14921 W TUBA ST 91345

Certificate Information: 14921 W TUBA ST 91345

Application / Permit
23014-10000-01863
Plan Check / Job No.
B23LA08886
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 22'-5" x 35'-1" (499 SF) ADDITION AT THE REAR OF THE EXISTING 1-STORY SINGLE-FAMILY DWELLING. ALL WORK DONE PER AN ENGINEERED DESIGN.
Permit Issued
Issued on 6/10/2024
Issuing Office
Valley
Current Status
CofO Issued on 9/25/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/12/2023 APPLICANT
Assigned to Plan Check Engineer 5/15/2023 KHUONG TRUONG
Corrections Issued 5/16/2023 KHUONG TRUONG
Building Plans Picked Up 5/23/2023 APPLICANT
Plan Check Approved 11/13/2023 DANIEL SMILEY
Issued 6/10/2024 APPLICANT
CofO in Progress 9/11/2024 JENNIFER RABUCHIN
CofO Issued 9/25/2024 DANIEL ORRANTE
Permit Finaled 9/25/2024 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/18/2023 COLIN LOREDO
Sewer availability Cleared 8/18/2023 COLIN LOREDO
Roof/Waste drainage to street Cleared 11/13/2023 COLIN LOREDO

Contact Information

Contractor R & M Construction; Lic. No.: 847093-B 11329 COLLETT AVE      GRANADA HILLS, CA 91344
Engineer Le,, Thang Huu; Lic. No.: S4978 507 MAGELLAN RD      ARCADIA, CA 91007

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/12/2024 Conditional Approval DAVID MATSON
Footing/Foundation/Slab 6/13/2024 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 6/20/2024 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 6/20/2024 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 6/25/2024 Partial Approval JENNIFER RABUCHIN
Deputy Wood Construction 7/10/2024 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 7/10/2024 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 7/16/2024 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 7/16/2024 Approved JENNIFER RABUCHIN
Green Building Rough 7/16/2024 Not Ready for Inspection JENNIFER RABUCHIN
HVAC-Rough 7/16/2024 Approved JENNIFER RABUCHIN
PLUMBING-Rough 7/16/2024 Approved JENNIFER RABUCHIN
Green Building Final 7/17/2024 Approved JENNIFER RABUCHIN
Insulation 7/17/2024 Approved JENNIFER RABUCHIN
Drywall Nailing 7/22/2024 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 7/22/2024 Partial Approval JENNIFER RABUCHIN
Service/Power Release 9/4/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 9/4/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 9/10/2024 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 9/10/2024 Approved JENNIFER RABUCHIN
Final 9/10/2024 OK to Issue CofO JENNIFER RABUCHIN
Green Building Rough 9/10/2024 Approved JENNIFER RABUCHIN
HVAC-Final 9/10/2024 Approved JENNIFER RABUCHIN
PLUMBING-Final 9/10/2024 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 9/10/2024 SGSOV Approved JENNIFER RABUCHIN
Service/Power Release 9/10/2024 Approved JENNIFER RABUCHIN
Smoke Detectors 9/10/2024 Approved JENNIFER RABUCHIN
Special/Order Compliance 9/10/2024 Approved JENNIFER RABUCHIN