14531 W ADDISON ST 91403

Certificate Information: 14531 W ADDISON ST 91403

Application / Permit
23014-10000-01926
Plan Check / Job No.
B23LA09134
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: One story addition to rear of dwelling to enlarge bedroom and add closet with full bathroom. Interior remodel to existing portion of dwelling to kitchen, bathrooms and bedrooms. Create new laundry room.
Permit Issued
Issued on 6/7/2023
Issuing Office
Current Status
CofO Issued on 5/31/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/17/2023 APPLICANT
Assigned to Plan Check Engineer 5/23/2023 DANIEL SMILEY
Corrections Issued 5/24/2023 DANIEL SMILEY
Applicant returned to address corrections 6/2/2023 HANS SANTIAGO
Plan Check Approved 6/7/2023 RICARDO RAMIREZ
Issued 6/7/2023 APPLICANT
CofO in Progress 5/28/2024 JACK KARGODORIAN
Permit Finaled 5/31/2024 RUBEN SALAS
CofO Issued 5/31/2024 RUBEN SALAS
Permit Finaled 5/31/2024 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/25/2023 RYAN KIM
Roof/Waste drainage to street Cleared 5/25/2023 RYAN KIM
Sewer availability Cleared 5/25/2023 RYAN KIM
ZI Cleared 5/31/2023 ASHLEY RODARTE

Contact Information

Architect Dembsky,, Amit; Lic. No.: C30383 5739 KANAN ROAD # 133      AGOURA HILLS, CA 91301
Contractor Power Roofing Inc; Lic. No.: 1073368-B       ,

Inspector Information

RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/26/2023 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 6/26/2023 Partial Approval THOMAS FINNILA
Sewer 6/26/2023 Not Ready for Inspection THOMAS FINNILA
Footing/Foundation/Slab 6/29/2023 Corrections Issued ARAM AVEDISIAN
PLUMBING-Rough 6/29/2023 Partial Approval ARAM AVEDISIAN
Deputy Drilled-In Anchors 6/30/2023 Conditional Approval THOMAS FINNILA
Footing/Foundation/Slab 7/11/2023 Corrections Issued THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 7/26/2023 Not Ready for Inspection THOMAS FINNILA
Deputy Drilled-In Anchors 8/10/2023 Conditional Approval DAVID MATSON
Floor/Roof Diaphrgm/Shear Wall 8/11/2023 Corrections Issued THOMAS FINNILA
Rough-Elec/Plmb/HVAC 8/11/2023 Partial Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 8/15/2023 Partial Approval THOMAS FINNILA
Rough-Elec/Plmb/HVAC 8/15/2023 Not Ready for Inspection THOMAS FINNILA
Deputy Wood Construction 8/18/2023 Conditional Approval JUAN VALENZUELA
ELECTRICAL-Rough 8/18/2023 Approved THOMAS FINNILA
HVAC-Rough 8/18/2023 Approved THOMAS FINNILA
BUILDING-Rough-Frame 8/22/2023 Conditional Approval THOMAS FINNILA
Insulation 8/24/2023 Approved THOMAS FINNILA
Shower Pan 8/24/2023 Approved THOMAS FINNILA
Green Building Rough 8/25/2023 Approved THOMAS FINNILA
Interior/Exterior Lathing 8/25/2023 Conditional Approval THOMAS FINNILA
Drywall Nailing 8/31/2023 Approved RYAN SALAZAR
Interior/Exterior Lathing 8/31/2023 Approved RYAN SALAZAR
Green Building Final 12/15/2023 Not Ready for Inspection THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 12/15/2023 SGSOV Not Ready THOMAS FINNILA
Smoke Detectors 12/15/2023 Not Ready for Inspection THOMAS FINNILA
Final 2/8/2024 Not Ready for Inspection THOMAS FINNILA
Green Building Final 2/8/2024 Not Ready for Inspection THOMAS FINNILA
Smoke Detectors 2/8/2024 Not Ready for Inspection THOMAS FINNILA
BUILDING-Rough-Frame 4/11/2024 Approved THOMAS FINNILA
Final 4/11/2024 Corrections Issued THOMAS FINNILA
Footing/Foundation/Slab 4/11/2024 Approved THOMAS FINNILA
Green Building Final 4/11/2024 Approved THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 4/11/2024 SGSOV Approved THOMAS FINNILA
Smoke Detectors 4/11/2024 Approved THOMAS FINNILA
Final 5/22/2024 Corrections Issued JACK KARGODORIAN
Final 5/24/2024 OK to Issue CofO JACK KARGODORIAN
Pre-Inspection 5/24/2024 Approved JACK KARGODORIAN