2021 1/4-1/2 E CITY VIEW AVE 90033

Certificate Information: 2021 1/4-1/2 E CITY VIEW AVE 90033

Application / Permit
23014-10000-01916
Plan Check / Job No.
B23LA09085
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(E) DETACHED GARAGE TO BE CONVERTED TO ADU (378SF) AND ADDITION OF ANOTHER ADU (242SF) PER STATE CODE
Permit Issued
Issued on 10/19/2023
Issuing Office
Metro
Current Status
CofO Issued on 9/17/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/16/2023 APPLICANT
Assigned to Plan Check Engineer 6/1/2023 JOE VO
Corrections Issued 7/11/2023 JOE VO
Quality Review Completed 7/14/2023 KEN GILL
Building Plans Picked Up 7/20/2023 APPLICANT
Plan Check Approved 9/20/2023 JOE VO
Issued 10/19/2023 APPLICANT
CofO in Progress 8/28/2024 LUIS CASTRO
CofO Issued 9/17/2024 DEROLD HAUFF
Permit Finaled 9/17/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/14/2023 JEANIE LAM
Roof/Waste drainage to street Cleared 8/14/2023 JEANIE LAM
Tenant Habitability Plan Cleared 8/14/2023 RICARDO BOHORQUEZ
Eng Process Fee Ord 176,300 Cleared 8/15/2023 JEANIE LAM
Sewer availability Cleared 8/15/2023 JEANIE LAM
Grading Pre-Inspection Cleared 8/16/2023 SERGIO VALENZUELA
Construction near power lines Cleared 8/18/2023 RIDWAN HARDY
Hydrant and Access approval Cleared 9/8/2023 JOHN CONNEALLY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/13/2023 Partial Approval OSVALDO PARAMO
Sewer 12/13/2023 Partial Inspection OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 12/21/2023 Corrections Issued OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 12/27/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
Excavation/Setback/Form/Re-Bar 1/12/2024 Conditional Approval ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 2/2/2024 Approved OSVALDO PARAMO
ELECTRICAL-Rough 3/28/2024 Approved OSVALDO PARAMO
HVAC-Rough 3/28/2024 Approved OSVALDO PARAMO
PLUMBING-Rough 3/28/2024 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 4/1/2024 Approved OSVALDO PARAMO
Green Building Rough 4/1/2024 Approved OSVALDO PARAMO
Interior/Exterior Lathing 4/1/2024 Partial Approval OSVALDO PARAMO
MERV13>=Rough 4/1/2024 Approved OSVALDO PARAMO
METHANE-Rough 4/1/2024 Approved OSVALDO PARAMO
Insulation 4/3/2024 Approved OSVALDO PARAMO
Drywall Nailing 4/8/2024 Approved OSVALDO PARAMO
Interior/Exterior Lathing 4/8/2024 Approved OSVALDO PARAMO
Sewer 5/7/2024 Approved ALIZAH MAYAGOITIA
Underground Mechanical 5/7/2024 Approved ALIZAH MAYAGOITIA
PLUMBING-Rough 7/31/2024 Approved OSVALDO PARAMO
Final 8/14/2024 Corrections Issued OSVALDO PARAMO
Footing/Foundation/Slab 8/14/2024 Approved OSVALDO PARAMO
Green Building Final 8/14/2024 Approved OSVALDO PARAMO
MERV13>=Final 8/14/2024 Approved OSVALDO PARAMO
METHANE-Barrier 8/14/2024 Approved OSVALDO PARAMO
METHANE-Subgrade 8/14/2024 Approved OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 8/14/2024 SGSOV Not Ready OSVALDO PARAMO
Service/Power Release 8/14/2024 Approved OSVALDO PARAMO
Smoke Detectors 8/14/2024 Not Ready for Inspection OSVALDO PARAMO
Final 8/22/2024 Corrections Issued OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 8/22/2024 SGSOV Not Ready OSVALDO PARAMO
Smoke Detectors 8/22/2024 Approved OSVALDO PARAMO
Final 8/27/2024 OK to Issue CofO LUIS CASTRO
SGSOV-Seismic Gas S/O Valve 8/27/2024 SGSOV Approved LUIS CASTRO