7724 S DENROCK AVE 90045
Certificate Information: 7724 S DENROCK AVE 90045
- Application / Permit
- 23014-10000-01605
- Plan Check / Job No.
- B23LA07659
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO SFD REAR ADDITION/FRONT PORCH ADDITION .MASTER BATH/LIVING REMODEL
- Permit Issued
- Issued on 7/24/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/25/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/27/2023 | ARSALAN SHABESTARI |
| Corrections Issued | 5/3/2023 | ARSALAN SHABESTARI |
| Quality Review Completed | 5/10/2023 | KEN GILL |
| Building Plans Picked Up | 5/12/2023 | APPLICANT |
| Applicant returned to address corrections | 7/12/2023 | ARSALAN SHABESTARI |
| Plan Check Approved | 7/24/2023 | ARSALAN SHABESTARI |
| Issued | 7/24/2023 | APPLICANT |
| CofO in Progress | 2/12/2024 | BOBBY KEY |
| Permit Finaled | 2/17/2024 | DANIEL ORRANTE |
| CofO Issued | 2/17/2024 | DANIEL ORRANTE |
| Permit Finaled | 2/17/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/23/2023 | DARIN LAM |
| Sewer availability | Cleared | 5/23/2023 | DARIN LAM |
| Grading Pre-Inspection | Cleared | 5/25/2023 | ALEXANDER HELFER |
| Specific Plan | Cleared | 6/23/2023 | PEDRO AYALA |
| Low Impact Development (LID) | Cleared | 7/14/2023 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 7/14/2023 | AHMED AMARRAGY |
Contact Information
| Contractor | Forsyth Construction Inc; Lic. No.: 560243-B | 578 WASHINGTON BLVD #377 MARINA DEL REY, CA 90292 |
| Engineer | Erdelyi,, Peter Tibor; Lic. No.: C26962 | 2999 OVERLAND AVE STE 103 LOS ANGELES, CA 90064 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/5/2023 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 9/15/2023 | Partial Approval | BOBBY KEY |
| Wood Frame | 9/15/2023 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 9/20/2023 | Partial Approval | BOBBY KEY |
| Insulation | 9/20/2023 | Approved | BOBBY KEY |
| Deputy Wood Construction | 10/6/2023 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 10/6/2023 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 10/12/2023 | Approved | BOBBY KEY |
| ELECTRICAL-Rough | 10/12/2023 | Conditional Approval | BOBBY KEY |
| Gas Test | 10/12/2023 | Partial Approval | BOBBY KEY |
| Green Building Rough | 10/12/2023 | Not Ready for Inspection | BOBBY KEY |
| HVAC-Rough | 10/12/2023 | Conditional Approval | BOBBY KEY |
| Interior/Exterior Lathing | 10/12/2023 | Not Ready for Inspection | BOBBY KEY |
| METHANE-Rough | 10/12/2023 | Approved | BOBBY KEY |
| PLUMBING-Rough | 10/12/2023 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 10/18/2023 | Approved | BOBBY KEY |
| Green Building Rough | 10/18/2023 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 10/18/2023 | Partial Approval | BOBBY KEY |
| Shower Pan | 10/18/2023 | Approved | BOBBY KEY |
| HVAC-Rough | 10/26/2023 | Approved | TEMISTOCLES CAAL |
| Insulation | 10/26/2023 | Approved | TEMISTOCLES CAAL |
| Drywall Nailing | 11/1/2023 | Approved | RICHARD STEINBACH |
| ELECTRICAL-Final | 2/6/2024 | Corrections Issued | BOBBY KEY |
| Final | 2/6/2024 | Not Ready for Inspection | BOBBY KEY |
| Green Building Final | 2/6/2024 | Approved | BOBBY KEY |
| HVAC-Final | 2/6/2024 | Corrections Issued | BOBBY KEY |
| Interior/Exterior Lathing | 2/6/2024 | Approved | BOBBY KEY |
| PLUMBING-Final | 2/6/2024 | Corrections Issued | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 2/6/2024 | SGSOV Approved | BOBBY KEY |
| Smoke Detectors | 2/6/2024 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 2/12/2024 | Approved | BOBBY KEY |
| Final | 2/12/2024 | OK to Issue CofO | BOBBY KEY |
| HVAC-Final | 2/12/2024 | Approved | BOBBY KEY |
| PLUMBING-Final | 2/12/2024 | Approved | BOBBY KEY |
| Service/Power Release | 2/12/2024 | Approved | BOBBY KEY |