4336 N LACLEDE AVE 90039

Certificate Information: 4336 N LACLEDE AVE 90039

Application / Permit
23014-10000-01547
Plan Check / Job No.
B23LA07288
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION OF (N) BEDROOM, (2) BATHROOMS & EXPAND (E) BEDROOMS (IRR 46'-9" X 32') & (N) PATIO COVER (8' X 4'-6") TO (E) 1-STORY SFD; INTERIOR REMODEL **eplan**
Permit Issued
Issued on 6/15/2023
Issuing Office
Current Status
CofO Issued on 3/21/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/20/2023 APPLICANT
Assigned to Plan Check Engineer 4/27/2023 NILOOFAR MEHRAIN
Corrections Issued 4/29/2023 NILOOFAR MEHRAIN
Quality Review Completed 5/2/2023 STEVEN KIM
Plan Check Approved 6/14/2023 NILOOFAR MEHRAIN
Issued 6/15/2023 APPLICANT
CofO in Progress 3/19/2025 NICHOLAS LOPEZ
Permit Finaled 3/21/2025 DEROLD HAUFF
CofO Issued 3/21/2025 DEROLD HAUFF
Permit Finaled 3/21/2025 DEROLD HAUFF

Permit Application Clearance Information

ZI Cleared 5/12/2023 ASHLEY RODARTE
Low Impact Development (LID) Cleared 6/6/2023 ROGELIO CORTES
Roof/Waste drainage to street Cleared 6/7/2023 HUGO LOPEZ
Eng Process Fee Ord 176,300 Cleared 6/8/2023 TREVOR QUAN
Sewer availability Cleared 6/8/2023 TREVOR QUAN

Contact Information

Contractor Bpc Development Inc; Lic. No.: 1059885-B       ,
Contractor Builder Point Construction; Lic. No.: 1059885-B       ,
Engineer Salto,, Alvaro; Lic. No.: C83859 2543 E NORMAN AVE      WEST COVINA, CA 91791

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/10/2023 Conditional Approval HAMIK HARTOUNIAN
Pre-Inspection 8/22/2023 Corrections Issued HAMIK HARTOUNIAN
Special/Order Compliance 8/22/2023 Partial Inspection RONNIE MINDANAO
Excavation/Setback/Form/Re-Bar 10/5/2023 Corrections Issued HAMIK HARTOUNIAN
Footing/Foundation/Slab 12/11/2023 Approved HAMIK HARTOUNIAN
Underground Mechanical 1/11/2024 Corrections Issued HAMIK HARTOUNIAN
Insulation 1/18/2024 Approved HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 1/24/2024 Partial Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 3/8/2024 Partial Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 4/2/2024 Not Ready for Inspection HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 4/2/2024 Corrections Issued HAMIK HARTOUNIAN
ELECTRICAL-Rough 5/15/2024 Approved THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 5/15/2024 Partial Approval THOMAS LOGRASSO
PLUMBING-Rough 5/15/2024 Approved THOMAS LOGRASSO
HVAC-Rough 5/24/2024 Corrections Issued THOMAS LOGRASSO
BUILDING-Rough-Frame 6/5/2024 Approved THOMAS LOGRASSO
HVAC-Rough 6/5/2024 Approved THOMAS LOGRASSO
Insulation 6/18/2024 Approved JOSEPH MCGARRY
Drywall Nailing 6/27/2024 Approved CHARLES BOGHOSKHAN
Interior/Exterior Lathing 7/22/2024 Approved LILIANA PORTILLO
HVAC-Final 12/26/2024 Corrections Issued ALIZAH MAYAGOITIA
HVAC-Final 1/10/2025 Approved WILLIAM SIERRA
PLUMBING-Final 1/14/2025 Corrections Issued THOMAS LOGRASSO
ELECTRICAL-Final 1/15/2025 Corrections Issued THOMAS LOGRASSO
ELECTRICAL-Final 1/27/2025 Not Ready for Inspection THOMAS LOGRASSO
Gas Test 1/28/2025 Approved THOMAS LOGRASSO
PLUMBING-Final 1/28/2025 Approved THOMAS LOGRASSO
Final 2/5/2025 Corrections Issued THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 2/5/2025 SGSOV Approved THOMAS LOGRASSO
Smoke Detectors 2/5/2025 Approved THOMAS LOGRASSO
ELECTRICAL-Final 2/14/2025 Approved THOMAS LOGRASSO
Final 2/14/2025 Not Ready for Inspection THOMAS LOGRASSO
Service/Power Release 2/14/2025 Approved THOMAS LOGRASSO
Special/Order Compliance 3/18/2025 Partial Approval NICHOLAS LOPEZ
Final 3/19/2025 OK to Issue CofO NICHOLAS LOPEZ