1633 N CURSON AVE 90046
Certificate Information: 1633 N CURSON AVE 90046
- Application / Permit
- 23014-10000-01885
- Plan Check / Job No.
- B23LA08952
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan: - ADDITION AND REMODEL TO (E) SFD
- Permit Issued
- Issued on 9/15/2023
- Issuing Office
- Current Status
- CofO Issued on 3/29/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/16/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/1/2023 | JAD BASMA |
| Corrections Issued | 6/8/2023 | JAD BASMA |
| Quality Review Completed | 6/16/2023 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 7/10/2023 | JAD BASMA |
| Applicant returned to address corrections | 7/21/2023 | JAD BASMA |
| Plan Check Approved | 9/14/2023 | JAD BASMA |
| Issued | 9/15/2023 | APPLICANT |
| CofO in Progress | 3/26/2024 | JOSEPH MCGARRY |
| Permit Finaled | 3/29/2024 | DEROLD HAUFF |
| CofO Issued | 3/29/2024 | DEROLD HAUFF |
| Permit Finaled | 3/29/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 7/15/2023 | HUGO LOPEZ |
| Sewer availability | Cleared | 7/15/2023 | HUGO LOPEZ |
| HPOZ | Cleared | 7/19/2023 | ERIK VAN BREENE |
| Eng Process Fee Ord 176,300 | Cleared | 7/20/2023 | HUGO LOPEZ |
Contact Information
| Architect | Offenhauser,, Frances A; Lic. No.: NA11186 | , |
| Contractor | Centrepoint Construction Inc; Lic. No.: 1032400-B | , |
| Contractor | Centrepoint Glass & Windows; Lic. No.: 1032400-B | , |
| Engineer | Parker,, Leo Augustine; Lic. No.: NA2829 | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/26/2023 | Partial Inspection | STUART CHAPMAN |
| Deputy Drilled-In Anchors | 10/5/2023 | Conditional Approval | STUART CHAPMAN |
| Excavation/Setback/Form/Re-Bar | 10/6/2023 | Approved | RAUL BARAJAS |
| Footing/Foundation/Slab | 10/6/2023 | Approved | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 10/19/2023 | Partial Approval | RAUL BARAJAS |
| PLUMBING-Rough | 10/19/2023 | Partial Approval | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 10/23/2023 | Partial Approval | STUART CHAPMAN |
| Insulation | 10/23/2023 | Partial Approval | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/25/2023 | No Access for Inspection | STUART CHAPMAN |
| Insulation | 10/25/2023 | No Access for Inspection | STUART CHAPMAN |
| Deputy Steel/Welding | 10/31/2023 | Conditional Approval | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/2/2023 | Not Ready for Inspection | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/6/2023 | Partial Approval | STUART CHAPMAN |
| BUILDING-Rough-Frame | 11/27/2023 | Corrections Issued | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/27/2023 | Approved | BRIAN SULLIVAN |
| Green Building Rough | 11/27/2023 | Approved | BRIAN SULLIVAN |
| Rough-Elec/Plmb/HVAC | 11/27/2023 | Approved | BRIAN SULLIVAN |
| Shower Pan | 12/14/2023 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 12/28/2023 | Approved | RAUL BARAJAS |
| Insulation | 12/28/2023 | Approved | RAUL BARAJAS |
| Drywall Nailing | 1/8/2024 | Approved | ROY SPAULDING |
| Interior/Exterior Lathing | 1/8/2024 | Approved | ROY SPAULDING |
| Final | 3/20/2024 | OK to Issue CofO | JOSEPH MCGARRY |
| Green Building Final | 3/20/2024 | Approved | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 3/20/2024 | SGSOV Approved | JOSEPH MCGARRY |
| Service/Power Release | 3/20/2024 | Approved | JOSEPH MCGARRY |
| Smoke Detectors | 3/20/2024 | Approved | JOSEPH MCGARRY |