3341 S BEVERLY DR 90034
Certificate Information: 3341 S BEVERLY DR 90034
- Application / Permit
- 23014-10000-01642
- Plan Check / Job No.
- B23LA07851
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan CONVERSION OF (E) 400 SQFT GARAGE WITH 2ND FLOOR 534 SQFT ADDITION TO BECOME TWO STORY 934 SQFT ADU PER LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 9/5/2023
- Issuing Office
- Current Status
- CofO Issued on 8/8/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/27/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/11/2023 | JAD BASMA |
| Corrections Issued | 5/13/2023 | JAD BASMA |
| Quality Review Completed | 5/19/2023 | TEODORO DIAZ RODRIGUEZ |
| Plan Check Approved | 8/17/2023 | JAD BASMA |
| Issued | 9/5/2023 | APPLICANT |
| CofO in Progress | 8/6/2024 | HERBERT GIRON |
| Permit Finaled | 8/8/2024 | DANIEL ORRANTE |
| CofO Issued | 8/8/2024 | DANIEL ORRANTE |
| Permit Finaled | 8/8/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 5/30/2023 | JASON NG |
| Eng Process Fee Ord 176,300 | Cleared | 6/2/2023 | JASON NG |
| Sewer availability | Cleared | 6/2/2023 | JASON NG |
| Grading Pre-Inspection | Cleared | 6/5/2023 | SERGIO VALENZUELA |
| Specific Plan | Cleared | 6/8/2023 | KYLE WINSTON |
| Low Impact Development (LID) | Cleared | 8/7/2023 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 8/9/2023 | HUGO LOPEZ |
| GPI Written Notices | Cleared | 8/16/2023 | JAD BASMA |
Contact Information
| Contractor | Urban Construction & Design Solutions Inc; Lic. No.: 1030683-B | , |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 9/25/2023 | Partial Approval | MEL KHACHATOURIAN |
| Sewer | 9/27/2023 | Approved | BEN MOLSTAD |
| Footing/Foundation/Slab | 9/30/2023 | Off-Hour Fees Due | |
| Footing/Foundation/Slab | 10/2/2023 | Off-Hour Fees Due | |
| Footing/Foundation/Slab | 10/3/2023 | No Access for Inspection | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 10/3/2023 | Off-Hour Fees Due | |
| Excavation/Setback/Form/Re-Bar | 10/4/2023 | Corrections Issued | KENNETH NAGLE |
| Footing/Foundation/Slab | 10/6/2023 | Corrections Issued | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 10/11/2023 | Not Ready for Inspection | KENNETH NAGLE |
| Footing/Foundation/Slab | 10/13/2023 | Not Ready for Inspection | KENNETH NAGLE |
| Floor/Roof Diaphrgm/Shear Wall | 10/31/2023 | Corrections Issued | KENNETH NAGLE |
| Floor/Roof Diaphrgm/Shear Wall | 11/16/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 1/17/2024 | Approved | KENNETH NAGLE |
| PLUMBING-Rough | 1/17/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 2/6/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 2/6/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 2/9/2024 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 2/9/2024 | Approved | OGANES TARAKHCHYAN |
| Deputy Wood Construction | 2/13/2024 | Approved | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 2/13/2024 | Partial Approval | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 2/22/2024 | Approved | OGANES TARAKHCHYAN |
| Green Building Rough | 2/22/2024 | Approved | OGANES TARAKHCHYAN |
| MERV13>=Rough | 2/22/2024 | Approved | OGANES TARAKHCHYAN |
| Insulation | 2/27/2024 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 3/7/2024 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 3/22/2024 | Approved | OGANES TARAKHCHYAN |
| Shower Pan | 3/22/2024 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 5/6/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 5/9/2024 | No Access for Inspection | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 5/13/2024 | Corrections Issued | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 5/21/2024 | Corrections Issued | ASHLEY THOMPSON |
| Final | 6/12/2024 | Corrections Issued | ASHLEY THOMPSON |
| Green Building Final | 6/12/2024 | Approved | ASHLEY THOMPSON |
| HVAC-Final | 6/12/2024 | Approved | ASHLEY THOMPSON |
| MERV13>=Final | 6/12/2024 | Approved | ASHLEY THOMPSON |
| PLUMBING-Final | 6/12/2024 | Approved | ASHLEY THOMPSON |
| SGSOV-Seismic Gas S/O Valve | 6/12/2024 | SGSOV Approved | ASHLEY THOMPSON |
| Smoke Detectors | 6/12/2024 | Approved | ASHLEY THOMPSON |
| ELECTRICAL-Final | 8/5/2024 | Approved | HERBERT GIRON |
| Final | 8/5/2024 | OK to Issue CofO | HERBERT GIRON |
| Service/Power Release | 8/5/2024 | Approved | HERBERT GIRON |