2404 E SHOREDALE AVE 90031

Certificate Information: 2404 E SHOREDALE AVE 90031

Application / Permit
23014-10000-01647
Plan Check / Job No.
B23LA07875
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan CONVERSION (E) 2 STORY SINGLE FAMILY RESIDENCE AT REAR OF PROPERTY INTO 1 STORY ADU ADU CHECKED PER CA GOVT CODE 65852.2(E)(1)(B) AND LAMC 12.22 A.33 (C)-(D), (G)
Permit Issued
Issued on 12/19/2023
Issuing Office
Current Status
CofO Issued on 10/28/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/27/2023 APPLICANT
Assigned to Plan Check Engineer 5/4/2023 NGHI SU
Corrections Issued 5/13/2023 SUNMIN LEE
Quality Review Completed 5/17/2023 GARO TELMI
Plan Check Approved 12/12/2023 NGHI SU
Issued 12/19/2023 APPLICANT
Permit Finaled 10/28/2024 RUBEN SALAS
CofO Issued 10/28/2024 RUBEN SALAS
Permit Finaled 10/28/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 5/25/2023 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 5/26/2023 STEVE MELGAR
Sewer availability Cleared 5/26/2023 STEVE MELGAR
ZI Cleared 5/31/2023 MAYELA VILLA
Roof/Waste drainage to street Cleared 7/9/2023 AHMED AMARRAGY
Construction near power lines Cleared 11/2/2023 TINA MIRANDA

Contact Information

Contractor Owner-Builder       ,
Engineer Pinzon,, Eduardo Andres; Lic. No.: C74869 821 W SPRUCE ST      WEST COVINA, CA 91790

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/28/2024 Partial Approval THOMAS LOGRASSO
Footing/Foundation/Slab 3/7/2024 Approved THOMAS LOGRASSO
Deputy Wood Construction 4/17/2024 Conditional Approval THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 4/18/2024 Corrections Issued SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 4/22/2024 Partial Approval THOMAS LOGRASSO
Deputy Wood Construction 6/4/2024 Approved LILIANA PORTILLO
Underground Mechanical 6/4/2024 Partial Approval LILIANA PORTILLO
ELECTRICAL-Rough 6/6/2024 Approved HAMIK HARTOUNIAN
PLUMBING-Rough 6/6/2024 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 6/7/2024 Not Ready for Inspection HAMIK HARTOUNIAN
HVAC-Rough 6/7/2024 Corrections Issued HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 6/11/2024 Not Ready for Inspection HAMIK HARTOUNIAN
HVAC-Rough 6/11/2024 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 6/13/2024 Not Ready for Inspection HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 6/13/2024 Approved HAMIK HARTOUNIAN
Underground Mechanical 6/18/2024 Partial Approval LILIANA PORTILLO
Insulation 7/3/2024 Corrections Issued FREDDIE RIVERA
Interior/Exterior Lathing 7/3/2024 Partial Inspection FREDDIE RIVERA
BUILDING-Rough-Frame 7/8/2024 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 7/8/2024 Partial Approval HAMIK HARTOUNIAN
Insulation 7/9/2024 Approved HAMIK HARTOUNIAN
Deputy Wood Construction 7/18/2024 Conditional Approval HAMIK HARTOUNIAN
Drywall Nailing 7/18/2024 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 7/26/2024 Approved ANTHONY RAMOS
Shower Pan 7/26/2024 Approved ANTHONY RAMOS
Final 9/30/2024 Corrections Issued HAMIK HARTOUNIAN
Gas Test 9/30/2024 Corrections Issued HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 9/30/2024 SGSOV Not Ready HAMIK HARTOUNIAN
Service/Power Release 9/30/2024 Not Ready for Inspection HAMIK HARTOUNIAN
Smoke Detectors 9/30/2024 Approved HAMIK HARTOUNIAN
ELECTRICAL-Final 10/3/2024 Approved ROY SPAULDING
Gas Test 10/3/2024 Corrections Issued ROY SPAULDING
HVAC-Final 10/3/2024 Approved ROY SPAULDING
PLUMBING-Final 10/3/2024 Approved ROY SPAULDING
Service/Power Release 10/3/2024 Approved ROY SPAULDING
Final 10/24/2024 Conditional Approval LUIS CASTRO
SGSOV-Seismic Gas S/O Valve 10/24/2024 SGSOV Approved LUIS CASTRO