1715 N AVENUE 56 90042
Certificate Information: 1715 N AVENUE 56 90042
- Application / Permit
- 23014-10000-01712
- Plan Check / Job No.
- B23LA08166
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 18' X 19'6" IRREGULARLY SHAPED ADDITION (285 SF) TO (E) SINGLE FAMILY DWELLING TO ADD MASTER BEDROOM, CLOSET AND BATHROOM. WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 6/13/2023
- Issuing Office
- Current Status
- CofO Issued on 1/11/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/3/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/8/2023 | WEIJIAN HUANG |
| Corrections Issued | 5/9/2023 | WEIJIAN HUANG |
| Applicant returned to address corrections | 5/30/2023 | MADISON ODELL |
| Plan Check Approved | 6/9/2023 | MADISON ODELL |
| Issued | 6/13/2023 | APPLICANT |
| CofO in Progress | 1/4/2024 | CRAIG VAUGHAN |
| CofO in Progress | 1/4/2024 | CRAIG VAUGHAN |
| Permit Finaled | 1/11/2024 | DEROLD HAUFF |
| Permit Finaled | 1/11/2024 | DEROLD HAUFF |
| CofO Issued | 1/11/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 5/11/2023 | RICARDO BOHORQUEZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/15/2023 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 5/15/2023 | JEANIE LAM |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Zhuang,, Wenbin; Lic. No.: S5236 | 205 S CHAPEL AVE #D-1 ALHAMBRA, CA 91801 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/27/2023 | Approved | CRAIG VAUGHAN |
| Underground Mechanical | 8/30/2023 | Partial Approval | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 8/31/2023 | Partial Approval | CRAIG VAUGHAN |
| PLUMBING-Rough | 8/31/2023 | Partial Approval | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/4/2023 | Corrections Issued | ROY SPAULDING |
| Floor/Roof Diaphrgm/Shear Wall | 10/6/2023 | Approved | ROY SPAULDING |
| Interior/Exterior Lathing | 10/11/2023 | Partial Approval | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 10/16/2023 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 10/16/2023 | Approved | CRAIG VAUGHAN |
| Green Building Rough | 10/16/2023 | Approved | CRAIG VAUGHAN |
| HVAC-Rough | 10/16/2023 | Partial Approval | CRAIG VAUGHAN |
| PLUMBING-Rough | 10/16/2023 | Corrections Issued | CRAIG VAUGHAN |
| Insulation | 10/18/2023 | Approved | ROY SPAULDING |
| Drywall Nailing | 10/24/2023 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 10/24/2023 | Approved | CRAIG VAUGHAN |
| Service/Power Release | 10/27/2023 | Corrections Issued | CRAIG VAUGHAN |
| Service/Power Release | 10/30/2023 | Approved | CRAIG VAUGHAN |
| Final | 12/15/2023 | Corrections Issued | CRAIG VAUGHAN |
| Green Building Final | 12/15/2023 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 12/15/2023 | SGSOV Approved | CRAIG VAUGHAN |
| Smoke Detectors | 12/15/2023 | Approved | CRAIG VAUGHAN |
| Final | 12/19/2023 | Partial Approval | ROY SPAULDING |
| HVAC-Final | 12/19/2023 | Approved | ROY SPAULDING |
| ELECTRICAL-Final | 1/3/2024 | Approved | CRAIG VAUGHAN |
| Final | 1/3/2024 | OK to Issue CofO | CRAIG VAUGHAN |
| PLUMBING-Final | 1/3/2024 | Approved | CRAIG VAUGHAN |