3917 S SOMERSET DR 90008
Certificate Information: 3917 S SOMERSET DR 90008
- Application / Permit
- 23014-10000-01614
- Plan Check / Job No.
- B23LA07716
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition to rear of (E) SFD. Scope includes major remodel of (E) structure. All work per engineered plans. Sprinklered thruout
- Permit Issued
- Issued on 9/5/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 5/29/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/26/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/1/2023 | LAWRENCE QUIRANTE |
| Corrections Issued | 5/3/2023 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 5/5/2023 | APPLICANT |
| Applicant returned to address corrections | 5/18/2023 | WEIJIAN HUANG |
| Applicant returned to address corrections | 6/2/2023 | MICHAEL LANZONE |
| Plan Check Approved | 6/7/2023 | MICHAEL LANZONE |
| Issued | 9/5/2023 | APPLICANT |
| CofO in Progress | 5/20/2024 | ANTHONY EGSON |
| Permit Finaled | 5/29/2024 | DEROLD HAUFF |
| CofO Issued | 5/29/2024 | DEROLD HAUFF |
| Permit Finaled | 5/29/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction near power lines | Cleared | 5/16/2023 | TORI CHEN |
| Eng Process Fee Ord 176,300 | Cleared | 5/23/2023 | WALLIE JONG |
| Sewer availability | Cleared | 5/23/2023 | WALLIE JONG |
| Low Impact Development (LID) | Cleared | 5/25/2023 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 5/26/2023 | HUGO LOPEZ |
Contact Information
| Contractor | All City Builders & Design Inc; Lic. No.: 1075374-B | 1450 N TUSTIN AVE #115 SANTA ANA, CA 92705 |
| Engineer | Doenitz,, Halle; Lic. No.: C91458 | 1010 OWOSSO AVE HERMOSA BEACH, CA 90254 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/19/2023 | Approved | ANTHONY EGSON |
| Footing/Foundation/Slab | 9/20/2023 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 9/29/2023 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/23/2023 | Partial Approval | ANTHONY EGSON |
| PLUMBING-Rough | 10/23/2023 | Corrections Issued | ANTHONY EGSON |
| Underground Mechanical | 10/26/2023 | Approved | ANTHONY EGSON |
| Insulation | 10/31/2023 | Partial Approval | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/2/2023 | Corrections Issued | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/6/2023 | Partial Approval | ANTHONY EGSON |
| Deputy Wood Construction | 12/20/2023 | Conditional Approval | BRENDAN MORELLI |
| PLUMBING-Rough | 12/21/2023 | Approved | STUART CHAPMAN |
| ELECTRICAL-Rough | 12/22/2023 | Approved | STUART CHAPMAN |
| HVAC-Rough | 12/22/2023 | Approved | STUART CHAPMAN |
| Deputy Wood Construction | 12/27/2023 | Approved | ANTHONY EGSON |
| Wood Frame | 12/27/2023 | Corrections Issued | ANTHONY EGSON |
| Wood Frame | 1/8/2024 | Corrections Issued | ANTHONY EGSON |
| BUILDING-Rough-Frame | 1/26/2024 | Partial Approval | ANTHONY EGSON |
| Green Building Rough | 1/26/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Interior/Exterior Lathing | 1/31/2024 | Approved | ANTHONY EGSON |
| Insulation | 2/7/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Insulation | 2/9/2024 | Approved | RONNIE MINDANAO |
| Drywall Nailing | 2/13/2024 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 2/13/2024 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 2/21/2024 | Approved | ANTHONY EGSON |
| Shower Pan | 2/21/2024 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 4/23/2024 | Approved | ANTHONY EGSON |
| Final | 4/23/2024 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 4/23/2024 | Not Ready for Inspection | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 4/23/2024 | SGSOV Approved | ANTHONY EGSON |
| Smoke Detectors | 4/23/2024 | Approved | ANTHONY EGSON |
| Final | 4/29/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Final | 4/29/2024 | Approved | ANTHONY EGSON |
| Final | 5/15/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Final | 5/17/2024 | OK to Issue CofO | ANTHONY EGSON |