAN |
| ELECTRICAL-Rough | 12/14/2023 | Approved | JUSTIN HAWLEY |
| HVAC-Rough | 12/14/2023 | Approved | JUSTIN HAWLEY |
| PLUMBING-Rough | 12/14/2023 | Approved | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 1/2/2024 | Approved | JUSTIN HAWLEY |
| Green Building Rough | 1/2/2024 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 1/2/2024 | Partial Approval | JUSTIN HAWLEY |
| MERV13>=Rough | 1/2/2024 | Approved | JUSTIN HAWLEY |
| Insulation | 1/3/2024 | Approved | JUSTIN HAWLEY |
| Drywall Nailing | 1/5/2024 | Approved | BRENDAN MORELLI |
| Interior/Exterior Lathing | 3/13/2024 | Approved | JUSTIN HAWLEY |
| Shower Pan | 3/13/2024 | Approved | JUSTIN HAWLEY |
| Final | 6/4/2024 | Corrections Issued | JUSTIN HAWLEY |
| Green Building Final | 6/4/2024 | Approved | JUSTIN HAWLEY |
| MERV13>=Final | 6/4/2024 | Approved | JUSTIN HAWLEY |
| SGSOV-Seismic Gas S/O Valve | 6/4/2024 | SGSOV Approved | JUSTIN HAWLEY |
| Smoke Detectors | 6/4/2024 | Approved | JUSTIN HAWLEY |
| ELECTRICAL-Final | 6/10/2024 | Approved | JUSTIN HAWLEY |
| Final | 6/10/2024 | OK to Issue CofO | JUSTIN HAWLEY |
| HVAC-Final | 6/10/2024 | Approved | JUSTIN HAWLEY |
| PLUMBING-Final | 6/10/2024 | Approved | JUSTIN HAWLEY |