1261 1/2 W 35TH PL 90007
Certificate Information: 1261 1/2 W 35TH PL 90007
- Application / Permit
- 23014-10000-01716
- Plan Check / Job No.
- B23LA08180
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan: Proposed Conversion of portion of an (E) Garage with 2nd-floor addition to Accessary dwelling unit per LAMC 12.22A.33(c)(d)
- Permit Issued
- Issued on 2/3/2025
- Issuing Office
- Current Status
- Issued on 2/3/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/24/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/8/2023 | RACHEL BEYENE |
| Corrections Issued | 6/14/2023 | RACHEL BEYENE |
| Quality Review Completed | 7/7/2023 | MICHAEL PEREZ |
| Applicant returned to address corrections | 8/31/2023 | RACHEL BEYENE |
| Applicant returned to address corrections | 9/20/2023 | RACHEL BEYENE |
| Applicant returned to address corrections | 10/3/2023 | RACHEL BEYENE |
| Applicant returned to address corrections | 5/13/2024 | SINA KHOSRAVI |
| Plan Check Approved | 9/26/2024 | RAHEL BEYENE |
| Issued | 2/3/2025 | APPLICANT |
Permit Application Clearance Information
| ZI | Cleared | 7/31/2023 | RUBEN VASQUEZ |
| Address approval | Cleared | 8/2/2023 | ADRIAN SANCHEZ |
| Roof/Waste drainage to street | Cleared | 8/2/2023 | ADRIAN SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/11/2023 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 8/11/2023 | ADRIAN SANCHEZ |
Contact Information
| Architect | Baek,, Sunpil; Lic. No.: NA35323 | , |
| Contractor | Owner-Builder | , |
| Engineer | Kim,, Hosang; Lic. No.: C67288 | 18759 WILLOWTREE LANE PORTER RANCH, CA 91326 |
| Engineer | Park,, Juntae; Lic. No.: C65104 | 3055 WILSHIRE BLVD 880 LOS ANGELES, CA 90010 |
| Engineer | Park,, Juntae; Lic. No.: NA65104 | , |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/4/2025 | Not Ready for Inspection | SABAS ALONSO |
| Green Building Rough | 2/7/2025 | No Access for Inspection | SABAS ALONSO |
| Footing/Foundation/Slab | 2/28/2025 | Approved | SABAS ALONSO |
| Deputy Drilled-In Anchors | 3/3/2025 | Conditional Approval | SABAS ALONSO |
| Excavation/Setback/Form/Re-Bar | 5/16/2025 | Not Ready for Inspection | SABAS ALONSO |
| Special/Order Compliance | 8/18/2025 | Corrections Issued | SABAS ALONSO |