725 N MANSFIELD AVE 90038

Certificate Information: 725 N MANSFIELD AVE 90038

Application / Permit
23014-10000-01560
Plan Check / Job No.
B23LA07368
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) DETACHED 1-STORY ADU (390 SF) PER CA Govt. Code 65852.2(e)(1)(B) and applicable part2 of LAMC 12.22 A.33(c)-(d), (g) - 800 SF max New Construction per State Law. All work done per engineer.
Permit Issued
Issued on 10/11/2024
Issuing Office
Metro
Current Status
CofO Issued on 6/2/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/20/2023 APPLICANT
Assigned to Plan Check Engineer 4/27/2023 AUNG SOE
Building Plans Picked Up 5/5/2023 APPLICANT
Corrections Issued 7/25/2023 AUNG SOE
Applicant returned to address corrections 8/18/2023 GEORGE ALVAREZ
Applicant returned to address corrections 9/28/2023 DANIEL SANJUAN
Applicant returned to address corrections 3/21/2024 DANIEL SMILEY
Plan Check Approved 10/11/2024 JOHN MESIAS
Issued 10/11/2024 APPLICANT
CofO in Progress 6/1/2026 BRIAN SULLIVAN
CofO Issued 6/2/2026 DEROLD HAUFF
Permit Finaled 6/2/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/14/2023 CHRISTINA BRACO
Roof/Waste drainage to street Cleared 9/14/2023 CHRISTINA BRACO
Eng Process Fee Ord 176,300 Cleared 3/20/2024 CHRISTINA BRACO
Roof/Waste drainage to street Cleared 3/20/2024 CHRISTINA BRACO
Sewer availability Cleared 3/20/2024 CHRISTINA BRACO
Construction near power lines Cleared 4/29/2024 TINA MIRANDA
Construction within easement Cleared 4/29/2024 TINA MIRANDA

Contact Information

Contractor Owner-Builder       ,
Engineer Liu,, Joseph; Lic. No.: C60045 825 S GOLDEN WEST AVE 9      ARCADIA, CA 91007

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/26/2025 Corrections Issued CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 4/1/2025 Approved CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 4/14/2025 Corrections Issued CRAIG VAUGHAN
BUILDING-Rough-Frame 4/16/2025 Partial Approval CRAIG VAUGHAN
PLUMBING-Rough 4/16/2025 Partial Approval CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 5/22/2025 Partial Approval BRIAN SULLIVAN
BUILDING-Rough-Frame 7/8/2025 Partial Approval CRAIG VAUGHAN
ELECTRICAL-Rough 7/8/2025 Corrections Issued CRAIG VAUGHAN
Green Building Rough 7/8/2025 Approved CRAIG VAUGHAN
HVAC-Rough 7/8/2025 Approved CRAIG VAUGHAN
METHANE-Rough 7/8/2025 Approved CRAIG VAUGHAN
PLUMBING-Rough 7/8/2025 Corrections Issued CRAIG VAUGHAN
Verify Sprinkler Sign Off 7/8/2025 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 7/15/2025 Approved CRAIG VAUGHAN
Rough-Elec/Plmb/HVAC 7/15/2025 Approved CRAIG VAUGHAN
Sewer 7/15/2025 Approved CRAIG VAUGHAN
Underground Mechanical 7/15/2025 Partial Approval CRAIG VAUGHAN
Insulation 7/24/2025 Approved DEVON JACKSON
Shower Pan 7/24/2025 Not Ready for Inspection DEVON JACKSON
Drywall Nailing 7/31/2025 Approved CRAIG VAUGHAN
Shower Pan 7/31/2025 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 8/14/2025 Approved ROY SPAULDING
ELECTRICAL-Final 3/18/2026 Corrections Issued CRAIG VAUGHAN
Final 3/18/2026 Corrections Issued CRAIG VAUGHAN
Footing/Foundation/Slab 3/18/2026 Approved CRAIG VAUGHAN
Green Building Final 3/18/2026 Approved CRAIG VAUGHAN
METHANE-Barrier 3/18/2026 Approved CRAIG VAUGHAN
METHANE-Subgrade 3/18/2026 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 3/18/2026 SGSOV Approved CRAIG VAUGHAN
Service/Power Release 3/18/2026 Approved CRAIG VAUGHAN
Smoke Detectors 3/18/2026 Approved CRAIG VAUGHAN
Final 4/14/2026 Corrections Issued CRAIG VAUGHAN
Final 4/20/2026 OK to Issue CofO CRAIG VAUGHAN