5339 E TEMPLETON ST 90032

Certificate Information: 5339 E TEMPLETON ST 90032

Application / Permit
23014-10000-01597
Plan Check / Job No.
B23LA07620
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan CONVERT 395 SF PORTION OF (E) 434 SF GARAGE AND ADDITION OF 150 SF INTO AN ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). CONVERT REMAINING 39 SF OF (E) GARAGE TO STORAGE. ALL WORK PER ENG.
Permit Issued
Issued on 12/8/2023
Issuing Office
Current Status
CofO Issued on 11/4/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/25/2023 APPLICANT
Assigned to Plan Check Engineer 4/28/2023 LUISANGEL VALENZUELA
Corrections Issued 4/28/2023 LUISANGEL VALENZUELA
Plan Check Approved 8/29/2023 LUISANGEL VALENZUELA
Issued 12/8/2023 APPLICANT
CofO in Progress 10/18/2024 LILIANA PORTILLO
No Progress 10/25/2024 CHARLES BOGHOSKHAN
CofO in Progress 10/25/2024 CHARLES BOGHOSKHAN
CofO Issued 11/4/2024 DEROLD HAUFF
Permit Finaled 11/4/2024 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 5/22/2023 SERGIO VALENZUELA
Address approval Cleared 5/30/2023 JESSICA OPINION
Roof/Waste drainage to street Cleared 5/30/2023 JESSICA OPINION
Eng Process Fee Ord 176,300 Cleared 6/1/2023 JESSICA OPINION
Sewer availability Cleared 6/1/2023 JESSICA OPINION

Contact Information

Contractor Riaan Construction; Lic. No.: 1113393-B       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/18/2023 Approved AMY COLIN
Footing/Foundation/Slab 12/18/2023 Approved AMY COLIN
Sewer 12/18/2023 Approved AMY COLIN
Floor/Roof Diaphrgm/Shear Wall 1/19/2024 Partial Approval AMY COLIN
ELECTRICAL-Rough 1/29/2024 Approved BRENDAN MORELLI
HVAC-Rough 1/29/2024 Corrections Issued BRENDAN MORELLI
PLUMBING-Rough 1/29/2024 Corrections Issued BRENDAN MORELLI
Insulation 3/5/2024 Corrections Issued LILIANA PORTILLO
Interior/Exterior Lathing 3/5/2024 Partial Approval LILIANA PORTILLO
BUILDING-Rough-Frame 3/7/2024 Approved LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 3/7/2024 Approved LILIANA PORTILLO
Green Building Rough 3/7/2024 Approved LILIANA PORTILLO
HVAC-Rough 3/7/2024 Approved LILIANA PORTILLO
Insulation 3/7/2024 Corrections Issued LILIANA PORTILLO
PLUMBING-Rough 3/7/2024 Approved LILIANA PORTILLO
Insulation 3/11/2024 Approved LILIANA PORTILLO
Drywall Nailing 3/18/2024 Approved HAMIK HARTOUNIAN
Shower Pan 3/18/2024 Not Ready for Inspection HAMIK HARTOUNIAN
Interior/Exterior Lathing 4/17/2024 Approved LILIANA PORTILLO
Shower Pan 4/17/2024 Approved LILIANA PORTILLO
ELECTRICAL-Final 10/7/2024 Not Ready for Inspection LILIANA PORTILLO
Final 10/7/2024 Corrections Issued LILIANA PORTILLO
Green Building Final 10/7/2024 Not Ready for Inspection LILIANA PORTILLO
HVAC-Final 10/7/2024 Not Ready for Inspection LILIANA PORTILLO
PLUMBING-Final 10/7/2024 Not Ready for Inspection LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 10/7/2024 SGSOV Not Required LILIANA PORTILLO
Smoke Detectors 10/7/2024 Approved LILIANA PORTILLO
ELECTRICAL-Final 10/17/2024 Approved LILIANA PORTILLO
Final 10/17/2024 OK to Issue CofO LILIANA PORTILLO
Green Building Final 10/17/2024 Approved LILIANA PORTILLO
HVAC-Final 10/17/2024 Approved LILIANA PORTILLO
PLUMBING-Final 10/17/2024 Approved LILIANA PORTILLO