2284-2284 1/2 W 27TH ST 90018

Certificate Information: 2284-2284 1/2 W 27TH ST 90018

Application / Permit
23014-10000-01678
Plan Check / Job No.
B23LA08004
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
PROPOSED 1 STORY ADDITION FOR BEDROOM EXTENSIONS ALONG WEST SIDE OF DUPLEX.
Permit Issued
Issued on 6/7/2023
Issuing Office
Metro
Current Status
CofO Issued on 2/7/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/1/2023 APPLICANT
Assigned to Plan Check Engineer 5/9/2023 LAWRENCE QUIRANTE
Corrections Issued 5/9/2023 LAWRENCE QUIRANTE
Building Plans Picked Up 5/12/2023 APPLICANT
Plan Check Approved 6/7/2023 ADAM HEGAZI
Issued 6/7/2023 APPLICANT
CofO in Progress 2/2/2024 SABAS ALONSO
Permit Finaled 2/7/2024 DEROLD HAUFF
CofO Issued 2/7/2024 DEROLD HAUFF
Permit Finaled 2/7/2024 DEROLD HAUFF

Permit Application Clearance Information

HPOZ Cleared 5/23/2023 CHRISTINA PARK
Roof/Waste drainage to street Cleared 5/31/2023 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 6/1/2023 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,
Engineer Cooke,, Conway Cecil; Lic. No.: S5524 34658 LINDA ROSEA RD      TEMECULA, CA 92592

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Methane Barrier 9/29/2023 Conditional Approval BRENDAN MORELLI
Excavation/Setback/Form/Re-Bar 9/29/2023 Corrections Issued RONNIE MINDANAO
Deputy Methane Barrier 10/2/2023 Conditional Approval RONNIE MINDANAO
Special/Order Compliance 10/2/2023 Corrections Issued RONNIE MINDANAO
Excavation/Setback/Form/Re-Bar 10/4/2023 Approved SABAS ALONSO
Deputy Methane Barrier 10/6/2023 Conditional Approval SABAS ALONSO
Deputy Methane Barrier 10/12/2023 Conditional Approval CRAIG DAVIS
Deputy Methane Barrier 10/13/2023 Conditional Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 11/7/2023 Partial Approval BRENDAN MORELLI
Insulation 11/7/2023 Partial Approval BRENDAN MORELLI
Wood Frame 12/6/2023 Corrections Issued SABAS ALONSO
BUILDING-Rough-Frame 12/15/2023 Not Ready for Inspection SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 12/15/2023 Partial Approval SABAS ALONSO
Green Building Rough 12/15/2023 Not Ready for Inspection SABAS ALONSO
METHANE-Rough 12/15/2023 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 12/20/2023 Approved SABAS ALONSO
Insulation 12/27/2023 Not Ready for Inspection SABAS ALONSO
Interior/Exterior Lathing 12/27/2023 Partial Approval SABAS ALONSO
Drywall Nailing 1/2/2024 Not Ready for Inspection SABAS ALONSO
BUILDING-Rough-Frame 1/5/2024 Conditional Approval SABAS ALONSO
Insulation 1/10/2024 Approved SABAS ALONSO
Drywall Nailing 1/16/2024 Approved SABAS ALONSO
BUILDING-Rough-Frame 1/23/2024 Approved SABAS ALONSO
Final 1/23/2024 Corrections Issued SABAS ALONSO
Footing/Foundation/Slab 1/23/2024 Approved SABAS ALONSO
Green Building Final 1/23/2024 Approved SABAS ALONSO
Green Building Rough 1/23/2024 Approved SABAS ALONSO
METHANE-Barrier 1/23/2024 Approved SABAS ALONSO
METHANE-Subgrade 1/23/2024 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 1/23/2024 SGSOV Approved SABAS ALONSO
Smoke Detectors 1/23/2024 Approved SABAS ALONSO
Final 2/1/2024 OK to Issue CofO SABAS ALONSO