2214 S HIGHLAND AVE 90016

Certificate Information: 2214 S HIGHLAND AVE 90016

Application / Permit
23014-10000-01957
Plan Check / Job No.
B23LA09244
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION IRREGULAR SHAPED ( 31'-6" X 18'-2") TO (E) SINGLE-FAMILY DWELLING TO CREATE MASTER BEDROOM, BATHROOM, WALKIN CLOSET AND INTERIOR REMODEL. WORK PER ENGINEER.
Permit Issued
Issued on 9/19/2023
Issuing Office
Current Status
CofO Issued on 6/11/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/17/2023 APPLICANT
Assigned to Plan Check Engineer 5/18/2023 ALEC MOUSAKHANIAN
Corrections Issued 5/19/2023 ALEC MOUSAKHANIAN
Applicant returned to address corrections 9/6/2023 ALEC MOUSAKHANIAN
Plan Check Approved 9/12/2023 ROSENDO MEDINA
Issued 9/19/2023 APPLICANT
CofO in Progress 6/10/2024 JUSTIN HAWLEY
CofO Issued 6/11/2024 DEROLD HAUFF
Permit Finaled 6/11/2024 DEROLD HAUFF

Permit Application Clearance Information

Low Impact Development (LID) Cleared 8/21/2023 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 8/23/2023 JEANIE LAM
Sewer availability Cleared 8/25/2023 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 9/6/2023 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,
Engineer Zelada,, Mynor Anibal; Lic. No.: C48666 22634 SYLVAN ST      WOODLAND HILLS, CA 91367

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/6/2023 Approved CALEB MEISTER
Deputy Drilled-In Anchors 10/18/2023 Conditional Approval CALEB MEISTER
BUILDING-Rough-Frame 10/19/2023 Partial Approval CALEB MEISTER
PLUMBING-Rough 10/19/2023 Partial Approval CALEB MEISTER
Floor/Roof Diaphrgm/Shear Wall 10/23/2023 Partial Approval CALEB MEISTER
Floor/Roof Diaphrgm/Shear Wall 11/14/2023 Partial Approval STUART CHAPMAN
ELECTRICAL-Rough 12/14/2023 Approved JUSTIN HAWLEY
HVAC-Rough 12/14/2023 Approved JUSTIN HAWLEY
PLUMBING-Rough 12/14/2023 Approved JUSTIN HAWLEY
BUILDING-Rough-Frame 1/2/2024 Approved JUSTIN HAWLEY
Green Building Rough 1/2/2024 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 1/2/2024 Partial Approval JUSTIN HAWLEY
MERV13>=Rough 1/2/2024 Approved JUSTIN HAWLEY
Insulation 1/3/2024 Approved JUSTIN HAWLEY
Drywall Nailing 1/5/2024 Approved BRENDAN MORELLI
Interior/Exterior Lathing 3/13/2024 Approved JUSTIN HAWLEY
Shower Pan 3/13/2024 Approved JUSTIN HAWLEY
Final 6/4/2024 Corrections Issued JUSTIN HAWLEY
Green Building Final 6/4/2024 Approved JUSTIN HAWLEY
MERV13>=Final 6/4/2024 Approved JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 6/4/2024 SGSOV Approved JUSTIN HAWLEY
Smoke Detectors 6/4/2024 Approved JUSTIN HAWLEY
ELECTRICAL-Final 6/10/2024 Approved JUSTIN HAWLEY
Final 6/10/2024 OK to Issue CofO JUSTIN HAWLEY
HVAC-Final 6/10/2024 Approved JUSTIN HAWLEY
PLUMBING-Final 6/10/2024 Approved JUSTIN HAWLEY