1248 N LAKME AVE 90744

Certificate Information: 1248 N LAKME AVE 90744

Application / Permit
23014-10000-01603
Plan Check / Job No.
B23LA07647
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN 827 SF ROOM ADDITION TO SFD ***FIRE SPRINKLERS REQUIRED PER NFPA 13D***
Permit Issued
Issued on 1/8/2025
Issuing Office
Current Status
Issued on 1/8/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/21/2023 APPLICANT
Assigned to Plan Check Engineer 6/26/2023 JOSEPH RAFOLS
Corrections Issued 6/27/2023 JOSEPH RAFOLS
Applicant returned to address corrections 8/17/2023 MICHAEL LOPEZ
Plan Check Approved 11/6/2024 JOSEPH RAFOLS
Issued 1/8/2025 APPLICANT

Permit Application Clearance Information

Low Impact Development (LID) Cleared 4/20/2024 MARTIN FRAGOSO
Eng Process Fee Ord 176,300 Cleared 9/18/2024 ERIK BEASLEY
Sewer availability Cleared 9/18/2024 ERIK BEASLEY
Clean Up Green Up Cleared 10/10/2024 ROSALINDA MEZA
HPOZ Cleared 10/23/2024 JORGE RUIZ
Historic monument Cleared 10/23/2024 JORGE RUIZ
Roof/Waste drainage to street Cleared 10/29/2024 ADRIAN SANCHEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Hale,, Ronald Richard; Lic. No.: C17056 1869 PALACIOS DR      SAN PEDRO, CA 90732

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/10/2025 Conditional Approval JOSEPH MCGARRY
METHANE-Barrier 1/10/2025 Approved JOSEPH MCGARRY
METHANE-Subgrade 1/10/2025 Approved JOSEPH MCGARRY
PLUMBING-Rough 1/22/2025 Partial Approval ANSON MAGLASANG
Wood Frame 1/22/2025 Partial Approval ANSON MAGLASANG
Floor/Roof Diaphrgm/Shear Wall 1/27/2025 Partial Approval EUGENE CASSIDY
Insulation 1/27/2025 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 2/28/2025 Partial Approval EUGENE CASSIDY
ELECTRICAL-Rough 3/25/2025 Partial Approval EUGENE CASSIDY
PLUMBING-Rough 3/25/2025 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Rough 4/7/2025 Approved EUGENE CASSIDY
PLUMBING-Rough 4/7/2025 Approved EUGENE CASSIDY
Service/Power Release 4/7/2025 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 5/2/2025 Approved EUGENE CASSIDY
Green Building Rough 5/2/2025 Approved EUGENE CASSIDY
HVAC-Final 5/2/2025 Not Ready for Inspection JOSEPH MCGARRY
HVAC-Rough 5/2/2025 Approved EUGENE CASSIDY
METHANE-Rough 5/2/2025 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 5/6/2025 Approved EUGENE CASSIDY
Insulation 5/6/2025 Approved EUGENE CASSIDY
Drywall Nailing 5/8/2025 Approved EUGENE CASSIDY
Special/Order Compliance 5/8/2025 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Rough 5/21/2025 Approved EUGENE CASSIDY
HVAC-Rough 5/21/2025 Approved EUGENE CASSIDY