342 N KINGS ROAD 90048
Certificate Information: 342 N KINGS ROAD 90048
- Application / Permit
- 23014-10000-01782
- Plan Check / Job No.
- B23LA08535
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan: 103 SF IRREGULAR SHAPED ADDITION TO FRONT PORTION OF (E) SFD, 36 SF PORCH ADDITION TO FRONT OF (E) SFD, 176 SF IRREGULAR SHAPED ADDITION TO REAR OF (E) SFD, 30 SF ADDITION TO REAR OF (E) SFD, REMODEL OF (E) SFD TO CREATE NEW BEDROOM AND BATHROOMS AND RELOCATE KITCHEN AND BATHROOMS , REMODEL/REFRAME AT (E) ENTRYWAY, REMOVE AND REPLACE 4 WINDOWS, ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 6/19/2023
- Issuing Office
- Current Status
- CofO Issued on 3/13/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/9/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/11/2023 | OMAR GARNICA |
| Corrections Issued | 5/12/2023 | OMAR GARNICA |
| Plan Check Approved | 6/19/2023 | OMAR GARNICA |
| Issued | 6/19/2023 | APPLICANT |
| CofO in Progress | 3/11/2024 | AMIR NAZARIAN |
| CofO Issued | 3/13/2024 | DEROLD HAUFF |
| Permit Finaled | 3/13/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Sewer availability | Cleared | 6/4/2023 | JOSEPH RHYU |
| Roof/Waste drainage to street | Cleared | 6/7/2023 | JOSEPH RHYU |
| Eng Process Fee Ord 176,300 | Cleared | 6/15/2023 | TREVOR QUAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Barakat,, Fouad Chafic; Lic. No.: C67449 | 11 CEDARWOOD DR POMONA, CA 91766 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/26/2023 | Conditional Approval | BRENDAN MORELLI |
| Footing/Foundation/Slab | 7/31/2023 | Partial Approval | LILIANA PORTILLO |
| METHANE-Barrier | 7/31/2023 | Approved | LILIANA PORTILLO |
| METHANE-Subgrade | 7/31/2023 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 8/18/2023 | Partial Approval | LILIANA PORTILLO |
| Insulation | 8/18/2023 | Partial Approval | LILIANA PORTILLO |
| Deputy Wood Construction | 8/23/2023 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 8/23/2023 | Partial Approval | LILIANA PORTILLO |
| Deputy Wood Construction | 9/28/2023 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Rough | 9/28/2023 | Corrections Issued | LILIANA PORTILLO |
| HVAC-Rough | 9/28/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| METHANE-Rough | 9/28/2023 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 9/28/2023 | Corrections Issued | LILIANA PORTILLO |
| ELECTRICAL-Rough | 10/2/2023 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 10/2/2023 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 10/2/2023 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 10/4/2023 | Conditional Approval | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 10/4/2023 | Corrections Issued | LILIANA PORTILLO |
| HVAC-Rough | 10/4/2023 | Conditional Approval | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 10/6/2023 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 10/6/2023 | Approved | LILIANA PORTILLO |
| Shower Pan | 10/6/2023 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 11/6/2023 | Conditional Approval | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 11/17/2023 | Approved | LILIANA PORTILLO |
| Green Building Rough | 11/17/2023 | Approved | LILIANA PORTILLO |
| Insulation | 11/17/2023 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 11/17/2023 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 11/30/2023 | Approved | BRENDAN MORELLI |
| Final | 2/21/2024 | Corrections Issued | AMIR NAZARIAN |
| Footing/Foundation/Slab | 2/21/2024 | Corrections Issued | AMIR NAZARIAN |
| Green Building Final | 2/21/2024 | Corrections Issued | AMIR NAZARIAN |
| SGSOV-Seismic Gas S/O Valve | 2/21/2024 | SGSOV Approved | AMIR NAZARIAN |
| Smoke Detectors | 2/21/2024 | Corrections Issued | AMIR NAZARIAN |
| Special/Order Compliance | 2/21/2024 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Final | 3/5/2024 | Corrections Issued | AMIR NAZARIAN |
| Footing/Foundation/Slab | 3/5/2024 | Approved | AMIR NAZARIAN |
| Green Building Final | 3/5/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Smoke Detectors | 3/5/2024 | Approved | AMIR NAZARIAN |
| Final | 3/8/2024 | OK to Issue CofO | AMIR NAZARIAN |
| Green Building Final | 3/8/2024 | Approved | AMIR NAZARIAN |