5722 W JEFFERSON BLVD 90016
Certificate Information: 5722 W JEFFERSON BLVD 90016
- Application / Permit
- 23014-10000-01629
- Plan Check / Job No.
- B23LA07767
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (22) Warehouse
- Work Description
- 2nd FLOOR ADDITION WITHIN (E) 1 STORY WAREHOUSE FOR STORAGE ROOMS
- Permit Issued
- Issued on 7/27/2023
- Issuing Office
- Metro
- Current Status
- Issued on 7/27/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/26/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/4/2023 | HERNAN ARREOLA |
| Corrections Issued | 5/13/2023 | HERNAN ARREOLA |
| Quality Review Completed | 5/17/2023 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 5/22/2023 | APPLICANT |
| Disabled Access Plans Picked Up | 6/15/2023 | APPLICANT |
| Plan Check Approved | 7/27/2023 | HERNAN ARREOLA |
| Issued | 7/27/2023 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 6/1/2023 | CELINA MORENO |
| Sewer availability | Cleared | 6/1/2023 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 6/2/2023 | CELINA MORENO |
| DAS Clearance | Cleared | 7/6/2023 | EDDIE GARIN |
| Community Plan Implem. Overlay | Cleared | 7/13/2023 | KYLE WINSTON |
| Green Code | Cleared | 7/18/2023 | NEGAR NEJAD |
Contact Information
| Architect | Segal,, Barry William; Lic. No.: C17861 | P O BOX 6108 ALTADENA, CA 91003 |
| Contractor | Arnold'S Remodeling; Lic. No.: 929036-B | 8146 LONGRIDGE AVENUE NORTH HOLLYWOOD, CA 91605 |
| Engineer | Falamaki,, Mohsen; Lic. No.: S3021 | 344 N BUNDY DRIVE LOS ANGELES, CA 90049 |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/11/2023 | Approved | ALFREDO LOPEZ |
| Wood Frame | 10/31/2023 | Approved | DARRYL ARNOLD |
| Drywall Nailing | 11/13/2023 | Approved | RICARDO ROBLES |
| Final | 12/14/2023 | Not Ready for Inspection | RICARDO ROBLES |
| Green Building Final | 12/14/2023 | Not Ready for Inspection | RICARDO ROBLES |
| Green Building Rough | 12/14/2023 | Not Ready for Inspection | RICARDO ROBLES |
| Reinforced Masonry Frame | 12/14/2023 | Not Ready for Inspection | RICARDO ROBLES |
| SGSOV-Seismic Gas S/O Valve | 12/14/2023 | SGSOV Not Ready | RICARDO ROBLES |
| Smoke Detectors | 12/14/2023 | Not Ready for Inspection | RICARDO ROBLES |
| Final | 12/21/2023 | Not Ready for Inspection | LUIS CCAMACHO |
| Green Building Final | 12/21/2023 | Not Ready for Inspection | LUIS CCAMACHO |
| Green Building Rough | 12/21/2023 | Not Ready for Inspection | LUIS CCAMACHO |
| Reinforced Masonry Frame | 12/21/2023 | Not Ready for Inspection | LUIS CCAMACHO |
| SGSOV-Seismic Gas S/O Valve | 12/21/2023 | SGSOV Not Ready | LUIS CCAMACHO |
| Smoke Detectors | 12/21/2023 | Not Ready for Inspection | LUIS CCAMACHO |
| Final | 1/3/2024 | Not Ready for Inspection | RICARDO ROBLES |
| Green Building Final | 1/3/2024 | Not Ready for Inspection | RICARDO ROBLES |
| Green Building Rough | 1/3/2024 | Not Ready for Inspection | RICARDO ROBLES |
| Reinforced Masonry Frame | 1/3/2024 | Not Ready for Inspection | RICARDO ROBLES |
| SGSOV-Seismic Gas S/O Valve | 1/3/2024 | SGSOV Not Ready | RICARDO ROBLES |
| Smoke Detectors | 1/3/2024 | Not Ready for Inspection | RICARDO ROBLES |
| Final | 1/24/2024 | Partial Approval | RICARDO ROBLES |
| Green Building Final | 1/24/2024 | Approved | RICARDO ROBLES |
| Green Building Rough | 1/24/2024 | Approved | RICARDO ROBLES |
| Reinforced Masonry Frame | 1/24/2024 | Approved | RICARDO ROBLES |
| SGSOV-Seismic Gas S/O Valve | 1/24/2024 | SGSOV Approved | RICARDO ROBLES |
| Smoke Detectors | 1/24/2024 | Approved | RICARDO ROBLES |