3734 S CHESAPEAKE AVE 90016

Certificate Information: 3734 S CHESAPEAKE AVE 90016

Application / Permit
23014-10000-01667
Plan Check / Job No.
B23LA07939
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
One story addition to single family dwelling at rear to add bedroom and bathroom. Addition at front to enlarge entrance. Remodel kitchen, bathroom and laundry room. Change out windows and doors as noted on plan.
Permit Issued
Issued on 6/14/2023
Issuing Office
Metro
Current Status
Issued on 6/14/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/28/2023 APPLICANT
Assigned to Plan Check Engineer 5/9/2023 AUNG SOE
Corrections Issued 5/12/2023 AUNG SOE
Building Plans Picked Up 5/17/2023 APPLICANT
Applicant returned to address corrections 5/30/2023 RICARDO RAMIREZ
Plan Check Approved 6/6/2023 JOSEPH RAFOLS
Issued 6/14/2023 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/1/2023 JEANIE LAM
Roof/Waste drainage to street Cleared 6/1/2023 JEANIE LAM
Sewer availability Cleared 6/1/2023 JEANIE LAM

Contact Information

Contractor A I R O Construction; Lic. No.: 1032640-B 13329 S CATALINA AVENUE      GARDENA, CA 90247
Engineer Adefeso,, Wole; Lic. No.: C63361 1620 CENTINELA AVE 304B      INGLEWOOD, CA 90302

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

Pre-Inspection 6/8/2026   

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/11/2023 Corrections Issued ANTHONY EGSON
Pre-Inspection 7/11/2023 Corrections Issued ANTHONY EGSON
Excavation/Setback/Form/Re-Bar 8/2/2023 Not Ready for Inspection ANTHONY EGSON
Footing/Foundation/Slab 8/2/2023 Corrections Issued ANTHONY EGSON
Excavation/Setback/Form/Re-Bar 8/22/2023 No Access for Inspection STUART CHAPMAN
Footing/Foundation/Slab 8/22/2023 No Access for Inspection STUART CHAPMAN
Piling/Pier/Caisson 8/22/2023 No Access for Inspection STUART CHAPMAN
Pre-Inspection 8/22/2023 No Access for Inspection STUART CHAPMAN
Excavation/Setback/Form/Re-Bar 8/24/2023 No Access for Inspection STUART CHAPMAN
Pre-Inspection 12/21/2023 No Access for Inspection STUART CHAPMAN
Excavation/Setback/Form/Re-Bar 1/10/2024 Approved ANTHONY EGSON
Footing/Foundation/Slab 1/10/2024 Not Ready for Inspection ANTHONY EGSON
Excavation/Setback/Form/Re-Bar 3/1/2024 Approved ANTHONY EGSON
Footing/Foundation/Slab 3/1/2024 Approved ANTHONY EGSON
PLUMBING-Rough 4/29/2024 Corrections Issued DAVID FEILER
Wood Frame 4/29/2024 Corrections Issued DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 6/4/2024 Not Ready for Inspection ANTHONY EGSON
Green Building Rough 6/4/2024 Not Ready for Inspection ANTHONY EGSON
PLUMBING-Rough 6/4/2024 Partial Approval ANTHONY EGSON
PLUMBING-Rough 6/7/2024 No Access for Inspection ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 6/11/2024 Partial Approval ANTHONY EGSON
Green Building Rough 6/11/2024 Not Ready for Inspection ANTHONY EGSON
PLUMBING-Rough 6/11/2024 Partial Approval ANTHONY EGSON
Insulation 6/18/2024 Partial Approval ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 6/25/2024 Partial Approval ANTHONY EGSON
Wood Frame 6/25/2024 Approved ANTHONY EGSON
Deputy Wood Construction 8/20/2024 Conditional Approval ANTHONY EGSON
Wood Frame 9/9/2024 Corrections Issued AMIR NAZARIAN
ELECTRICAL-Rough 10/17/2024 Corrections Issued ANTHONY EGSON
HVAC-Rough 10/17/2024 Corrections Issued ANTHONY EGSON
PLUMBING-Rough 10/17/2024 Corrections Issued ANTHONY EGSON
ELECTRICAL-Rough 10/31/2024 Approved BARRY HACHE
HVAC-Rough 10/31/2024 Not Ready for Inspection BARRY HACHE
PLUMBING-Rough 10/31/2024 Approved BARRY HACHE
Floor/Roof Diaphrgm/Shear Wall 1/6/2025 Approved JOSE MACIAS
HVAC-Rough 1/6/2025 Approved JOSE MACIAS
Green Building Rough 2/5/2025 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 2/5/2025 Partial Approval JUSTIN HAWLEY
Insulation 2/19/2025 Approved LUIS CASTRO
Shower Pan 3/26/2025 Approved ALEX COLIN
Drywall Nailing 4/8/2025 Approved LUIS CASTRO
BUILDING-Rough-Frame 8/26/2025 Approved LUIS CASTRO
ELECTRICAL-Final 8/26/2025 Not Ready for Inspection LUIS CASTRO
Final 8/26/2025 Not Ready for Inspection LUIS CASTRO
Green Building Final 8/26/2025 Not Ready for Inspection LUIS CASTRO
HVAC-Final 8/26/2025 Not Ready for Inspection LUIS CASTRO
PLUMBING-Final 8/26/2025 Not Ready for Inspection LUIS CASTRO
SGSOV-Seismic Gas S/O Valve 8/26/2025 SGSOV Not Ready LUIS CASTRO
Smoke Detectors 8/26/2025 Not Ready for Inspection LUIS CASTRO