1900 S CLYDE AVE 90019
Certificate Information: 1900 S CLYDE AVE 90019
- Application / Permit
- 23014-10000-01585
- Plan Check / Job No.
- B23LA07504
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition 474 sf. to existing single family house + attached garage
- Permit Issued
- Issued on 5/10/2023
- Issuing Office
- Current Status
- CofO Issued on 4/16/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/24/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/28/2023 | JOSEPH RAFOLS |
| Corrections Issued | 5/1/2023 | JOSEPH RAFOLS |
| Plan Check Approved | 5/10/2023 | JOSEPH RAFOLS |
| Issued | 5/10/2023 | APPLICANT |
| CofO in Progress | 4/9/2024 | ALIZAH MAYAGOITIA |
| Permit Finaled | 4/16/2024 | DEROLD HAUFF |
| CofO Issued | 4/16/2024 | DEROLD HAUFF |
| Permit Finaled | 4/16/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 5/9/2023 | WALLIE JONG |
| Sewer availability | Cleared | 5/9/2023 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 5/10/2023 | WALLIE JONG |
Contact Information
| Contractor | Primary Design Builders Inc; Lic. No.: 1036604-B | , |
| Engineer | Hwang,, Junho; Lic. No.: NA5592 | , |
| Engineer | Hwang,, Junho; Lic. No.: S5592 | 815 FAIRVIEW AVE #205 SOUTH PASADENA, CA 91030 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/25/2023 | Conditional Approval | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 6/6/2023 | Partial Approval | JOSE AVILA |
| Footing/Foundation/Slab | 6/6/2023 | Partial Approval | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 7/11/2023 | Partial Approval | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 7/18/2023 | Approved | JOSE AVILA |
| Insulation | 7/18/2023 | Partial Approval | JOSE AVILA |
| BUILDING-Rough-Frame | 10/13/2023 | Approved Pending GreenApproval | RONNIE MINDANAO |
| ELECTRICAL-Rough | 10/13/2023 | Corrections Issued | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 10/13/2023 | Not Ready for Inspection | RONNIE MINDANAO |
| Green Building Rough | 10/13/2023 | Not Ready for Inspection | RONNIE MINDANAO |
| HVAC-Rough | 10/13/2023 | Not Ready for Inspection | RONNIE MINDANAO |
| PLUMBING-Rough | 10/13/2023 | Partial Approval | RONNIE MINDANAO |
| ELECTRICAL-Rough | 10/17/2023 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 10/17/2023 | Corrections Issued | JOSE AVILA |
| HVAC-Rough | 10/17/2023 | Corrections Issued | JOSE AVILA |
| PLUMBING-Rough | 10/17/2023 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 11/16/2023 | Not Ready for Inspection | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 11/16/2023 | Partial Approval | RONNIE MINDANAO |
| Green Building Rough | 11/16/2023 | Not Ready for Inspection | RONNIE MINDANAO |
| HVAC-Rough | 11/16/2023 | Corrections Issued | RONNIE MINDANAO |
| Deputy Wood Construction | 11/20/2023 | Conditional Approval | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 11/29/2023 | Partial Approval | JOSE AVILA |
| Green Building Rough | 12/4/2023 | Not Ready for Inspection | RONNIE MINDANAO |
| Interior/Exterior Lathing | 12/4/2023 | Corrections Issued | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 12/6/2023 | Approved | RONNIE MINDANAO |
| Green Building Rough | 12/6/2023 | Approved | RONNIE MINDANAO |
| Service/Power Release | 12/6/2023 | Not Ready for Inspection | RONNIE MINDANAO |
| HVAC-Rough | 12/8/2023 | Approved | RONNIE MINDANAO |
| Interior/Exterior Lathing | 12/8/2023 | Approved | RONNIE MINDANAO |
| Insulation | 12/13/2023 | Approved | SCOTT FINNILA |
| Drywall Nailing | 12/19/2023 | Approved | RONNIE MINDANAO |
| Shower Pan | 12/19/2023 | Not Ready for Inspection | RONNIE MINDANAO |
| Drywall Nailing | 12/20/2023 | Approved | RONNIE MINDANAO |
| Interior/Exterior Lathing | 12/26/2023 | Approved | RONNIE MINDANAO |
| Shower Pan | 12/26/2023 | Approved | RONNIE MINDANAO |
| ELECTRICAL-Final | 3/22/2024 | Not Ready for Inspection | STUART CHAPMAN |
| Final | 3/22/2024 | Corrections Issued | STUART CHAPMAN |
| Footing/Foundation/Slab | 3/22/2024 | Approved | STUART CHAPMAN |
| Green Building Final | 3/22/2024 | Approved | STUART CHAPMAN |
| HVAC-Final | 3/22/2024 | Not Ready for Inspection | STUART CHAPMAN |
| PLUMBING-Final | 3/22/2024 | Not Ready for Inspection | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 3/22/2024 | SGSOV Not Ready | STUART CHAPMAN |
| Smoke Detectors | 3/22/2024 | Approved | STUART CHAPMAN |
| ELECTRICAL-Final | 3/27/2024 | Approved | STUART CHAPMAN |
| Final | 3/27/2024 | Corrections Issued | STUART CHAPMAN |
| HVAC-Final | 3/27/2024 | Approved | STUART CHAPMAN |
| PLUMBING-Final | 3/27/2024 | Approved | STUART CHAPMAN |
| Service/Power Release | 3/27/2024 | Not Ready for Inspection | STUART CHAPMAN |
| Final | 4/3/2024 | Corrections Issued | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 4/3/2024 | SGSOV Approved | RICHARD DOCKUS |
| Final | 4/8/2024 | OK to Issue CofO | ALIZAH MAYAGOITIA |
| Service/Power Release | 4/8/2024 | Approved | ALIZAH MAYAGOITIA |