4438-4438 1/2 E JASPER ST 90032

Certificate Information: 4438-4438 1/2 E JASPER ST 90032

Application / Permit
23014-10000-01579
Plan Check / Job No.
B23LA07489
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: EXTERIOR REMODEL TO (E) 2-STORY S.F.D. TO ADD NEW DOOR TO CRAWL SPACE AND CONVERT (E) CRAWL SPACE OF (E) S.F.D. INTO A (N) ATTACHED IRREGULAR SHAPED 34'-5" x 14'-9" ACCESSORY DWELLING UNIT TO COMPLY WITH LAMC 12.22 A.33(c) AND (e) PER DESIGN
Permit Issued
Issued on 7/7/2023
Issuing Office
Current Status
CofO Issued on 8/9/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/24/2023 APPLICANT
Assigned to Plan Check Engineer 4/28/2023 ALFRED RAMIREZ
Corrections Issued 4/29/2023 ALFRED RAMIREZ
Plan Check Approved 6/29/2023 ALFRED RAMIREZ
Plan Check Approved 7/7/2023 ALFRED RAMIREZ
Issued 7/7/2023 APPLICANT
CofO in Progress 7/26/2025 ALIZAH MAYAGOITIA
No Progress 8/3/2025 DEROLD HAUFF
CofO in Progress 8/3/2025 DEROLD HAUFF
Permit Finaled 8/9/2025 DEROLD HAUFF
CofO Issued 8/9/2025 DEROLD HAUFF
Permit Finaled 8/9/2025 DEROLD HAUFF

Permit Application Clearance Information

"Q" conditions Cleared 5/23/2023 RYAN LY
ZI Cleared 5/23/2023 RYAN LY
Address approval Cleared 5/31/2023 HUGO LOPEZ
Eng Process Fee Ord 176,300 Cleared 5/31/2023 HUGO LOPEZ
Sewer availability Cleared 5/31/2023 HUGO LOPEZ
Grading Pre-Inspection Cleared 6/29/2023 ALFRED RAMIREZ

Contact Information

Architect Le, Clerc, Sarah Jane; Lic. No.: NA39716       ,
Architect Noteware,, Brian Arthur; Lic. No.: C21514 845 20TH STREET, #106      SANTA MONICA, CA 90403
Contractor Owner-Builder       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/18/2024 Partial Approval LILIANA PORTILLO
Sewer 6/18/2024 Not Ready for Inspection LILIANA PORTILLO
Deputy Drilled-In Anchors 6/28/2024 Conditional Approval LILIANA PORTILLO
Deputy Drilled-In Anchors 7/1/2024 Conditional Approval LILIANA PORTILLO
Footing/Foundation/Slab 7/2/2024 Approved LILIANA PORTILLO
Pre-Inspection 8/26/2024 Partial Inspection LILIANA PORTILLO
PLUMBING-Rough 8/30/2024 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Rough 10/23/2024 Corrections Issued LILIANA PORTILLO
Interior/Exterior Lathing 10/23/2024 Partial Approval LILIANA PORTILLO
PLUMBING-Rough 10/23/2024 Approved LILIANA PORTILLO
Wood Frame 10/23/2024 Not Ready for Inspection LILIANA PORTILLO
ELECTRICAL-Rough 11/1/2024 Not Ready for Inspection LILIANA PORTILLO
HVAC-Rough 11/1/2024 Not Ready for Inspection LILIANA PORTILLO
Wood Frame 11/1/2024 Not Ready for Inspection LILIANA PORTILLO
ELECTRICAL-Rough 11/6/2024 Not Ready for Inspection LILIANA PORTILLO
HVAC-Rough 11/6/2024 Corrections Issued LILIANA PORTILLO
BUILDING-Rough-Frame 12/12/2024 Approved LILIANA PORTILLO
ELECTRICAL-Rough 12/12/2024 Approved LILIANA PORTILLO
HVAC-Rough 12/12/2024 Approved LILIANA PORTILLO
Insulation 12/24/2024 Approved LILIANA PORTILLO
Drywall Nailing 1/27/2025 Approved LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 1/27/2025 Approved LILIANA PORTILLO
Interior/Exterior Lathing 1/27/2025 Approved LILIANA PORTILLO
Shower Pan 1/27/2025 Approved LILIANA PORTILLO
PLUMBING-Final 7/7/2025 Approved LILIANA PORTILLO
ELECTRICAL-Final 7/25/2025 Approved ALIZAH MAYAGOITIA
Final 7/25/2025 OK to Issue CofO ALIZAH MAYAGOITIA
HVAC-Final 7/25/2025 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 7/25/2025 SGSOV Approved ALIZAH MAYAGOITIA
Smoke Detectors 7/25/2025 Approved ALIZAH MAYAGOITIA