2225 S WALNUT AVE 90291

Certificate Information: 2225 S WALNUT AVE 90291

Application / Permit
23014-10000-01564
Plan Check / Job No.
B23LA07416
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: Addition (143sf) to an existing one story SFD. Major remodel to dwelling. Dwelling to be sprinklered system throughout.
Permit Issued
Issued on 5/19/2023
Issuing Office
Current Status
CofO Issued on 6/7/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/20/2023 APPLICANT
Assigned to Plan Check Engineer 4/26/2023 MINA HABILI
Corrections Issued 4/27/2023 MINA HABILI
Plan Check Approved 5/18/2023 RICARDO RAMIREZ
Issued 5/19/2023 APPLICANT
CofO in Progress 6/5/2024 HERBERT GIRON
Permit Finaled 6/7/2024 DANIEL ORRANTE
CofO Issued 6/7/2024 DANIEL ORRANTE
Permit Finaled 6/7/2024 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/10/2023 DARIN LAM
Roof/Waste drainage to street Cleared 5/10/2023 DARIN LAM
Specific Plan Cleared 5/10/2023 ALESSANDRO MERCURI

Contact Information

Contractor Global Developers Inc; Lic. No.: 1023874-B       ,
Engineer Markarian,, Mardiros; Lic. No.: C53434 3814 VANALDEN AVE      TARZANA, CA 91356

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/14/2023 Conditional Approval EVAN COOPER
Excavation/Setback/Form/Re-Bar 7/19/2023 Corrections Issued EVAN COOPER
Pre-Inspection 7/19/2023 Not Ready for Inspection EVAN COOPER
Footing/Foundation/Slab 7/27/2023 Corrections Issued EVAN COOPER
Wood Frame 7/27/2023 Not Ready for Inspection EVAN COOPER
PLUMBING-Rough 8/28/2023 Corrections Issued HERBERT GIRON
Wood Frame 8/28/2023 Not Ready for Inspection HERBERT GIRON
Insulation 8/30/2023 Not Ready for Inspection HERBERT GIRON
PLUMBING-Rough 8/30/2023 Partial Approval HERBERT GIRON
Wood Frame 8/30/2023 Corrections Issued HERBERT GIRON
BUILDING-Rough-Frame 9/1/2023 Partial Approval HERBERT GIRON
Footing/Foundation/Slab 9/1/2023 Corrections Issued HERBERT GIRON
Insulation 9/1/2023 Partial Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 9/7/2023 Partial Approval HERBERT GIRON
Footing/Foundation/Slab 9/7/2023 Approved HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 10/5/2023 Partial Approval JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 10/18/2023 Not Ready for Inspection RICHARD STEINBACH
PLUMBING-Rough 10/18/2023 Partial Inspection RICHARD STEINBACH
Floor/Roof Diaphrgm/Shear Wall 11/3/2023 Corrections Issued HERBERT GIRON
ELECTRICAL-Rough 11/9/2023 Approved HERBERT GIRON
PLUMBING-Rough 11/9/2023 Approved HERBERT GIRON
HVAC-Rough 11/14/2023 Approved TEMISTOCLES CAAL
PLUMBING-Rough 11/14/2023 Approved TEMISTOCLES CAAL
BUILDING-Rough-Frame 11/16/2023 Corrections Issued HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 11/16/2023 Approved HERBERT GIRON
BUILDING-Rough-Frame 12/4/2023 Approved HERBERT GIRON
Green Building Rough 12/4/2023 Approved HERBERT GIRON
Interior/Exterior Lathing 12/4/2023 Partial Approval HERBERT GIRON
Verify Sprinkler Sign Off 12/4/2023 Approved HERBERT GIRON
Shower Pan 12/8/2023 Approved HERBERT GIRON
Insulation 12/13/2023 Approved HERBERT GIRON
Interior/Exterior Lathing 12/13/2023 Approved HERBERT GIRON
Drywall Nailing 12/21/2023 Approved HERBERT GIRON
Service/Power Release 2/20/2024 Not Ready for Inspection HERBERT GIRON
Gas Test 3/27/2024 Approved HERBERT GIRON
Grounding or Bonding 4/10/2024 Partial Approval HERBERT GIRON
HVAC-Final 5/1/2024 Corrections Issued HERBERT GIRON
PLUMBING-Final 5/1/2024 Approved HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 5/1/2024 SGSOV Approved HERBERT GIRON
Smoke Detectors 5/1/2024 Approved HERBERT GIRON
ELECTRICAL-Final 5/3/2024 Corrections Issued HERBERT GIRON
Final 5/3/2024 Corrections Issued HERBERT GIRON
Green Building Final 5/3/2024 Approved HERBERT GIRON
HVAC-Final 5/3/2024 Approved HERBERT GIRON
PLUMBING-Final 5/3/2024 Approved HERBERT GIRON
ELECTRICAL-Final 5/7/2024 Approved HERBERT GIRON
Final 5/7/2024 Corrections Issued HERBERT GIRON
Final 6/4/2024 OK to Issue CofO HERBERT GIRON
Service/Power Release 6/4/2024 Approved HERBERT GIRON