3773 S CIMARRON ST 90018
Certificate Information: 3773 S CIMARRON ST 90018
- Application / Permit
- 23014-10000-01920
- Plan Check / Job No.
- B23LA09098
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan - convert (e) garage to detached ADU, addition to detached ADU per LAMC 12.22 A.33 (c)(d) R3 occupancy
- Permit Issued
- Issued on 11/21/2023
- Issuing Office
- Current Status
- Issued on 11/21/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/17/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/18/2023 | KELVIN CHUONG |
| Corrections Issued | 5/23/2023 | KELVIN CHUONG |
| Quality Review Completed | 5/25/2023 | RODOLFO ARIAS |
| Applicant returned to address corrections | 10/30/2023 | KELVIN CHUONG |
| Applicant returned to address corrections | 11/7/2023 | KELVIN CHUONG |
| Applicant returned to address corrections | 11/17/2023 | KELVIN CHUONG |
| Plan Check Approved | 11/20/2023 | KELVIN CHUONG |
| Issued | 11/21/2023 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/1/2023 | ARMEN MEHRABIAN |
| Metro Rail approval | Cleared | 7/7/2023 | JENNIFER SU |
| Address approval | Cleared | 7/9/2023 | AHMED AMARRAGY |
| Sewer availability | Cleared | 7/9/2023 | AHMED AMARRAGY |
| Roof/Waste drainage to street | Cleared | 7/10/2023 | HUGO LOPEZ |
| Construction near power lines | Cleared | 10/6/2023 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 7/30/2024 | Approved | SABAS ALONSO |
| Underground Mechanical | 7/30/2024 | Approved | SABAS ALONSO |
| Deputy Drilled-In Anchors | 8/2/2024 | Conditional Approval | SABAS ALONSO |
| Excavation/Setback/Form/Re-Bar | 8/6/2024 | Corrections Issued | SABAS ALONSO |
| Excavation/Setback/Form/Re-Bar | 8/8/2024 | Corrections Issued | SABAS ALONSO |
| Deputy Drilled-In Anchors | 10/8/2025 | Conditional Approval | SABAS ALONSO |
| Deputy Wood Construction | 10/8/2025 | Conditional Approval | SABAS ALONSO |
| HVAC-Rough | 10/14/2025 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 10/16/2025 | Corrections Issued | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 10/23/2025 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 6/1/2026 | Approved | SABAS ALONSO |
| ELECTRICAL-Rough | 6/1/2026 | Approved | SABAS ALONSO |
| Green Building Rough | 6/1/2026 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 6/1/2026 | Partial Approval | SABAS ALONSO |
| PLUMBING-Rough | 6/1/2026 | Approved | SABAS ALONSO |
| Shower Pan | 6/1/2026 | Approved | SABAS ALONSO |
| Insulation | 6/5/2026 | No Result Entered | SABAS ALONSO |