805 N LEONARD ROAD 90049
Certificate Information: 805 N LEONARD ROAD 90049
- Application / Permit
- 23014-10000-01742
- Plan Check / Job No.
- B23LA08319
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan Converting Garage to Part of SFD and buld a (N) 2 Car Carport. Per engineering design. .
- Permit Issued
- Issued on 8/3/2023
- Issuing Office
- Current Status
- CofO Issued on 2/5/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/4/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/9/2023 | ALFREDO JARA |
| Corrections Issued | 5/10/2023 | ALFREDO JARA |
| Applicant returned to address corrections | 7/25/2023 | ALFREDO JARA |
| Plan Check Approved | 8/3/2023 | ALFREDO JARA |
| Issued | 8/3/2023 | APPLICANT |
| CofO in Progress | 2/2/2024 | KEVIN SARGSYAN |
| Permit Finaled | 2/5/2024 | DANIEL ORRANTE |
| CofO Issued | 2/5/2024 | DANIEL ORRANTE |
| Permit Finaled | 2/5/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 5/18/2023 | HISASHI KOBAYAKAWA |
| BHO/Hillside ordinance | Cleared | 5/18/2023 | JASON NG |
| BHO/Hillside ordinance | Cleared | 5/18/2023 | JASON NG |
| BHO/Hillside ordinance | Cleared | 5/18/2023 | JASON NG |
| BHO/Hillside ordinance | Cleared | 5/18/2023 | JASON NG |
| Watercourse | Cleared | 5/18/2023 | HISASHI KOBAYAKAWA |
| Eng Process Fee Ord 176,300 | Cleared | 5/19/2023 | JASON NG |
| Low Impact Development (LID) | Cleared | 7/14/2023 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 7/16/2023 | AHMED AMARRAGY |
| GPI Written Notices | Cleared | 7/25/2023 | ALFREDO JARA |
| Grading Pre-Inspection | Cleared | 7/25/2023 | ALFREDO JARA |
Contact Information
| Contractor | Value Construction Inc; Lic. No.: 982837-B | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/20/2023 | No Access for Inspection | KENNETH NAGLE |
| Excavation/Setback/Form/Re-Bar | 9/22/2023 | Corrections Issued | ARAM AVEDISIAN |
| Deputy Other (see comments) | 9/26/2023 | Conditional Approval | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 9/27/2023 | Approved | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/13/2023 | Partial Approval | KENNETH NAGLE |
| BUILDING-Rough-Frame | 11/3/2023 | Partial Approval | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 11/3/2023 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 11/3/2023 | Approved | ARAM AVEDISIAN |
| HVAC-Rough | 11/3/2023 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 11/3/2023 | Approved | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/8/2023 | Approved | KEVIN SARGSYAN |
| Insulation | 11/8/2023 | Approved | KEVIN SARGSYAN |
| Drywall Nailing | 11/14/2023 | Approved | KEVIN SARGSYAN |
| Deck | 11/21/2023 | Approved | KEVIN SARGSYAN |
| Sewer | 12/14/2023 | Corrections Issued | KEVIN SARGSYAN |
| Sewer | 12/19/2023 | Approved | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 2/1/2024 | Approved | KEVIN SARGSYAN |
| FLOOD-Proofing Certificate | 2/1/2024 | Approved | KEVIN SARGSYAN |
| Final | 2/1/2024 | OK to Issue CofO | KEVIN SARGSYAN |
| Green Building Final | 2/1/2024 | Approved | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 2/1/2024 | SGSOV Approved | KEVIN SARGSYAN |
| Smoke Detectors | 2/1/2024 | Approved | KEVIN SARGSYAN |