1352 S HUDSON AVE 90019

Certificate Information: 1352 S HUDSON AVE 90019

Application / Permit
23014-10000-01692
Plan Check / Job No.
B23LA08046
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(22) Storage Building
Work Description
ePlan PROPOSED ATTACHED TWO STORAGE BUILDINGS TO EXISTING GARAGE "COMPLY WITH DEPARTMENT ORDER effective date 02/22/2023. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
Permit Issued
Issued on 10/24/2025
Issuing Office
Current Status
CofO in Progress on 7/22/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/1/2023 APPLICANT
Assigned to Plan Check Engineer 5/18/2023 CRYSTEL MAALOUF
Corrections Issued 5/26/2023 CRYSTEL MAALOUF
Quality Review Completed 6/6/2023 TU HUA
Applicant returned to address corrections 10/9/2024 CRYSTEL MAALOUF
Applicant returned to address corrections 10/30/2024 CRYSTEL MAALOUF
Applicant returned to address corrections 4/16/2025 CRYSTEL MAALOUF
Applicant returned to address corrections 5/23/2025 CRYSTEL MAALOUF
Applicant returned to address corrections 6/26/2025 CRYSTEL MAALOUF
Plan Check Approved 10/24/2025 CRYSTEL MAALOUF
Issued 10/24/2025 APPLICANT
CofO in Progress 7/22/2026 LUIS CORRAL

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/24/2025 JESSICA OPINION
Sewer availability Cleared 4/24/2025 JESSICA OPINION
CPC Cleared 5/12/2025 DAVID URITA
ZA Case Cleared 5/12/2025 DAVID URITA
Low Impact Development (LID) Cleared 10/21/2025 DANIEL LEON-MENDOZA
Flood clearance Cleared 10/22/2025 TUYEN LE
Roof/Waste drainage to street Cleared 10/23/2025 MICHAEL BROWN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/3/2025 Not Ready for Inspection JUSTIN HAWLEY
Pre-Inspection 11/5/2025 Approved LUIS CORRAL
BUILDING-Rough-Frame 11/12/2025 Not Ready for Inspection LUIS CORRAL
FLOOD-Elevation Certificate 11/12/2025 Not Ready for Inspection LUIS CORRAL
FLOOD-Proofing Certificate 11/12/2025 Not Ready for Inspection LUIS CORRAL
Footing/Foundation/Slab 11/12/2025 Corrections Issued LUIS CORRAL
Green Building Rough 11/12/2025 Not Ready for Inspection LUIS CORRAL
METHANE-Barrier 11/12/2025 Not Ready for Inspection LUIS CORRAL
METHANE-Rough 11/12/2025 Not Ready for Inspection LUIS CORRAL
METHANE-Subgrade 11/12/2025 Not Ready for Inspection LUIS CORRAL
Wood Frame 11/12/2025 Corrections Issued LUIS CORRAL
BUILDING-Rough-Frame 7/6/2026 Conditional Approval LUIS CORRAL
FLOOD-Elevation Certificate 7/6/2026 Not Ready for Inspection LUIS CORRAL
FLOOD-Proofing Certificate 7/6/2026 Not Ready for Inspection LUIS CORRAL
Footing/Foundation/Slab 7/6/2026 Conditional Approval LUIS CORRAL
Green Building Final 7/6/2026 Conditional Approval LUIS CORRAL
Green Building Rough 7/6/2026 Conditional Approval LUIS CORRAL
METHANE-Barrier 7/6/2026 Approved LUIS CORRAL
METHANE-Final 7/6/2026 Approved LUIS CORRAL
METHANE-Rough 7/6/2026 Approved LUIS CORRAL
METHANE-Subgrade 7/6/2026 Approved LUIS CORRAL
SGSOV-Seismic Gas S/O Valve 7/6/2026 SGSOV Approved LUIS CORRAL
Smoke Detectors 7/6/2026 Approved LUIS CORRAL
BUILDING-Rough-Frame 7/13/2026 Not Ready for Inspection LUIS CORRAL
FLOOD-Elevation Certificate 7/13/2026 Not Ready for Inspection LUIS CORRAL
FLOOD-Proofing Certificate 7/13/2026 Not Ready for Inspection LUIS CORRAL
Final 7/13/2026 Corrections Issued LUIS CORRAL
Footing/Foundation/Slab 7/13/2026 Not Ready for Inspection LUIS CORRAL
Green Building Final 7/13/2026 Approved LUIS CORRAL
Green Building Rough 7/13/2026 Approved LUIS CORRAL
BUILDING-Rough-Frame 7/20/2026 Approved LUIS CORRAL
Drywall Nailing 7/20/2026 Approved LUIS CORRAL
ELECTRICAL-Final 7/20/2026 Approved LUIS CORRAL
FLOOD-Proofing Certificate 7/20/2026 Approved LUIS CORRAL
Final 7/20/2026 Partial Approval LUIS CORRAL
Footing/Foundation/Slab 7/20/2026 Approved LUIS CORRAL
Insulation 7/20/2026 Approved LUIS CORRAL
Final 7/21/2026 OK to Issue CofO LUIS CORRAL