8423 1/2 W 4TH ST 90048

Certificate Information: 8423 1/2 W 4TH ST 90048

Application / Permit
23014-10000-01695
Plan Check / Job No.
B23LA08063
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan****PROPOSED 2-STORY ADDITION TO GARAGE WITH ADU PER LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 1/8/2024
Issuing Office
Current Status
CofO Issued on 5/6/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/2/2023 APPLICANT
Assigned to Plan Check Engineer 5/4/2023 SINA KHOSRAVI
Corrections Issued 5/9/2023 SINA KHOSRAVI
Quality Review Completed 5/15/2023 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 6/29/2023 SINA KHOSRAVI
Applicant returned to address corrections 9/13/2023 SINA KHOSRAVI
Applicant returned to address corrections 10/2/2023 SINA KHOSRAVI
Applicant returned to address corrections 11/17/2023 SINA KHOSRAVI
Applicant returned to address corrections 12/5/2023 SINA KHOSRAVI
Plan Check Approved 1/8/2024 SINA KHOSRAVI
Issued 1/8/2024 APPLICANT
CofO in Progress 5/2/2025 EVAN COOPER
Permit Finaled 5/6/2025 RICHARD STEINBACH
CofO Issued 5/6/2025 RICHARD STEINBACH
Permit Finaled 5/6/2025 RICHARD STEINBACH

Permit Application Clearance Information

Tenant Habitability Plan Cleared 5/16/2023 ISMAEL HERNANDEZ
Address approval Cleared 5/23/2023 ADRIAN SANCHEZ
Eng Process Fee Ord 176,300 Cleared 5/26/2023 ADRIAN SANCHEZ
Roof/Waste drainage to street Cleared 5/26/2023 ADRIAN SANCHEZ
Sewer availability Cleared 5/26/2023 ADRIAN SANCHEZ
Low Impact Development (LID) Cleared 8/15/2023 LUIS LUVANO
Construction near power lines Cleared 12/12/2023 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 1/12/2024 Partial Approval MEL KHACHATOURIAN
Pre-Inspection 1/19/2024 Approved MEL KHACHATOURIAN
Footing/Foundation/Slab 1/31/2024 Corrections Issued MEL KHACHATOURIAN
METHANE-Barrier 1/31/2024 Approved MEL KHACHATOURIAN
METHANE-Subgrade 1/31/2024 Approved MEL KHACHATOURIAN
Footing/Foundation/Slab 2/9/2024 Approved MEL KHACHATOURIAN
Wood Frame 2/26/2024 Corrections Issued MEL KHACHATOURIAN
Deputy Wood Construction 2/27/2024 No Access for Inspection MEL KHACHATOURIAN
Wood Frame 2/27/2024 Partial Approval MEL KHACHATOURIAN
ELECTRICAL-Rough 4/17/2024 Not Ready for Inspection MEL KHACHATOURIAN
Gas Test 4/17/2024 Approved MEL KHACHATOURIAN
PLUMBING-Rough 4/17/2024 Approved MEL KHACHATOURIAN
Sewer 4/17/2024 Approved MEL KHACHATOURIAN
Underground Mechanical 4/17/2024 Approved MEL KHACHATOURIAN
ELECTRICAL-Rough 5/2/2024 Not Ready for Inspection MEL KHACHATOURIAN
HVAC-Rough 5/2/2024 Not Ready for Inspection MEL KHACHATOURIAN
Wood Frame 5/2/2024 Not Ready for Inspection MEL KHACHATOURIAN
ELECTRICAL-Rough 5/21/2024 Not Ready for Inspection MEL KHACHATOURIAN
Wood Frame 5/21/2024 Corrections Issued MEL KHACHATOURIAN
BUILDING-Rough-Frame 6/28/2024 Corrections Issued MEL KHACHATOURIAN
ELECTRICAL-Rough 6/28/2024 Partial Approval MEL KHACHATOURIAN
ELECTRICAL-Rough 7/15/2024 Partial Approval MEL KHACHATOURIAN
Wood Frame 7/15/2024 Partial Approval MEL KHACHATOURIAN
BUILDING-Rough-Frame 7/22/2024 Corrections Issued MEL KHACHATOURIAN
ELECTRICAL-Rough 7/22/2024 Partial Approval MEL KHACHATOURIAN
Interior/Exterior Lathing 7/22/2024 Partial Approval MEL KHACHATOURIAN
BUILDING-Rough-Frame 7/25/2024 Approved MEL KHACHATOURIAN
Green Building Rough 7/25/2024 Approved MEL KHACHATOURIAN
Insulation 8/6/2024 Approved SEAN HAUPT
Drywall Nailing 8/13/2024 Approved DANIEL VERA
Special/Order Compliance 8/13/2024 Partial Approval DANIEL VERA
Interior/Exterior Lathing 8/21/2024 Approved DANIEL VERA
Shower Pan 8/21/2024 Approved DANIEL VERA
Service/Power Release 10/23/2024 Corrections Issued MEL KHACHATOURIAN
ELECTRICAL-Final 11/1/2024 Approved BOBBY KEY
Final 11/1/2024 Corrections Issued BOBBY KEY
Green Building Final 11/1/2024 Not Ready for Inspection BOBBY KEY
HVAC-Final 11/1/2024 Corrections Issued BOBBY KEY
PLUMBING-Final 11/1/2024 Not Ready for Inspection BOBBY KEY
SGSOV-Seismic Gas S/O Valve 11/1/2024 SGSOV Not Ready BOBBY KEY
Smoke Detectors 11/1/2024 Approved BOBBY KEY
Service/Power Release 12/13/2024 Approved BOBBY KEY
Final 1/29/2025 No Access for Inspection MEL KHACHATOURIAN
Green Building Final 1/29/2025 No Access for Inspection MEL KHACHATOURIAN
SGSOV-Seismic Gas S/O Valve 1/29/2025 SGSOV Not Ready MEL KHACHATOURIAN
Special/Order Compliance 1/30/2025 Approved MEL KHACHATOURIAN
Final 2/13/2025 Corrections Issued BOBBY KEY
Green Building Final 2/13/2025 Approved BOBBY KEY
HVAC-Final 2/13/2025 Approved BOBBY KEY
PLUMBING-Final 2/13/2025 Approved BOBBY KEY
SGSOV-Seismic Gas S/O Valve 2/13/2025 SGSOV Not Ready BOBBY KEY
Final 5/2/2025 OK to Issue CofO EVAN COOPER
SGSOV-Seismic Gas S/O Valve 5/2/2025 SGSOV Approved EVAN COOPER