11821 W JUNIETTE ST 90230
Certificate Information: 11821 W JUNIETTE ST 90230
- Application / Permit
- 23014-10000-01919
- Plan Check / Job No.
- B23LA09094
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 15'-1" X 18'-6 ADDITION AND CONVERT GARAGE INTO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d) - PER ENGINEER
- Permit Issued
- Issued on 3/4/2024
- Issuing Office
- Current Status
- CofO Issued on 4/21/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/22/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/25/2023 | DANIEL ABRAMYAN |
| Corrections Issued | 5/25/2023 | DANIEL ABRAMYAN |
| Applicant returned to address corrections | 5/26/2023 | DANIEL ABRAMYAN |
| Applicant returned to address corrections | 11/29/2023 | DANIEL ABRAMYAN |
| Applicant returned to address corrections | 1/12/2024 | DANIEL ABRAMYAN |
| Applicant returned to address corrections | 1/23/2024 | DANIEL ABRAMYAN |
| Applicant returned to address corrections | 2/5/2024 | DANIEL ABRAMYAN |
| Plan Check Approved | 2/16/2024 | DANIEL ABRAMYAN |
| Issued | 3/4/2024 | APPLICANT |
| CofO in Progress | 4/2/2025 | DAVID FEILER |
| Permit Finaled | 4/21/2025 | RICHARD STEINBACH |
| CofO Issued | 4/21/2025 | RICHARD STEINBACH |
| Permit Finaled | 4/21/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 6/15/2023 | JASON NG |
| Eng Process Fee Ord 176,300 | Cleared | 6/28/2023 | JASON NG |
| Sewer availability | Cleared | 6/28/2023 | JASON NG |
| Specific Plan | Cleared | 11/8/2023 | ALESSANDRO MERCURI |
| Construction near power lines | Cleared | 11/28/2023 | OSCAR CASTRO |
| Roof/Waste drainage to street | Cleared | 11/28/2023 | ANDREA SAINT-ANTONIN |
Contact Information
| Contractor | Reds General Construction Inc; Lic. No.: 1061700-B | , |
| Engineer | Lu,, Yi; Lic. No.: S5678 | P O BOX 2754 PALOS VERDES PENINSULA, CA 90274 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/23/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Sewer | 4/23/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Sewer | 5/6/2024 | Approved | TEMISTOCLES CAAL |
| Excavation/Setback/Form/Re-Bar | 7/1/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 7/1/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Excavation/Setback/Form/Re-Bar | 7/10/2024 | Approved | HERBERT GIRON |
| Footing/Foundation/Slab | 7/10/2024 | Approved | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 7/31/2024 | Partial Approval | TEMISTOCLES CAAL |
| Special/Order Compliance | 7/31/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Underground Mechanical | 8/7/2024 | Approved | TEMISTOCLES CAAL |
| Gas Test | 11/1/2024 | Approved | MICHAEL ALLEN |
| Service/Power Release | 12/11/2024 | Corrections Issued | MICHAEL ALLEN |
| Service/Power Release | 12/16/2024 | Approved | MICHAEL ALLEN |
| BUILDING-Rough-Frame | 2/25/2025 | Approved | MICHAEL ALLEN |
| Drywall Nailing | 2/25/2025 | Approved | MICHAEL ALLEN |
| ELECTRICAL-Final | 2/25/2025 | Approved | MICHAEL ALLEN |
| Final | 2/25/2025 | Corrections Issued | MICHAEL ALLEN |
| HVAC-Final | 2/25/2025 | Approved | MICHAEL ALLEN |
| MERV13>=Final | 2/25/2025 | Approved | MICHAEL ALLEN |
| MERV13>=Rough | 2/25/2025 | Approved | MICHAEL ALLEN |
| PLUMBING-Final | 2/25/2025 | Approved | MICHAEL ALLEN |
| SGSOV-Seismic Gas S/O Valve | 2/25/2025 | SGSOV Approved | MICHAEL ALLEN |
| Smoke Detectors | 2/25/2025 | Approved | MICHAEL ALLEN |
| Final | 4/1/2025 | OK to Issue CofO | RUBEN RIVAS |
| Service/Power Release | 4/12/2025 | Approved | DAVID FEILER |