16844 S MERIT AVE 90247

Certificate Information: 16844 S MERIT AVE 90247

Application / Permit
23014-10000-01552
Plan Check / Job No.
B23LA07343
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Addition to (E) SFD to create FAMILY ROOM and COVERED PATIO. All work per Engineered plans.
Permit Issued
Issued on 10/17/2023
Issuing Office
Valley
Current Status
CofO Issued on 5/2/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/20/2023 APPLICANT
Assigned to Plan Check Engineer 4/24/2023 MICHAEL LANZONE
Corrections Issued 4/27/2023 MICHAEL LANZONE
Building Plans Picked Up 5/1/2023 APPLICANT
Applicant returned to address corrections 8/17/2023 DANIEL SMILEY
Plan Check Approved 8/22/2023 DANIEL SANJUAN
Issued 10/17/2023 APPLICANT
CofO in Progress 5/2/2024 JAMES CHAVEZ
Permit Finaled 5/2/2024 ANSON MAGLASANG
CofO Issued 5/2/2024 ANSON MAGLASANG
Permit Finaled 5/2/2024 ANSON MAGLASANG

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/30/2023 HUGO LOPEZ
Roof/Waste drainage to street Cleared 5/30/2023 HUGO LOPEZ

Contact Information

Contractor Smart Construction Consultants Inc; Lic. No.: 1040768-B 30700 RUSSELL RANCH RD_#250      WESTLAKE VILLAGE, CA 91362
Engineer Cooke,, Conway Cecil; Lic. No.: S5524 34658 LINDA ROSEA RD      TEMECULA, CA 92592

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 11/8/2023 Conditional Approval JAMES CHAVEZ
Footing/Foundation/Slab 11/9/2023 Partial Approval JAMES CHAVEZ
Deputy Drilled-In Anchors 11/30/2023 Conditional Approval JAMES CHAVEZ
Footing/Foundation/Slab 11/30/2023 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 12/18/2023 Corrections Issued JOHN KLARIN
ELECTRICAL-Rough 12/18/2023 Not Ready for Inspection JOHN KLARIN
Green Building Rough 12/18/2023 Not Ready for Inspection JOHN KLARIN
MERV13>=Rough 12/18/2023 Not Ready for Inspection JOHN KLARIN
Deputy Wood Construction 1/9/2024 Conditional Approval JAMES CHAVEZ
ELECTRICAL-Rough 1/9/2024 Corrections Issued JAMES CHAVEZ
Floor/Roof Diaphrgm/Shear Wall 1/9/2024 Partial Approval JAMES CHAVEZ
Green Building Rough 1/9/2024 Not Ready for Inspection JAMES CHAVEZ
MERV13>=Rough 1/9/2024 Approved JAMES CHAVEZ
Interior/Exterior Lathing 1/12/2024 Approved JOHN KLARIN
Insulation 1/16/2024 Approved JAMES CHAVEZ
Drywall Nailing 1/18/2024 Approved JAMES CHAVEZ
Green Building Rough 1/18/2024 Approved JAMES CHAVEZ
BUILDING-Rough-Frame 4/3/2024 Approved JAMES CHAVEZ
ELECTRICAL-Final 4/3/2024 Approved JAMES CHAVEZ
Final 4/3/2024 Corrections Issued JAMES CHAVEZ
Green Building Final 4/3/2024 Approved JAMES CHAVEZ
HVAC-Final 4/3/2024 Approved JAMES CHAVEZ
MERV13>=Final 4/3/2024 Approved JAMES CHAVEZ
SGSOV-Seismic Gas S/O Valve 4/3/2024 SGSOV Not Ready JAMES CHAVEZ
Service/Power Release 4/3/2024 Not Ready for Inspection JAMES CHAVEZ
Smoke Detectors 4/3/2024 Not Ready for Inspection JAMES CHAVEZ
ELECTRICAL-Final 5/1/2024 Approved JAMES CHAVEZ
Final 5/1/2024 OK to Issue CofO JAMES CHAVEZ
HVAC-Final 5/1/2024 Approved JAMES CHAVEZ
SGSOV-Seismic Gas S/O Valve 5/1/2024 SGSOV Approved JAMES CHAVEZ
Smoke Detectors 5/1/2024 Approved JAMES CHAVEZ