4329 N ALLOTT AVE 91423

Certificate Information: 4329 N ALLOTT AVE 91423

Application / Permit
23014-10000-01728
Plan Check / Job No.
B23LA08238
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION AND REMODEL TO (E) SFD
Permit Issued
Issued on 6/15/2023
Issuing Office
Current Status
CofO Issued on 4/16/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/3/2023 APPLICANT
Assigned to Plan Check Engineer 5/4/2023 JAD BASMA
Corrections Issued 5/19/2023 JAD BASMA
Quality Review Completed 5/23/2023 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 5/25/2023 APPLICANT
Plan Check Approved 6/15/2023 JAD BASMA
Issued 6/15/2023 APPLICANT
CofO in Progress 1/23/2024 MISAEL ESPARZA
Permit Finaled 4/16/2024 DANIEL ORRANTE
CofO Issued 4/16/2024 DANIEL ORRANTE
Permit Finaled 4/16/2024 DANIEL ORRANTE

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 5/31/2023 WALLIE JONG
Sewer availability Cleared 5/31/2023 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 6/5/2023 WALLIE JONG
ZI Cleared 6/6/2023 SPENCER WEJROWSKI

Contact Information

Contractor Owner-Builder       ,
Engineer , Spsengineering; Lic. No.: C93079 15445 VENTURA BLVD   63    SHERMAN OAKS, CA 91403

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/28/2023 Approved DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 7/17/2023 Corrections Issued MISAEL ESPARZA
Wood Frame 7/17/2023 Not Ready for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 8/18/2023 Partial Approval MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 8/18/2023 Approved MISAEL ESPARZA
Green Building Rough 8/18/2023 Not Ready for Inspection MISAEL ESPARZA
Rough-Elec/Plmb/HVAC 8/18/2023 Corrections Issued MISAEL ESPARZA
Wood Frame 8/18/2023 Partial Approval MISAEL ESPARZA
BUILDING-Rough-Frame 8/24/2023 Approved MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 8/24/2023 Approved MISAEL ESPARZA
Green Building Rough 8/24/2023 Approved MISAEL ESPARZA
Insulation 8/24/2023 Approved MISAEL ESPARZA
Interior/Exterior Lathing 8/24/2023 Partial Approval MISAEL ESPARZA
Rough-Elec/Plmb/HVAC 8/24/2023 Approved MISAEL ESPARZA
Drywall Nailing 9/8/2023 Approved MISAEL ESPARZA
Interior/Exterior Lathing 9/8/2023 Approved MISAEL ESPARZA
Final 1/12/2024 Not Ready for Inspection MISAEL ESPARZA
Green Building Final 1/12/2024 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 1/12/2024 SGSOV Approved MISAEL ESPARZA
Smoke Detectors 1/12/2024 Approved MISAEL ESPARZA
Final 1/19/2024 OK to Issue CofO MISAEL ESPARZA