5753 N NATICK AVE 91411
Certificate Information: 5753 N NATICK AVE 91411
- Application / Permit
- 23014-10000-01927
- Plan Check / Job No.
- B23LA09135
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 12'10" X 17'6" ADDITION AND REMODEL OF (E) SINGLE FAMILY DWELLING TO ENLARGE MASTER BEDROOM, ADD A NEW BATHROOM AND CLOSET, REMODEL KITCHEN AND EXISTING BATHROOMS, AND REMOVE AND REPLACE ALL WINDOWS. WORK DONE PER ARCHITECT.
- Permit Issued
- Issued on 6/9/2023
- Issuing Office
- Current Status
- CofO in Progress on 3/5/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/17/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/23/2023 | MADISON ODELL |
| Corrections Issued | 5/24/2023 | MADISON ODELL |
| Plan Check Approved | 6/7/2023 | MADISON ODELL |
| Issued | 6/9/2023 | APPLICANT |
| CofO in Progress | 3/5/2024 | RYAN SALAZAR |
| CofO in Progress | 3/8/2024 | RYAN SALAZAR |
| CofO in Progress | 5/7/2024 | RYAN SALAZAR |
| CofO in Progress | 1/15/2025 | RAUL OLAGI |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 6/5/2023 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/6/2023 | ROMAN GUTIERREZ |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: NA30383 | , |
| Contractor | Better Together Builders Inc; Lic. No.: 1047689-B | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/31/2023 | Corrections Issued | RYAN SALAZAR |
| PLUMBING-Rough | 7/31/2023 | Partial Approval | RYAN SALAZAR |
| Underground Mechanical | 7/31/2023 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 8/21/2023 | Not Ready for Inspection | RYAN SALAZAR |
| PLUMBING-Rough | 8/21/2023 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 9/5/2023 | Corrections Issued | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 9/5/2023 | Partial Approval | RYAN SALAZAR |
| Green Building Rough | 9/5/2023 | Approved | RYAN SALAZAR |
| Rough-Elec/Plmb/HVAC | 9/5/2023 | Approved | RYAN SALAZAR |
| Shower Pan | 9/5/2023 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 9/13/2023 | Partial Approval | RYAN SALAZAR |
| Insulation | 9/21/2023 | Partial Approval | RYAN SALAZAR |
| Drywall Nailing | 10/2/2023 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 10/2/2023 | Approved | MICHEL ABAJAN |
| Sewer | 12/11/2023 | Corrections Issued | RYAN SALAZAR |
| BUILDING-Rough-Frame | 1/19/2024 | Approved | RYAN SALAZAR |
| Final | 1/19/2024 | Corrections Issued | RYAN SALAZAR |
| Footing/Foundation/Slab | 1/19/2024 | Approved | RYAN SALAZAR |
| Green Building Final | 1/19/2024 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 1/19/2024 | SGSOV Approved | RYAN SALAZAR |
| Smoke Detectors | 1/19/2024 | Approved | RYAN SALAZAR |
| Final | 3/5/2024 | Not Ready for Inspection | RYAN SALAZAR |
| Final | 3/11/2024 | Corrections Issued | RYAN SALAZAR |
| Final | 3/18/2024 | Partial Inspection | RYAN SALAZAR |
| Final | 3/21/2024 | Partial Approval | RYAN SALAZAR |
| Final | 5/6/2024 | Corrections Issued | RYAN SALAZAR |
| Special/Order Compliance | 1/14/2025 | Corrections Issued | RYAN SALAZAR |