4314 N CAMELLIA AVE 91604

Certificate Information: 4314 N CAMELLIA AVE 91604

Application / Permit
23014-10000-01840
Plan Check / Job No.
B23LA08781
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERSION (E) GARAGE TO ADU W/ 1 STORY ADDITION PER STATE LAW
Permit Issued
Issued on 3/20/2024
Issuing Office
Valley
Current Status
CofO Issued on 1/17/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/11/2023 APPLICANT
Assigned to Plan Check Engineer 5/15/2023 KHUONG TRUONG
Corrections Issued 5/15/2023 KHUONG TRUONG
Building Plans Picked Up 5/19/2023 APPLICANT
Applicant returned to address corrections 9/21/2023 KHUONG TRUONG
Plan Check Approved 2/14/2024 DANIEL SANJUAN
Issued 3/20/2024 APPLICANT
CofO in Progress 1/15/2025 RAUL OLAGI
Permit Finaled 1/17/2025 RUBEN SALAS
CofO Issued 1/17/2025 RUBEN SALAS
Permit Finaled 1/17/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/8/2023 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 6/8/2023 DAGOVERTO GUERRERO
Roof/Waste drainage to street Cleared 6/8/2023 DAGOVERTO GUERRERO
Sewer availability Cleared 6/8/2023 DAGOVERTO GUERRERO
ZI Cleared 6/14/2023 NELSON RODRIGUEZ
Construction near power lines Cleared 2/3/2024 RIDWAN HARDY

Contact Information

Architect Schneider,, Brent T; Lic. No.: C21821 2282 TOWNSGATE ROAD SUITE 3      WESTLAKE VILLAGE, CA 91361
Contractor Navarro Construction Inc; Lic. No.: 781996-B 3579 E FOOTHILL BLVD 259      PASADENA, CA 91107

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 4/15/2024 Approved CHRISTOPHER ROJAS
Footing/Foundation/Slab 4/19/2024 Approved CHRISTOPHER ROJAS
Deputy Reinf. Concrete 4/23/2024 Conditional Approval JUAN VALENZUELA
BUILDING-Rough-Frame 6/13/2024 Approved CHRISTOPHER ROJAS
ELECTRICAL-Rough 6/13/2024 Partial Approval CHRISTOPHER ROJAS
Green Building Rough 6/13/2024 Not Ready for Inspection CHRISTOPHER ROJAS
BUILDING-Rough-Frame 7/1/2024 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Rough 7/1/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Green Building Rough 7/1/2024 Not Ready for Inspection CHRISTOPHER ROJAS
HVAC-Rough 7/1/2024 Not Ready for Inspection CHRISTOPHER ROJAS
PLUMBING-Rough 7/1/2024 Not Ready for Inspection CHRISTOPHER ROJAS
BUILDING-Rough-Frame 7/12/2024 Approved CHRISTOPHER ROJAS
ELECTRICAL-Rough 7/12/2024 Approved CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 7/12/2024 Approved CHRISTOPHER ROJAS
Green Building Rough 7/12/2024 Approved CHRISTOPHER ROJAS
HVAC-Rough 7/12/2024 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 7/12/2024 Partial Inspection CHRISTOPHER ROJAS
PLUMBING-Rough 7/12/2024 Approved CHRISTOPHER ROJAS
Wood Frame 7/12/2024 Approved CHRISTOPHER ROJAS
Insulation 7/25/2024 Corrections Issued CHRISTOPHER ROJAS
Insulation 7/26/2024 Approved CHRISTOPHER ROJAS
Drywall Nailing 7/31/2024 Approved SALVADOR MARTINEZ
Interior/Exterior Lathing 7/31/2024 Approved SALVADOR MARTINEZ
Final 11/26/2024 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Final 12/30/2024 Partial Inspection CHRISTOPHER ROJAS
Final 12/30/2024 Corrections Issued CHRISTOPHER ROJAS
Green Building Final 12/30/2024 Approved CHRISTOPHER ROJAS
HVAC-Final 12/30/2024 Approved CHRISTOPHER ROJAS
PLUMBING-Final 12/30/2024 Approved CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 12/30/2024 SGSOV Approved CHRISTOPHER ROJAS
Service/Power Release 12/30/2024 Partial Inspection CHRISTOPHER ROJAS
Smoke Detectors 12/30/2024 Approved CHRISTOPHER ROJAS
ELECTRICAL-Final 1/14/2025 Approved RAUL OLAGI
Final 1/14/2025 OK to Issue CofO RAUL OLAGI