19433 W VALERIO ST 91335

Certificate Information: 19433 W VALERIO ST 91335

Application / Permit
23014-10000-01897
Plan Check / Job No.
B23LA08992
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODEL 1 STORY ADDITION TO (E) SFD. SEE COMMENTS
Permit Issued
Issued on 8/28/2023
Issuing Office
Metro
Current Status
CofO Issued on 7/17/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/15/2023 APPLICANT
Assigned to Plan Check Engineer 5/18/2023 ZAW HAN
Corrections Issued 5/22/2023 ZAW HAN
Building Plans Picked Up 5/22/2023 APPLICANT
Plan Check Approved 7/18/2023 DANIEL SANJUAN
Issued 8/28/2023 APPLICANT
CofO in Progress 6/25/2024 JEFFREY BULL
Permit Finaled 7/17/2024 JOHN JANSON
CofO Issued 7/17/2024 JOHN JANSON
Permit Finaled 7/17/2024 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/25/2023 WALLIE JONG
Sewer availability Cleared 5/25/2023 WALLIE JONG
"T" removal Cleared 5/26/2023 JASON CHAN
Low Impact Development (LID) Cleared 6/27/2023 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 6/27/2023 WALLIE JONG
Hydrant and Access approval Cleared 7/13/2023 RUEL COLE

Contact Information

Contractor Joe Willie Corporation; Lic. No.: 1035837-B 12258 WOODRUFF AVE      DOWNEY, CA 90241
Engineer Rhee,, Kyle; Lic. No.: C78215 2753 WAVERLY DR 403      LOS ANGELES, CA 90039

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/7/2023 Approved JEFFREY BULL
Footing/Foundation/Slab 9/7/2023 Approved JEFFREY BULL
BUILDING-Rough-Frame 9/28/2023 Not Ready for Inspection JEFFREY BULL
Green Building Rough 9/28/2023 Not Ready for Inspection JEFFREY BULL
Pre-Inspection 9/28/2023 Not Ready for Inspection JEFFREY BULL
Floor/Roof Diaphrgm/Shear Wall 10/26/2023 Partial Approval JEFFREY BULL
Floor/Roof Diaphrgm/Shear Wall 11/17/2023 Approved JEFFREY BULL
Special/Order Compliance 11/17/2023 Corrections Issued JEFFREY BULL
ELECTRICAL-Rough 12/4/2023 Approved JEFFREY BULL
PLUMBING-Rough 12/4/2023 Approved JEFFREY BULL
Insulation 12/15/2023 Corrections Issued JEFFREY BULL
Interior/Exterior Lathing 12/15/2023 Partial Approval JEFFREY BULL
Drywall Nailing 1/3/2024 Approved JEFFREY BULL
Green Building Rough 1/3/2024 Approved JEFFREY BULL
BUILDING-Rough-Frame 4/1/2024 Approved JEFFREY BULL
ELECTRICAL-Final 4/1/2024 Approved JEFFREY BULL
Final 4/1/2024 Corrections Issued JEFFREY BULL
Green Building Final 4/1/2024 Not Ready for Inspection JEFFREY BULL
PLUMBING-Final 4/1/2024 Approved JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 4/1/2024 SGSOV Approved JEFFREY BULL
Smoke Detectors 4/1/2024 Approved JEFFREY BULL
Final 6/25/2024 OK to Issue CofO JEFFREY BULL
Green Building Final 6/25/2024 Approved JEFFREY BULL