15153 W LA MAIDA ST 91403
Certificate Information: 15153 W LA MAIDA ST 91403
- Application / Permit
- 23014-10000-01746
- Plan Check / Job No.
- B23LA04356
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan 2 of 2 ADDITION TO (E) SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 10/20/2023
- Issuing Office
- Current Status
- CofO Issued on 5/13/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/17/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/30/2023 | ADRIANA LOPEZ |
| Corrections Issued | 5/4/2023 | ADRIANA LOPEZ |
| Quality Review Completed | 5/22/2023 | QUAN NGHIEM |
| Applicant returned to address corrections | 9/6/2023 | ADRIANA LOPEZ |
| Applicant returned to address corrections | 9/29/2023 | ADRIANA LOPEZ |
| Plan Check Approved | 10/18/2023 | ADRIANA LOPEZ |
| Issued | 10/20/2023 | APPLICANT |
| CofO in Progress | 3/25/2025 | JACK KARGODORIAN |
| Permit Finaled | 5/13/2025 | RUBEN SALAS |
| Permit Finaled | 5/13/2025 | RUBEN SALAS |
| CofO Issued | 5/13/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 6/1/2023 | TAL SHEMEN |
| Eng Process Fee Ord 176,300 | Cleared | 6/5/2023 | TAL SHEMEN |
| Sewer availability | Cleared | 6/5/2023 | TAL SHEMEN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| DAVID ANDERSON, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/27/2023 | Corrections Issued | THOMAS FINNILA |
| Footing/Foundation/Slab | 5/2/2024 | Approved | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 5/15/2024 | Partial Approval | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/20/2024 | Partial Approval | JACK KARGODORIAN |
| Deputy Wood Construction | 5/30/2024 | Conditional Approval | DAVID MATSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/5/2024 | Partial Approval | MICHEL ABAJAN |
| ELECTRICAL-Rough | 7/5/2024 | Approved | JACK KARGODORIAN |
| HVAC-Rough | 7/5/2024 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 7/5/2024 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 7/9/2024 | Approved | RYAN SALAZAR |
| Green Building Rough | 7/9/2024 | Approved | RYAN SALAZAR |
| MERV13>=Rough | 7/9/2024 | Approved | RYAN SALAZAR |
| ELECTRICAL-Rough | 7/16/2024 | Approved | JACK KARGODORIAN |
| Insulation | 7/16/2024 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 7/16/2024 | Corrections Issued | JACK KARGODORIAN |
| Drywall Nailing | 7/24/2024 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Rough | 7/24/2024 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 7/24/2024 | Order to Comply Issued | JACK KARGODORIAN |
| Shower Pan | 7/24/2024 | Not Ready for Inspection | JACK KARGODORIAN |
| Shower Pan | 7/29/2024 | Corrections Issued | JACK KARGODORIAN |
| Shower Pan | 7/30/2024 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 8/21/2024 | Approved | MISAEL ESPARZA |
| Final | 2/4/2025 | Corrections Issued | MISAEL ESPARZA |
| Green Building Final | 2/4/2025 | Approved | MISAEL ESPARZA |
| MERV13>=Final | 2/4/2025 | Partial Inspection | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 2/4/2025 | SGSOV Not Ready | MISAEL ESPARZA |
| Smoke Detectors | 2/4/2025 | Corrections Issued | MISAEL ESPARZA |
| Final | 3/21/2025 | OK to Issue CofO | JACK KARGODORIAN |
| MERV13>=Final | 3/21/2025 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 3/21/2025 | SGSOV Approved | JACK KARGODORIAN |
| Smoke Detectors | 3/21/2025 | Approved | JACK KARGODORIAN |