1224 1/2 S ALDINE CT 90731

Certificate Information: 1224 1/2 S ALDINE CT 90731

Application / Permit
23014-10000-01704
Plan Check / Job No.
B23LA08113
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
3'-0" X 18'-0" ADDITION AND REMODEL OF EXISTING DETACHED GARAGE TO CONVERT TO ACCESSORY DWELLING UNIT LAMC 12.22 A.33(c) AND (d) - PER ENGINEER
Permit Issued
Issued on 8/22/2023
Issuing Office
Current Status
CofO Issued on 7/2/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/2/2023 APPLICANT
Assigned to Plan Check Engineer 5/5/2023 DANIEL ABRAMYAN
Corrections Issued 5/6/2023 DANIEL ABRAMYAN
Applicant returned to address corrections 5/31/2023 DANIEL ABRAMYAN
Plan Check Approved 8/17/2023 DANIEL ABRAMYAN
Issued 8/22/2023 APPLICANT
CofO in Progress 7/2/2024 JAMES CHAVEZ
CofO Issued 7/2/2024 ANSON MAGLASANG
Permit Finaled 7/2/2024 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 5/9/2023 ANA SORIANO
Roof/Waste drainage to street Cleared 5/9/2023 ANA SORIANO
Grading Pre-Inspection Cleared 5/16/2023 SERGIO VALENZUELA
Eng Process Fee Ord 176,300 Cleared 6/14/2023 KHAING AYE
Sewer availability Cleared 6/14/2023 KHAING AYE
Construction near power lines Cleared 8/14/2023 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Gonzalez,, Felix Bolivar; Lic. No.: NA64738       ,

Inspector Information

JOSEPH MCGARRY, (310) 732-4559 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 11/14/2023 Partial Approval JAMES CHAVEZ
Underground Mechanical 11/14/2023 Partial Approval JAMES CHAVEZ
Footing/Foundation/Slab 11/30/2023 Corrections Issued ANSON MAGLASANG
Footing/Foundation/Slab 12/13/2023 Approved JAMES CHAVEZ
Floor/Roof Diaphrgm/Shear Wall 1/26/2024 Partial Approval ANSON MAGLASANG
Interior/Exterior Lathing 2/16/2024 Partial Approval EUGENE CASSIDY
Rough-Elec/Plmb/HVAC 2/16/2024 Corrections Issued EUGENE CASSIDY
BUILDING-Rough-Frame 2/22/2024 Corrections Issued EUGENE CASSIDY
Green Building Rough 2/22/2024 Approved EUGENE CASSIDY
Rough-Elec/Plmb/HVAC 2/22/2024 Approved EUGENE CASSIDY
Insulation 3/6/2024 Approved EUGENE CASSIDY
Drywall Nailing 3/13/2024 Approved ANSON MAGLASANG
Sewer 5/21/2024 Partial Approval JAMES CHAVEZ
BUILDING-Rough-Frame 5/31/2024 Approved JAMES CHAVEZ
ELECTRICAL-Final 5/31/2024 Not Ready for Inspection JAMES CHAVEZ
Final 5/31/2024 Corrections Issued JAMES CHAVEZ
Green Building Final 5/31/2024 Not Ready for Inspection JAMES CHAVEZ
SGSOV-Seismic Gas S/O Valve 5/31/2024 SGSOV Not Ready JAMES CHAVEZ
Smoke Detectors 5/31/2024 Not Ready for Inspection JAMES CHAVEZ
SGSOV-Seismic Gas S/O Valve 6/10/2024 SGSOV Not Ready JAMES CHAVEZ
Final 6/28/2024 Partial Inspection JAMES CHAVEZ
Green Building Final 6/28/2024 Not Ready for Inspection JAMES CHAVEZ
SGSOV-Seismic Gas S/O Valve 6/28/2024 SGSOV Approved JAMES CHAVEZ
Smoke Detectors 6/28/2024 Approved JAMES CHAVEZ
Final 7/2/2024 OK to Issue CofO JAMES CHAVEZ
Green Building Final 7/2/2024 Approved JAMES CHAVEZ