2219-2219 3/4 S 6TH AVE 90018
Certificate Information: 2219-2219 3/4 S 6TH AVE 90018
- Application / Permit
- 23014-10000-01887
- Plan Check / Job No.
- B23LA08958
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- NEW UNIT AND NEW REC ROOM ON 2ND STORY ATTACHED TO EXISTING 1 STORY DUPLEX
- Permit Issued
- Issued on 1/19/2024
- Issuing Office
- Current Status
- CofO Issued on 10/28/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/15/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/1/2023 | MARCELA FRANQUEZ |
| Corrections Issued | 6/9/2023 | MARCELA FRANQUEZ |
| Quality Review Completed | 6/21/2023 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 6/23/2023 | APPLICANT |
| Plan Check Approved | 1/11/2024 | MARCELA FRANQUEZ |
| Issued | 1/19/2024 | APPLICANT |
| CofO in Progress | 10/28/2024 | MARTIN TAVITIAN |
| CofO in Progress | 10/28/2024 | RAFAEL ESPINOZA |
| CofO in Progress | 10/28/2024 | RAFAEL ESPINOZA |
| CofO Issued | 10/28/2024 | RAFAEL ESPINOZA |
| Permit Finaled | 10/28/2024 | RAFAEL ESPINOZA |
Permit Application Clearance Information
| Address approval | Cleared | 6/14/2023 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 6/14/2023 | WALLIE JONG |
| DAS Clearance | Cleared | 6/15/2023 | MARCELA FRANQUEZ |
| Tenant Habitability Plan | Cleared | 6/20/2023 | RICARDO BOHORQUEZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/26/2023 | WALLIE JONG |
| Sewer availability | Cleared | 6/26/2023 | WALLIE JONG |
| Green Code | Cleared | 9/14/2023 | AARON COSTA |
| Community Plan Implem. Overlay | Cleared | 9/15/2023 | ISAIAH ROSS |
| ZI | Cleared | 9/15/2023 | ISAIAH ROSS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/15/2024 | Conditional Approval | MICHAEL ROSENBERG |
| Excavation/Setback/Form/Re-Bar | 2/16/2024 | Partial Approval | LUIS CCAMACHO |
| Pre-Inspection | 2/16/2024 | Partial Approval | LUIS CCAMACHO |
| Excavation/Setback/Form/Re-Bar | 2/29/2024 | Partial Approval | JEROME BLACKWOOD |
| Green Building Rough | 3/12/2024 | Approved | MARTIN TAVITIAN |
| METHANE-Rough | 3/12/2024 | Approved | MARTIN TAVITIAN |
| Wood Frame | 3/12/2024 | Partial Approval | MARTIN TAVITIAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/21/2024 | Partial Approval | MARTIN TAVITIAN |
| Wood Frame | 3/22/2024 | Not Ready for Inspection | MARTIN TAVITIAN |
| Deputy Wood Construction | 3/26/2024 | No Access for Inspection | MICHAEL ROSENBERG |
| Floor/Roof Diaphrgm/Shear Wall | 3/27/2024 | Partial Approval | JACOB MYERS |
| Interior/Exterior Lathing | 4/3/2024 | Partial Approval | JACOB MYERS |
| Wood Frame | 4/15/2024 | Not Ready for Inspection | MARTIN TAVITIAN |
| Interior/Exterior Lathing | 4/19/2024 | Partial Approval | MARTIN TAVITIAN |
| Special/Order Compliance | 5/14/2024 | Partial Approval | MARTIN TAVITIAN |
| Insulation | 6/5/2024 | Not Ready for Inspection | MARTIN TAVITIAN |
| Insulation | 6/7/2024 | Not Ready for Inspection | MARTIN TAVITIAN |
| Drywall Nailing | 6/18/2024 | Approved | MARTIN TAVITIAN |
| Final | 9/20/2024 | OK to Issue CofO | MARTIN TAVITIAN |
| Footing/Foundation/Slab | 9/20/2024 | Approved | MARTIN TAVITIAN |
| Green Building Final | 9/20/2024 | Approved | MARTIN TAVITIAN |
| METHANE-Barrier | 9/20/2024 | Approved | MARTIN TAVITIAN |
| METHANE-Subgrade | 9/20/2024 | Approved | MARTIN TAVITIAN |
| SGSOV-Seismic Gas S/O Valve | 9/20/2024 | SGSOV Approved | MARTIN TAVITIAN |
| Smoke Detectors | 9/20/2024 | Approved | MARTIN TAVITIAN |
| Wood Frame | 9/20/2024 | Approved | MARTIN TAVITIAN |