7511 S AIRPORT BLVD 90045
Certificate Information: 7511 S AIRPORT BLVD 90045
- Application / Permit
- 23014-10000-01896
- Plan Check / Job No.
- B23LA08991
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2ND FLOOR ADU ABOVE DETACHED GARAGE PER LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 11/2/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/4/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/15/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/1/2023 | SERGIO GUTIERREZ |
| Corrections Issued | 6/6/2023 | SERGIO GUTIERREZ |
| Quality Review Completed | 6/6/2023 | KEN GILL |
| Building Plans Picked Up | 6/8/2023 | APPLICANT |
| Applicant returned to address corrections | 9/14/2023 | SERGIO GUTIERREZ |
| Plan Check Approved | 10/24/2023 | SERGIO GUTIERREZ |
| Issued | 11/2/2023 | APPLICANT |
| CofO in Progress | 7/8/2024 | JOHN MATTILLO |
| Permit Finaled | 12/4/2025 | CLAUDIO MORENO |
| CofO Issued | 12/4/2025 | CLAUDIO MORENO |
| Permit Finaled | 12/4/2025 | CLAUDIO MORENO |
Permit Application Clearance Information
| Address approval | Cleared | 6/7/2023 | LIAM ODONOVAN |
| Eng Process Fee Ord 176,300 | Cleared | 6/7/2023 | LIAM ODONOVAN |
| Grading Pre-Inspection | Cleared | 6/8/2023 | SERGIO VALENZUELA |
| Sewer availability | Cleared | 6/16/2023 | JASON NG |
| Low Impact Development (LID) | Cleared | 6/21/2023 | TOMMY YIN |
| Specific Plan | Cleared | 6/23/2023 | EDUARDO HERMOSO |
| Roof/Waste drainage to street | Cleared | 6/28/2023 | JASON NG |
| Construction near power lines | Cleared | 8/7/2023 | RIDWAN HARDY |
| Construction within easement | Cleared | 8/7/2023 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 8/9/2023 | KURT CORRAL |
Contact Information
| Contractor | Murrieta General Construction Inc; Lic. No.: 939792-B | 5045 FALCON AVE LONG BEACH, CA 90807 |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| ROBERT GARTH, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN MATTILLO, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PEDRO RIVERA, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| EUSEBIO GUZMAN, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PAUL REECE, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| ANDREW BEELI, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 11/8/2023 | Not Ready for Inspection | ANDREW BEELI |
| Footing/Foundation/Slab | 11/8/2023 | Not Ready for Inspection | ANDREW BEELI |
| Green Building Rough | 11/8/2023 | Not Ready for Inspection | ANDREW BEELI |
| PLUMBING-Rough | 11/8/2023 | Corrections Issued | ANDREW BEELI |
| BUILDING-Rough-Frame | 11/16/2023 | Corrections Issued | ANDREW BEELI |
| ELECTRICAL-Rough | 11/16/2023 | Not Ready for Inspection | ANDREW BEELI |
| Gas Test | 11/16/2023 | Not Ready for Inspection | ANDREW BEELI |
| Green Building Rough | 11/16/2023 | Not Ready for Inspection | ANDREW BEELI |
| PLUMBING-Rough | 11/16/2023 | Not Ready for Inspection | ANDREW BEELI |
| ELECTRICAL-Rough | 11/21/2023 | Not Ready for Inspection | ANDREW BEELI |
| Footing/Foundation/Slab | 11/21/2023 | Partial Approval | ANDREW BEELI |
| PLUMBING-Rough | 11/21/2023 | Corrections Issued | ANDREW BEELI |
| BUILDING-Rough-Frame | 12/5/2023 | Partial Approval | ANDREW BEELI |
| Green Building Rough | 12/5/2023 | Partial Approval | ANDREW BEELI |
| PLUMBING-Rough | 12/5/2023 | Partial Approval | ANDREW BEELI |
| Insulation | 12/21/2023 | Partial Approval | ANDREW BEELI |
| Interior/Exterior Lathing | 12/21/2023 | Corrections Issued | ANDREW BEELI |
| Drywall Nailing | 12/28/2023 | Partial Approval | ANDREW BEELI |
| Interior/Exterior Lathing | 12/28/2023 | Partial Approval | ANDREW BEELI |
| BUILDING-Rough-Frame | 1/24/2024 | Partial Approval | ANDREW BEELI |
| Green Building Rough | 1/24/2024 | Corrections Issued | ANDREW BEELI |
| Drywall Nailing | 2/9/2024 | Approved | ANDREW BEELI |
| Service/Power Release | 4/17/2024 | Corrections Issued | ANDREW BEELI |
| Service/Power Release | 4/19/2024 | Corrections Issued | JOHN MATTILLO |
| BUILDING-Rough-Frame | 5/7/2024 | Partial Approval | ANDREW BEELI |
| ELECTRICAL-Final | 5/7/2024 | Not Ready for Inspection | ANDREW BEELI |
| Final | 5/7/2024 | Not Ready for Inspection | ANDREW BEELI |
| Footing/Foundation/Slab | 5/7/2024 | Approved | ANDREW BEELI |
| Green Building Final | 5/7/2024 | Not Ready for Inspection | ANDREW BEELI |
| Green Building Rough | 5/7/2024 | Not Ready for Inspection | ANDREW BEELI |
| PLUMBING-Final | 5/7/2024 | Corrections Issued | ANDREW BEELI |
| SGSOV-Seismic Gas S/O Valve | 5/7/2024 | SGSOV No Gas | ANDREW BEELI |
| Service/Power Release | 5/7/2024 | Approved | ANDREW BEELI |
| Smoke Detectors | 5/7/2024 | Approved | ANDREW BEELI |
| BUILDING-Rough-Frame | 5/15/2024 | Approved | ANDREW BEELI |
| Final | 5/15/2024 | Not Ready for Inspection | ANDREW BEELI |
| Green Building Final | 5/15/2024 | Approved | ANDREW BEELI |
| Green Building Rough | 5/15/2024 | Approved | ANDREW BEELI |
| HVAC-Final | 5/16/2024 | Approved | ANDREW BEELI |
| ELECTRICAL-Final | 6/11/2024 | Approved | ANDREW BEELI |
| Final | 6/11/2024 | Corrections Issued | ANDREW BEELI |
| ELECTRICAL-Final | 6/12/2024 | Not Ready for Inspection | ANDREW BEELI |
| Final | 6/20/2024 | Not Ready for Inspection | ANDREW BEELI |
| HVAC-Final | 6/20/2024 | Corrections Issued | ANDREW BEELI |
| Final | 6/28/2024 | OK to Issue CofO | JOHN MATTILLO |
| HVAC-Final | 6/28/2024 | Approved | JOHN MATTILLO |