1626 S SYCAMORE AVE 90019

Certificate Information: 1626 S SYCAMORE AVE 90019

Application / Permit
23014-10000-01837
Plan Check / Job No.
B23LA08733
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New 1-story ADU per state law.
Permit Issued
Issued on 5/2/2024
Issuing Office
Metro
Current Status
CofO in Progress on 3/9/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/10/2023 APPLICANT
Assigned to Plan Check Engineer 5/15/2023 JOSEPH RAFOLS
Corrections Issued 5/15/2023 JOSEPH RAFOLS
Building Plans Picked Up 5/24/2023 APPLICANT
Applicant returned to address corrections 9/22/2023 MICHAEL LANZONE
Applicant returned to address corrections 4/22/2024 HUAN LE
Plan Check Approved 4/22/2024 MINA HABILI
Issued 5/2/2024 APPLICANT
CofO in Progress 2/25/2025 ARTHUR NEGRETE
No Progress 3/9/2025 DEROLD HAUFF
CofO in Progress 3/9/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/6/2023 JESSICA OPINION
Roof/Waste drainage to street Cleared 6/6/2023 JESSICA OPINION
Eng Process Fee Ord 176,300 Cleared 6/22/2023 JESSICA OPINION
Sewer availability Cleared 6/22/2023 JESSICA OPINION
Construction near power lines Cleared 9/9/2023 RIDWAN HARDY
Flood clearance Cleared 4/17/2024 FRANCISCO JIMENEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/6/2024 Approved RICHARD DOCKUS
Excavation/Setback/Form/Re-Bar 5/14/2024 Corrections Issued AMIR NAZARIAN
Excavation/Setback/Form/Re-Bar 5/15/2024 Corrections Issued AMIR NAZARIAN
Excavation/Setback/Form/Re-Bar 5/17/2024 Approved AMIR NAZARIAN
Floor/Roof Diaphrgm/Shear Wall 5/24/2024 Approved ARTHUR NEGRETE
PLUMBING-Rough 5/24/2024 Approved ARTHUR NEGRETE
Floor/Roof Diaphrgm/Shear Wall 5/31/2024 Approved AMIR NAZARIAN
BUILDING-Rough-Frame 6/21/2024 Not Ready for Inspection JUSTIN HAWLEY
ELECTRICAL-Rough 6/21/2024 Approved JUSTIN HAWLEY
FLOOD-Proofing Certificate 6/21/2024 Approved JUSTIN HAWLEY
Floor/Roof Diaphrgm/Shear Wall 6/21/2024 Approved JUSTIN HAWLEY
Gas Test 6/21/2024 Approved JUSTIN HAWLEY
Green Building Rough 6/21/2024 Not Ready for Inspection JUSTIN HAWLEY
HVAC-Rough 6/21/2024 Corrections Issued JUSTIN HAWLEY
PLUMBING-Rough 6/21/2024 Corrections Issued JUSTIN HAWLEY
Underground Mechanical 6/21/2024 Partial Approval JUSTIN HAWLEY
BUILDING-Rough-Frame 7/3/2024 Approved ARTHUR NEGRETE
Green Building Rough 7/3/2024 Approved ARTHUR NEGRETE
HVAC-Rough 7/3/2024 Approved ARTHUR NEGRETE
Insulation 7/3/2024 Approved ARTHUR NEGRETE
Interior/Exterior Lathing 7/3/2024 Approved ARTHUR NEGRETE
PLUMBING-Rough 7/3/2024 Approved ARTHUR NEGRETE
Sewer 7/3/2024 Approved ARTHUR NEGRETE
Drywall Nailing 7/8/2024 Approved AMIR NAZARIAN
Interior/Exterior Lathing 7/10/2024 Partial Approval JOSH MEISTER
Shower Pan 7/10/2024 Approved JOSH MEISTER
Underground Mechanical 7/24/2024 Partial Approval AMIR NAZARIAN
FLOOD-Elevation Certificate 10/10/2024 Not Ready for Inspection JOAQUIN GREENOUGH
Final 10/10/2024 Corrections Issued JOAQUIN GREENOUGH
Footing/Foundation/Slab 10/10/2024 Not Ready for Inspection JOAQUIN GREENOUGH
Green Building Final 10/10/2024 Not Ready for Inspection JOAQUIN GREENOUGH
HVAC-Rough 10/10/2024 Not Ready for Inspection JOAQUIN GREENOUGH
METHANE-Barrier 10/10/2024 Not Ready for Inspection JOAQUIN GREENOUGH
METHANE-Final 10/10/2024 Not Ready for Inspection JOAQUIN GREENOUGH
METHANE-Subgrade 10/10/2024 Not Ready for Inspection JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 10/10/2024 SGSOV Not Ready JOAQUIN GREENOUGH
Service/Power Release 10/10/2024 Not Ready for Inspection JOAQUIN GREENOUGH
Smoke Detectors 10/10/2024 Not Ready for Inspection JOAQUIN GREENOUGH
ELECTRICAL-Final 10/16/2024 Approved ARTHUR NEGRETE
FLOOD-Elevation Certificate 10/16/2024 Approved ARTHUR NEGRETE
Final 10/16/2024 Partial Approval ARTHUR NEGRETE
Footing/Foundation/Slab 10/16/2024 Approved ARTHUR NEGRETE
Green Building Final 10/16/2024 Approved ARTHUR NEGRETE
HVAC-Final 10/16/2024 Approved ARTHUR NEGRETE
METHANE-Barrier 10/16/2024 Approved ARTHUR NEGRETE
METHANE-Final 10/16/2024 Approved ARTHUR NEGRETE
METHANE-Subgrade 10/16/2024 Approved ARTHUR NEGRETE
PLUMBING-Final 10/16/2024 Approved ARTHUR NEGRETE
SGSOV-Seismic Gas S/O Valve 10/16/2024 SGSOV Approved ARTHUR NEGRETE
Service/Power Release 10/16/2024 Approved ARTHUR NEGRETE
Smoke Detectors 10/16/2024 Approved ARTHUR NEGRETE
Final 2/24/2025 OK to Issue CofO ARTHUR NEGRETE