1715 N AVENUE 56 90042

Certificate Information: 1715 N AVENUE 56 90042

Application / Permit
23014-10000-01712
Plan Check / Job No.
B23LA08166
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 18' X 19'6" IRREGULARLY SHAPED ADDITION (285 SF) TO (E) SINGLE FAMILY DWELLING TO ADD MASTER BEDROOM, CLOSET AND BATHROOM. WORK DONE PER ENGINEERING.
Permit Issued
Issued on 6/13/2023
Issuing Office
Current Status
CofO Issued on 1/11/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/3/2023 APPLICANT
Assigned to Plan Check Engineer 5/8/2023 WEIJIAN HUANG
Corrections Issued 5/9/2023 WEIJIAN HUANG
Applicant returned to address corrections 5/30/2023 MADISON ODELL
Plan Check Approved 6/9/2023 MADISON ODELL
Issued 6/13/2023 APPLICANT
CofO in Progress 1/4/2024 CRAIG VAUGHAN
CofO in Progress 1/4/2024 CRAIG VAUGHAN
Permit Finaled 1/11/2024 DEROLD HAUFF
Permit Finaled 1/11/2024 DEROLD HAUFF
CofO Issued 1/11/2024 DEROLD HAUFF

Permit Application Clearance Information

Tenant Habitability Plan Cleared 5/11/2023 RICARDO BOHORQUEZ
Eng Process Fee Ord 176,300 Cleared 5/15/2023 JEANIE LAM
Roof/Waste drainage to street Cleared 5/15/2023 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,
Engineer Zhuang,, Wenbin; Lic. No.: S5236 205 S CHAPEL AVE #D-1      ALHAMBRA, CA 91801

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/27/2023 Approved CRAIG VAUGHAN
Underground Mechanical 8/30/2023 Partial Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 8/31/2023 Partial Approval CRAIG VAUGHAN
PLUMBING-Rough 8/31/2023 Partial Approval CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 10/4/2023 Corrections Issued ROY SPAULDING
Floor/Roof Diaphrgm/Shear Wall 10/6/2023 Approved ROY SPAULDING
Interior/Exterior Lathing 10/11/2023 Partial Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 10/16/2023 Approved CRAIG VAUGHAN
ELECTRICAL-Rough 10/16/2023 Approved CRAIG VAUGHAN
Green Building Rough 10/16/2023 Approved CRAIG VAUGHAN
HVAC-Rough 10/16/2023 Partial Approval CRAIG VAUGHAN
PLUMBING-Rough 10/16/2023 Corrections Issued CRAIG VAUGHAN
Insulation 10/18/2023 Approved ROY SPAULDING
Drywall Nailing 10/24/2023 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 10/24/2023 Approved CRAIG VAUGHAN
Service/Power Release 10/27/2023 Corrections Issued CRAIG VAUGHAN
Service/Power Release 10/30/2023 Approved CRAIG VAUGHAN
Final 12/15/2023 Corrections Issued CRAIG VAUGHAN
Green Building Final 12/15/2023 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 12/15/2023 SGSOV Approved CRAIG VAUGHAN
Smoke Detectors 12/15/2023 Approved CRAIG VAUGHAN
Final 12/19/2023 Partial Approval ROY SPAULDING
HVAC-Final 12/19/2023 Approved ROY SPAULDING
ELECTRICAL-Final 1/3/2024 Approved CRAIG VAUGHAN
Final 1/3/2024 OK to Issue CofO CRAIG VAUGHAN
PLUMBING-Final 1/3/2024 Approved CRAIG VAUGHAN