14531 W ADDISON ST 91403
Certificate Information: 14531 W ADDISON ST 91403
- Application / Permit
- 23014-10000-01926
- Plan Check / Job No.
- B23LA09134
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: One story addition to rear of dwelling to enlarge bedroom and add closet with full bathroom. Interior remodel to existing portion of dwelling to kitchen, bathrooms and bedrooms. Create new laundry room.
- Permit Issued
- Issued on 6/7/2023
- Issuing Office
- Current Status
- CofO Issued on 5/31/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/17/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/23/2023 | DANIEL SMILEY |
| Corrections Issued | 5/24/2023 | DANIEL SMILEY |
| Applicant returned to address corrections | 6/2/2023 | HANS SANTIAGO |
| Plan Check Approved | 6/7/2023 | RICARDO RAMIREZ |
| Issued | 6/7/2023 | APPLICANT |
| CofO in Progress | 5/28/2024 | JACK KARGODORIAN |
| Permit Finaled | 5/31/2024 | RUBEN SALAS |
| CofO Issued | 5/31/2024 | RUBEN SALAS |
| Permit Finaled | 5/31/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/25/2023 | RYAN KIM |
| Roof/Waste drainage to street | Cleared | 5/25/2023 | RYAN KIM |
| Sewer availability | Cleared | 5/25/2023 | RYAN KIM |
| ZI | Cleared | 5/31/2023 | ASHLEY RODARTE |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: C30383 | 5739 KANAN ROAD # 133 AGOURA HILLS, CA 91301 |
| Contractor | Power Roofing Inc; Lic. No.: 1073368-B | , |
Inspector Information
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/26/2023 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Rough | 6/26/2023 | Partial Approval | THOMAS FINNILA |
| Sewer | 6/26/2023 | Not Ready for Inspection | THOMAS FINNILA |
| Footing/Foundation/Slab | 6/29/2023 | Corrections Issued | ARAM AVEDISIAN |
| PLUMBING-Rough | 6/29/2023 | Partial Approval | ARAM AVEDISIAN |
| Deputy Drilled-In Anchors | 6/30/2023 | Conditional Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 7/11/2023 | Corrections Issued | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 7/26/2023 | Not Ready for Inspection | THOMAS FINNILA |
| Deputy Drilled-In Anchors | 8/10/2023 | Conditional Approval | DAVID MATSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/11/2023 | Corrections Issued | THOMAS FINNILA |
| Rough-Elec/Plmb/HVAC | 8/11/2023 | Partial Approval | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 8/15/2023 | Partial Approval | THOMAS FINNILA |
| Rough-Elec/Plmb/HVAC | 8/15/2023 | Not Ready for Inspection | THOMAS FINNILA |
| Deputy Wood Construction | 8/18/2023 | Conditional Approval | JUAN VALENZUELA |
| ELECTRICAL-Rough | 8/18/2023 | Approved | THOMAS FINNILA |
| HVAC-Rough | 8/18/2023 | Approved | THOMAS FINNILA |
| BUILDING-Rough-Frame | 8/22/2023 | Conditional Approval | THOMAS FINNILA |
| Insulation | 8/24/2023 | Approved | THOMAS FINNILA |
| Shower Pan | 8/24/2023 | Approved | THOMAS FINNILA |
| Green Building Rough | 8/25/2023 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 8/25/2023 | Conditional Approval | THOMAS FINNILA |
| Drywall Nailing | 8/31/2023 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 8/31/2023 | Approved | RYAN SALAZAR |
| Green Building Final | 12/15/2023 | Not Ready for Inspection | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 12/15/2023 | SGSOV Not Ready | THOMAS FINNILA |
| Smoke Detectors | 12/15/2023 | Not Ready for Inspection | THOMAS FINNILA |
| Final | 2/8/2024 | Not Ready for Inspection | THOMAS FINNILA |
| Green Building Final | 2/8/2024 | Not Ready for Inspection | THOMAS FINNILA |
| Smoke Detectors | 2/8/2024 | Not Ready for Inspection | THOMAS FINNILA |
| BUILDING-Rough-Frame | 4/11/2024 | Approved | THOMAS FINNILA |
| Final | 4/11/2024 | Corrections Issued | THOMAS FINNILA |
| Footing/Foundation/Slab | 4/11/2024 | Approved | THOMAS FINNILA |
| Green Building Final | 4/11/2024 | Approved | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 4/11/2024 | SGSOV Approved | THOMAS FINNILA |
| Smoke Detectors | 4/11/2024 | Approved | THOMAS FINNILA |
| Final | 5/22/2024 | Corrections Issued | JACK KARGODORIAN |
| Final | 5/24/2024 | OK to Issue CofO | JACK KARGODORIAN |
| Pre-Inspection | 5/24/2024 | Approved | JACK KARGODORIAN |